Staff ReportONj 11 COUNCIL AGENDA REPORT DATE: JANUARY 7, 2016 TO: MAYOR AND TOWN COUNCIL FROM: LAUREL PREVETTI, TOWN MANAGER MEETING DATE: 01/19/16 ITEM NO: 5 SUBJECT: PPW JOB NO. 15-811-9901 AND 15-811-9903 — FY 2015/16 ANNUAL STREET REPAIR AND RESURFACING PROJECT AND PAVEMENT REHABILITATION - CRACK SEAL 811-9901 AND 811-9903 A. APPROVE THE REVISED PLANS AND SPECIFICATIONS FOR THE ANNUAL STREET REPAIR AND RESURFACING AND PAVEMENT REHABILITATION — CRACK SEAL PROJECT AND AUTHORIZE THE TOWN TO ADVERTISE THE PROJECT FOR BID. B. AUTHORIZE THE TOWN MANAGER TO AWARD AND EXECUTE A CONSTRUCTION AGREEMENT IN AN AMOUNT NOT TO EXCEED THE AVAILABLE BUDGETED AMOUNT OF $2,232,782, WHICH INCLUDES A 15 PERCENT CONTINGENCY. RECOMMENDATION: Approve the revised plans and specifications for the Annual Street Repair and Resurfacing and Pavement Rehabilitation — Crack Seal Project and authorize the Town to advertise the project for bid. 2. Authorize the Town Manager to award and execute a construction agreement in an amount not to exceed the available budgeted amount of $2,232,782, which includes a 15 percent contingency. BACKGROUND: The Town's adopted FY 2015/16 — 2019/20 Capital Improvement Program (CIP) Budget designates funding for the Town's Street Repair and Resurfacing Program and Pavement Rehabilitation — Crack Seal. PREPARED BY: MATT MORLEY DIRECTOR OF PARKS AND PUBLIC WORKS Reviewed by: Assistant Town Manager ! own Attorney Finance PAGE 2 MAYOR AND TOWN COUNCIL SUBJECT: PPW JOB NO. 15-811-9901 AND 15-811-9903 — FY 2015/16 ANNUAL STREET REPAIR AND RESURFACING PROJECT AND PAVEMENT REHABILITATION - CRACK SEAL 811-9901 AND 811-9903 JANUARY 7, 2016 BACKGROUND (cont'd): This is a recurring annual project for street resurfacing activities throughout the Town to enhance vehicular safety and maintain the roadway infrastructure in Los Gatos. Preventive maintenance programs such as this are essential to managing the life cycle costs associated with Town infrastructure. Preventive maintenance activities extend the life of the streets, reducing the frequency of much more involved and much more costly reconstruction. At the June 16, 2015 Town Council meeting, the Town Council approved a Capital Improvement Program budget for FY 2015/16. In conjunction with the capital budget discussion, Council approved a project scope and budget for the FY 2014/15 Annual Street Repair and Resurfacing and Pavement Rehabilitation — Crack Seal Project as provided for in the project's June 16, 2015 Town Council report. Following Council's authorization for staff to bid and award the project, staff developed the plans and specifications to meet the scope and budget and advertised the project for bid. The list of streets in this project are included as Attachment 1. Bids for the revised plans and specifications were opened on July 17, 2015. The bids received exceeded the Council's approved budget allocation of $900,000. Reasons for the high bids included a robust economy with high demand for available contractors and timing of the bid, as interested contractors had already filled their summer construction schedules, lowering interest in the project. Staff returned to Council at the August 4, 2015 Town Council meeting requesting Council reject all bids and noting staff would return to Council in late fall or early winter with a request to rebid the project with the goal of procuring more favorable bid results. Council authorized staff to reject all bids. DISCUSSION: The streets incorporated into this project were developed from the street maintenance list provided to Council at the June 2, 2015 Town Council meeting (Attachment 1). This street list was created by the Town's Streetsaver Pavement Management Program, as well as through visual verification surveys by Town staff. Streetsaver makes recommendations on streets for inclusion based on the amount of funds available and how those funds can be utilized to improve streets. At times, Streetsaver identifies streets for maintenance to prevent those streets from deteriorating to a point where more expensive maintenance is required. This means streets in poorer condition (lower Pavement Condition Index or