Bachman Park Presentation
BACHMAN PARK REHABILITATION PROJECT
Town Council Meeting
December 19, 2017
1
Project Budget $540,000
60% General Funds/40% CDBG Grant Funds (ADA park pathways)
Community Meeting on 11/16/2017
December Parks Commission Mtg.
BACKGROUND
BACHMAN PARK
2
RECOMMENDED PROJECT DESIGN SCOPE
BACHMAN PARK
ADA Pathway Upgrades/New Light Poles
Bachman Sidewalk/Pathway
High benches/Trash cans
Fix walls/Landscaping
3
Resurface/Restripe Court
Provide New Water Fountain
Build ADA Path to Basketball Courts
BACHMAN PARK
Additive Scope
4
Begin Project Design
Return to Council in Feb. with Final Design
Bid/Award Contracts in February/March
Spring 2018 Construction
BACHMAN PARK
NEXT STEPS
5