Almond Grove TC1207PresentationAlmond Grove District Concrete Street Reconstruction Update December 17, 2012 Introduction •Project History •2010 -11 CIP – Scope Clarified •2011 -2013 - Work Progress •Reconstruction of Concrete Streets Project Area Curb, Gutters, & Sidewalks Broken Curb Cracking along Curb Failed Gutter Key Issues •Construction impacts •Access limitations •Impacts on local businesses •Construction phasing to consider the on -street parking •Life Cycle Costs •Pedestrian Improvements •Traffic Calming Cost Analysis Street (10 Total) Reconstruction Option Total Cost * (Millions) Projected Maintenance Costs for 50 years (Millions) PCC Reconstruct with PCC $13.8 $5.0 PCC Reconstruct with AC $11.8 $24.0 *Total cost including construction, contingency, design, management, inspection, and admin. fees Recommendations •Accept Report •Provide Direction Regarding: •Implementation •Phasing •Community Outreach •Construction Material •Budget Preparation