PCI) may not receive maintenance as extending the timeline on those streets does not create significantly greater expense. The visual verification provides the physical review to ensure staff agrees with the computer generated list. In addition, several streets identified by the Town's street maintenance crew as high priority streets are included on the new recommended project list. The revised list combining staff recommended streets with a modified Streetsaver list is provided as Attachment 2. These are the streets that will receive maintenance under this project. PAGE MAYOR AND TOWN COUNCIL SUBJECT: PPW JOB NO. 15-811-9901 AND 15-811-9903 — FY 2015/16 ANNUAL STREET REPAIR AND RESURFACING PROJECT AND PAVEMENT REHABILITATION - CRACK SEAL 811-9901 AND 811-9903 JANUARY 7, 2016 DISCUSSION (cont'd): The need for pavement maintenance and rehabilitation work on the Town's roadway system exceeds the amount of available resources. In order to maximize the use of Town resources, staff recommends the use of a Rubberized Asphalt Concrete (RAC) cape seal process as an alternative to the more conventional Asphalt Concrete (AC) overlay. The base material is made from recycled rubber, which consists of ground up or granulated rubber particles derived from tires. The RAC cape seal process is the application of a rubber chip seal followed by an application of a slurry seal or microsurfacing for final surfacing which results in a thin pavement surfacing that provides improved resistance to reflective cracking (old cracking that radiates to a new surface) and seals the street to prevent damaging water intrusion. Use of RAC provides significant cost savings when compared to conventional overlay strategies. This application has a life expectancy of approximately 8-10 years. The Town has successfully resurfaced streets in many neighborhoods over the past few years with RAC and found this resurfacing approach to be cost effective with very good results, e.g., sections of University Avenue, Wedgewood Avenue, and Roberts Road. In addition to the previous $900,000 allocated to the project by Council from the FY 14-15 Street Maintenance funds, staff is also recommending allocation of FYI 5-16 Annual Street Repair and Resurfacing and Pavement Rehabilitation — Crack Seal funds towards the project for a total project allocation of $2,232,782 (total funding from the budget minus $900,000 set aside for Almond Grove). The engineer's estimate for this project is $2,219,644, which includes a 15% contingency. Staff is including an additive alternate for additional pavement digout (pothole) repairs for an additional $117,000, to be used for miscellaneous pothole repairs throughout the Town. This additive alternate will only be awarded if the base bid plus the additive alternate low bid come within the total street allocation dollars of $2,232,782. Plans and specifications for this project are complete and will be available for review on the Town website at www.LosGatosCA. ovg /CIP and at the Parks and Public Works Engineering Department the Friday before the Town Council meeting. CONCLUSION: 1. Approve the revised plans and specifications for the Annual Street Repair and Resurfacing and Pavement Rehabilitation — Crack Seal Project and authorize the Town to advertise the project for bid. 2. ,Authorize the Town Manager to award and execute a construction agreement in an amount not to exceed the available budgeted amount of $2,232,782, which is a 15 percent contingency. PAGE 4 MAYOR AND TOWN COUNCIL SUBJECT: PPW JOB NO. 15-811-9901 AND 15-811-9903 — FY 2015/16 ANNUAL STREET REPAIR AND RESURFACING PROJECT AND PAVEMENT REHABILITATION - CRACK SEAL 811-9901 AND 811-9903 JANUARY 7, 2016 COORDINATION: This project has been coordinated with the Finance Department. ENVIRONMENTAL ASSESSMENT: This is a project as defined under CEQA and is Categorically Exempt [Section 15301(c) Existing streets, sidewalks, trails and similar facilities]. A Notice of Exemption has been filed. FISCAL IMPACT: There are sufficient funds available for these projects through the Town's adopted FY 2015/16 — 2019/20 Capital Improvement Program Budget as demonstrated in the fiscal