14 Staff Report -Balzer Field Restroom Remodel and Expansion Project.oW 0 MEETING DATE: 1/16/07 ITEM NO: COUNCIL AGENDA REPORT ~OV•OS DATE: JANUARY 11, 2007 TO: MAYOR AND TOWN COUNCIL FROM: DEBRA J. FIGONE, TOWN MANAGER SUBJECT: PROJECT 0608 (PPW JOB NO. 04-60) BALZE FIELD RESTR001 ~'n REMODEL AND EXPANSION PROJECT A. ADOPT RESOLUTION APPROVING PLANS AND SPECIFICATIONS FOR THE BALZER FIELD RESTROOM REMODEL AND EXPANSION PROJECT (0608) AND AUTHORIZE STAFF TO ADVERTISE THE PROJECT FOR BID. B. AUTHORIZE BUDGET REVENUE ADJUSTMENTS AS FOLLOWS FOR THE PROJECT (0608): 1) $11,174 IN STATE PROPOSITION 12 PARK BOND FUNDS. 2) $13,826 FROM RESERVE FOR FUTURE YEAR'S CAPITAL PROJECTS FUND. C. AUTHORIZE $25,000 PROJECT BUDGET EXPENDITURE ADJUSTMENT FOR THE PROJECT (410-0608) AS FOLLOWS: 1) $11,174 IN STATE PROPOSITION 12 PARK BOND (FUND 410- 0608). 2) $13,826 FROM THE GENERAL FUND RESERVE FOR FUTURE YEAR'S CAPITAL PROJECTS (FUND 400-0608). RECOMMENDATION: 1. Adopt Resolution approving plans and specifications for the Balzer Field Restroom Remodel and Expansion Project (0608) and authorize staff to advertise the project for bid. 2. Authorize budget revenue adjustments as follows for the Project (0608): 1) $11,174 in State Proposition 12 Park Bond Funds. 2) $13,826 from Reserve for Future Year's Capital Projects Fund. 3. Authorize $25,000 project budget expenditure adjustment for the Project (410-0608) as follows: 1) $11,174 in State Proposition 12 Park Bond (Fund 410-0608). 2) $13,826 from the General Fund Reserve for Future Year's Capital Projects (Fund 400- 0608). PREPARED BY: KEVIN ROHANI Interim Director of Parks and Public Works NAME\COUNCIL REPORTS\06-08.balzar.field.restroom. remodel.p&s.doc Reviewed by: j Assistant Town Manager f - Town Attorney Clerk Administrator Finance Community Development 1 Fl- PAGE 2 MAYOR AND TOWN COUNCIL SUBJECT: PROJECT 0608 (PW JOB NO. 04-60) BALZER FIELD RESTROOM REMODEL AND EXPANSION PROJECT JANUARY 11, 2007 BACKGROUND: The FY 2006-07 Capital Improvement Program designates $130,000 in State Proposition 12 Parks Grant funding for the Balzer Field Restroom Remodel and Expansion. This project is consistent with the Town's goals to improve public health and safety and meets the eligibility requirements for this State grant program. The current Balzer Field restroom facilities do not provide sufficient space for public use. The existing facility has only two single-room restrooms which are in poor condition with frequent breakdowns and need for repairs. This facility is heavily used by the general public who come to the baseball field and who use Los Gatos Creek Trail. DISCUSSION: Staff determined there are three construction methods to improve Balzer Field's restroom facility: 1) a complete demolition of the existing facility and replace with a pre-fabricated unit, 2) complete demolition of the existing facility and build a new facility, or 3) expand and remodel the existing facility. After careful review of these approaches and the estimated construction costs, staff determined the most economical and practical approach is to expand and remodel the existing facility (method 0). This project will increase the square footage of the facility by 627 square feet, from 537 sq.ft. to 1,164 sq.ft.. It will remodel and expand the men's and women's restrooms, snack shack, and storage area, and will upgrade the water lines and sewer pipelines. The project's expanded storage room will provide the larger storage space needed by Little League and enable the removal of the existing metal storage unit. Little League is in support of this project and are looking forward to the construction and improvements to this facility. Staff has been in contact with them to ensure that the project does not interfere with their season's activities, and the