Development Impact Fees Status ReportDATE: TO: FROM: COUNCIL AGENDA REPORT DECEMBER 8, 2014 MAYOR AND TOWN COUNCIL - GREG LARSON, TOWN MANAGER MEETING DATE: 12/16/14 ITEM NO: S SUBJECT: ACCEPT FY 2013/14 STATUS REPORT ON RECEIPT AND USE OF DEVELOPMENT IMPACT FEES RECOMMENDATION: Accept FY 2013/14 status report on receipt and use of development impact fees. BACKGROUND: In order to ensure that mitigation fees associated with development are spent in a timely manner and on projects for which they were being collected, the State Legislature passed a bill known as AB 1600 (The Mitigation Fee Act). This bill applies to developer fees which were increased or imposed on or after January 1, 1989. The Mitigation Fee Act (California Government Code, § 66000 et seq.) requires local agencies that impose development impact fees to present an annual, consolidated report showing the receipt and use of those fees. The Annual Status Report (Attachment 1) must be reviewed by Council within 180 days after the close of the fiscal year represented. The Town collects three development impact fees that meet the AB 1600 reporting requirement, the Traffic Impact Mitigation Fee, Below- Market Priced Housing Program In -Lieu Fees, and the Construction Activity Impact Fee. Separate balances exist for each of these fees either as individual accounts or in the case of Traffic Impact Mitigation Fees, separate funds. As of June 30, 2014 all accounts or funds with unspent balances have been credited interest revenue at the Town's current interest rate earned on its total investment portfolio. DISCUSSION: AB 1600 Requires that a status report be prepared annually which must include the following: • A brief description of the fee and the fund into which the fee was deposited; PREPARED BY: STEP . C NWAY Administrative Services and Finance Director Reviewed by: 1.P Assistant Town Manager fil d�jown Attorney Finance N:\MGR\AdminWorkFiles\2014 Council Reports\Dec 16 \12 -16 -14 AB 1600 2014 Report.doc PAGE 2 MAYOR AND TOWN COUNCIL SUBJECT: ACCEPT FY 2013/14 STATUS REPORT ON RECEIPT AND USE OF DEVELOPMENT IMPACT FEES DECEMBER 8, 2014 DISCUSSION (cont'd): • The amount of the fee; • The associated fund's beginning and ending balances for the fiscal year; • The total amount of fees collected and interest earned; • Identification of each public improvement on which impact fees were expended and amount of expenditure on each improvement, including the total percentage of the cost of the public improvement that was funded with impact fees; • Identification of approximate date by which construction of a public improvement will begin; • Determination that sufficient funds have been collected to complete financing on an incomplete public improvement; • Description of each inter -fund transfer or loan made from the account or fund, including the public improvement on which the loaned funds will be expended, and in the case of an inter -fund loan, the date on which the loan will be repaid and the rate of interest that the account or fund will receive on the loan; and • Amount of any refunds made due to inability to expend impact fees once a determination is made that sufficient impact fees have been collected to finance a public improvement, and the improvement remains incomplete, and the City has not determined an approximate date by which construction will begin. This information is presented in the attached FY 2013 /14 Annual Status Report on Receipt and Use of Development hnpact Fees. CONCLUSION: Staff recommends Council receive and file the FY 2013/14 Annual Status Report on Receipt and Use of Development Impact Fees as required under the Mitigation Fee Act (AB 1600). ENVIRONMENTAL ASSESSMENT: The recommended action is not a project defined under CEQA, and no further action is required. Attachments: 1. FY 2013 /14 Annual Status Report on Receipt and Use of Development Impact Fees. TOWN OF LOS GATOS ANNUAL STATUS REPORT ON RECEIPT AND USE OF DEVELOPMENT IMPACT FEES JUNE 30, 2014 TRAFFIC IMPACT MITIGATION FEES FUND Beginning FundBalaace (7 /01/2013\ Some of Funds Fees Collected FY 13/14 $2 ,399,546 923,059 Interest Famed FY 13/14 52,194 Use ofDinds Capital Outlay : Wmchester/KnowIcs W inches ter /Lark intersection $423,563 21,981 Highway 9/University Intersection 6,588 Project Overhead Business Service Charge 1,679 Total Use of blinds 4453.Rl l Ending Cash Balance (7/01/2014) Pre -Flnal Audit $2,920,988 Designated Future Projects: Per FY 14/15 through 19/20 Capital Improvement Plan: Winchester lark Intersection hmprovements 237,060 Highway 9/ University Avenue hrguovments 837,122 Los Cams Boulevard /Shannon hnprovements 20,000 Los Gatos Boulevard/lark Avenue Improvements 174,299 BiussomFLll Road/Cherry Avenue Intersection hupvts 500,000 Town Digital Aehal PhotogmphyTopogmphic Map 42,000 Monument Control Network Upgrade 10,000 Intersection Safety and Traffic Flow hmprovements 40,000 Admin istration and Program Support 50,000 Total CB' and Operating Budget Commitments $1,910,481 Potential Project 13st (Estimates Only) per Unfunded List Union Avenue Widening $3,000,000 Los Gatos Boulevard Widening 1,400,000 BlossomFIdl Road Bridge W ideniag 3,500,000 $7 ,900,000 Current Funding Shortfall ($6,889,493) ATTACHMENT 1 CONSTRUCTION IMPACT ACTIVITY FEE Beginning FundBalance (7/01/2013\ $0 Source of Funds Fees Collected FY 13/14 656,881 Interest Famed FY 13/14 (Funds expended upon receipt) Total Source ofFlmth $656,881 Use of Funds Business Services Charge - Capitaloutlay : Street Repair and Resurfacing Project FY 13/14 $656,881 Ending Fund Balance (7 /01/2014) Pre -Final Audit $0 Per FY 14/15 through 19/20 Capital Improvement Plan: Street Repair and Resurfacing Project $2,525,000 Total Projects $2,525,000 Current Funding Shortfall ($2,525,000) BELOW-MARKET PRICED HOUSING PROGRAM IN-LIEU FEES Beginning FundBalance (7/01/2013) Source of Funds Fees Collected FY 13/14 Return fmm Escrow on Foreclosed Properties 13/14 $1,797,855 469,665 369,683 lutemst Famed FY 13/14 35,187 Total Source of Funds $2,672,390 Use of Funds StaffAd®inistmtion $13,000 Total Use of Funds $13,000 Ending FundBalunce (7/01 /2014) Pre -Final Audit $2,659,390 Potential Futum Projects Eareme Low laconic Housing Program $1,100,000 Reacquisition of Distressed/Foreclosed Properties 500,000 Neighborhood Housing ProgmniServices (5 Year Total) 1,100,000 Total Projects $2,700,000 Current Funding Shortfall ($40,610)