table below. }v i - STREET' REPAIR AND RESURFACINC/ PAVEWNT RERABILITATION -CRACK SEAL ro � PROJECT 811-9901/ PROJECT 811-9903 Carryforward Adopted Available Expended/ Total Amount Budget Appropriation Encumbered AiWWe Contract FY2015-2016 FY2014/15 FY2015/16 IFY2015/16 FY2015/16 Balance Amount 811-9901 Street Repair and Resurfacing $ 1,550,456 $ 1,125,000 $ 2,675,456 ; $ 31,752 $ 2,643,704 $ 1,743,704 811-9903 Pavement Rehabilitation - Crack Seal $ 329,078 $ 160,000 $ 489,078 $ $ 489,078 $ 489,078 TOTALS $ 1,879,534 $ 1,285,000 $ 3,164,534 $ 31,752 $ 3,132,782 $ 2,232,782 *This project was presented to Council as part of the Capital Improvement Program. A portion ($900,000) of the actual funding for this project is being held pendi ig resolution of fandng needs for the Almond Grove Street Reconstruction project. TOTAL EXPENDITURES BYCATEGORY(Engineer's Estimate): Construction $ 1,930,125 Contingency- 15% $ 289,519 TOTALS $ 2,219,644 Attachments: 1. FY 14/15 Street Resurfacing List 2. FY 15/16 Annual Street Resurfacing List FY1445 Streal R"Urfacing List Legend: RC Rubber Cape Seal S Starry Seal JIMI Crack Fnlep MS M¢roaurface ^m I ou ATTACHMENT 1 Area Street From To Tyta (RC, S. YS) I lFoster Roatl.bhnson Erb of Town Limit I RC Moran Ave Erb Town Lanes RC Moran Wa Moran Ave C-na RC 2 Mo opera CI Moran Ave Eno RC Oka Lane Moran Ave End RC Oka Road Lark Naw sectbn RC Paseo Laura Moran Ave Entl RC Alberto W 9 End RC 3 BOA VI9ta Ave 9 End RC Bella VISta CI Wis Visla Ave Ertl S Los Gatos -Saratoga Rd (Hwy 9) Attend Los Galos Blvd RC 4 Arbraws Town Lknn N. Santa Cruz Ave RC Ashlar Ave San Sema N. Santa Cruz Ave Rc FancherG San Bersb End RC Man sa Ave N. Santa Cruz Ave Sen It r to RC me sa cl Sen Benib EW RC Monterey Ave 9 Thuaton RC Morn orae SI 9 Andrews SI RC Give Street San genas N. Santa Cruz Ave RC Ban Benib 9 Margost, RC San Mateo Ave San Sento N Same Cruz Ave RC Thurston Street San Benno N. Santa Cha Ave RC 5 IShOM Road Isnannon fOld 13basom lax Rd I RC anis W C ss Town Limits RC ester Ct Fonestx Rd Erb RC S ester Rd rKemed Kenned Rd End RC rod CI Kennad Rd End RC Rd St Rtl T of lM H9I RCwr ut IFnnrosterfirl Erb qC Alla He' hN G Lona Alta Ave End RC Broadwa Enlenslon W Main S1 End S Mon Ave Broadwg End RC Cross W Johrbeon Ave Lana Ana Ave RC C saw . S St Pnvate RC Glen Ri Emnsion o3 of Nicnas Mctlokon End S Johnson Ave Los Gatos Blvo St RC 7 Johnson Habw Johnson Ave End RC Loma Alta Ave Los Gatos BNd C ens W RC Los Gatos BNd pleasant SI Loma Aqa Ave MS Los Gatos SNtl Loma Alts Ave Johnson Ave RC E Mem St East abe Of 17 Pleasant St MS Montebello W W Mem St End S Shannon Rd Los Gabs SW Hicks Rd RC les Ave Lana Alla Ave Vista Del Mar RC Surd Ave Foster Rd EndI RC Alla In a CI Santa Rosa U Erd RC Auzerars G Santa Ross Dr End RC a Cdorado C' Santa Rosa d bbd RC Madera ISOMa Rosa Dr Erb RC Santa Rosa Dr jShannon Rd End S Stena Azule a Santa Rosa p End/Fawn Luntts RC Legend: RC Rubber Cape Seal S Starry Seal JIMI Crack Fnlep MS M¢roaurface ^m I ou ATTACHMENT 1 FY 15-16 ANNUAL STREET RESURFACING LIST Area Street From To Type (RC, MS) I Mullen Ave University Ave End RC Mozart Ave End Town Limits RC Mozart Wy Mozart Ave End RC Molonera Ct Mozart Ave End RC 2 Oka Lane Mozart Ave End RC Oka Road Lark Ave New section RC Paseo Laura Mozart Ave End RC Amanda Ln Shannon End RC 3 Shannon Rd Los Gatos Blvd Hicks Rd RC Short Rd Shannon Rd Old Blossom Hill Rd RC Towne Terrace University Ave Milbrae Ln RC Avery Ln Towne Terrace University Ave RC 4 Rushmore Ln Towne Terrace Riviera Dr RC Milbrae Ln Towne Terrace Riviera Dr RC Alberto Wy Hwy 9 End RC 5 Bella Vista Ave Hwy 9 End RC 6 Los Gatos -Saratoga Rd (Hwy 9) Alberto Wy Los Gatos Blvd MS Forrester Ct Forrester Rd End RC Forrester Rd Kennedy Rd End RC 7 Kennedy Ct Kennedy Rd End RC Kennedy Rd Varies Vanes RC Leotar Ct Forrester Rd End RC Cross Wy Johnson Ave Loma Alta Ave RC Cypress Wy Spring St Private RC Eugenia Wy Cypress Wy Town Limits RC S Blackberry Hill Rd Cypress Wy County RC Foster Rd Johnson Ave End of Town Limit RC Johnson Hollow Johnson Ave jEnd RC Sund Ave Foster Rd End RC TYPE RC Asphalt Rubber Cape Seal MS Asphalt Rubber Chip Seal with Microsurfacing ATTACHMENT 2