Staff Presentation (2)
ALMOND GROVE PHASE II UPDATE
Town Council Meeting
December 20, 2016
1
Trees
Ramps
Utilities Upgrades/Project Phasing
ALMOND GROVE PHASE II UPDATE:
2
Established Goals
Goal Achievement
TREES
AG II UPDATE
3
TREES
AG II UPDATE
Examples of Replacements
Nuisance Tree -
Sweet Gum
In Decline
Damage to Curb/Sidewalk
Internal Rot
4
AG II UPDATE
TREES – New and Replacement
Chinese Pistache
5
AG II UPDATE
TREES – New and Replacement
Eastern Red Bud
6
AG II UPDATE
TREES – New and Replacement
Maidenhair
7
AG II UPDATE
TREES – New and Replacement
Crape Myrtle
8
AG II UPDATE
TREES – New and Replacement
London Plane
9
7 Approved Types
Design Direction:
“Build Flared Ramps where Room”
RAMPS
AG II UPDATE
Curbed Ramps
Flared Ramps
10
Utilities Need Work
Staging/ Schedule
Contractor Proposed Schedule
Town Approval Required
2.5 – 3 Streets per year
Fully Complete in 3 Years
AG II UPDATE
UTILITY/PROJECT STAGING
11
Design Completion – January 2017
Council PSE Approval – February 2017
Award of Bid – April 2017
Construction Start (1st Yr) – May 2017
Const. Closeout(1st Yr) – Dec. 2017
AG II UPDATE
NEXT STEPS
12
AG II UPDATE
QUESTIONS