Town will be providing portable restroom facilities during the construction period. The project expenditures include design consultant services and Town staffing, (Public Works Maintenance Workers and Building Inspector hours), both of which can be deemed as a Town match toward the Roberti Z.Berg-Harris component of the State Proposition 12 Park Bond grant. Staff recommends a $13,826 budget adjustment from the general fund reserve for capital projects to meet this match component. The remaining project costs, ($141,174), are reimbursable by the State Proposition 12 Park Bond grant. Plans and Specifications for this project are complete and will be available for review in the Clerk Department on the Friday before the Council meeting. It is anticipated that the construction project will be awarded by the Town Council in February 2007 and construction will begin in March 2007. PAGE 3 MAYOR AND TOWN COUNCIL SUBJECT: PROJECT 0608 (PW JOB NO. 04-60 BALZER FIELD RESTROOM REMODEL AND EXPANSION PROJECT JANUARY 11, 2007 CONCLUSION: It is recommended that the Council adopt the attached Resolution approving plans and specifications for the Balzer Field Restroom Remodel and Expansion project and authorize staff to advertise the project for bids. If Council approves the Balzer Field Restroom Remodel and Expansion, it will be advertised and a construction contract will be presented for Council award on February 20, 2007. ENVIRONMENTAL ASSESSMENT: This is a project as defined under CEQA but is Categorically Exempt (Section 15301e). A Notice of Exemption will not be filed. FISCAL IMPACT: The project's budget is $130,000 with funding from the State Proposition 12 Park Bond funds. The project's revised cost estimate is $155,000, an increase of $25,000 to cover replacement of a sewer line and electrical panel not included in the original building estimate and a 10% contingency. This increase is recommended to be met by an adjustment in Proposition 12 funds ($11,174) and the general fund Reserve for Future Capital Projects ($13,826). The following chart describes these adjustments: BALZER BASEBALL FIELD RESTROOM EXPANSION PROJECT Project 0608 Budget Budget Revised FY 2006/07 Fiscal Impact Funding Adjustments Budget State Proposition 12 Park Bond (Fund 410-0608) 130,000 11,174 141,174 Reserve for Future Capital Projects (Fund 400-0608) 13,826 13,826 TOTALS 130,000 25,000 155,000 TOTAL EXPENDITURES BY CATEGORY Staff Labor Materials Construction Construction Contingency (TOTALS AttarhmPntr Resolution approving plans and specifications for the Balzer Field Restroom Remodel and Expansion project. ft; RESOLUTION RESOLUTION OF THE TOWN COUNCIL OF THE TOWN OF LOS GATOS APPROVING THE PLANS AND SPECIFICATIONS FOR PPW JOB NO. 04-60 - BALZER FIELD RESTROOM REMODEL AND EXPANSION AND AUTHORIZE STAFF TO ADVERTISE THE PROJECT FOR BIDS FOR PROJECT 0608 WHEREAS, plans and specifications for the Balzer Field Restroom Remodel and Expansion have been prepared by the Town Engineer and duly filed with the Clerk Administrator; and WHEREAS, the Town Council of the Town of Los Gatos has reviewed said plans and specifications. NOW, THEREFORE, BE IT RESOLVED THAT the Town Council hereby approves the plans and specifications for the Balzer Field Restroom Remodel and Expansion project. BE IT FURTHER RESOLVED THAT the Clerk Administrator is hereby authorized and directed to advertise the Balzer Field Restroom Remodel and Expansion project for bids in the manner prescribed by the Town Municipal Code. PASSED AND ADOPTED at a regular meeting of the Town Council of the Town of Los Gatos held on the 16th of January, 2007 by the following vote: AYES: NAYS: ABSENT: ABSTAIN: SIGNED: MAYOR OF THE TOWN OF LOS GATOS LOS GATOS, CALIFORNIA ATTEST: CLERK ADMINISTRATOR OF THE TOWN OF LOS GATOS LOS GATOS, CALIFORNIA