Loading...
12 Staff Report - PPW Job No. 05-09tpW N 0 *af'a41t Yr~ X03 GASps DATE: COUNCIL; AGENDA REPORT JANUARY 4, 2007 MEETING DATE: 1/16/07 ITEM NO: TO: MAYOR AND TOWN COUNCIL r FROM: DEBRA J. FIGONE, TOWN MANAGER SUBJECT: PROJECT 410-0601 (PPW JOB NO. OS-09) AWARD OF CONSTRUCTION CONTRACT FOR COLLEGE AVENUE WALKWAY REPAIR AND RESURFACING A. ADOPT RESOLUTION DECLARING DURAN AND VENABLES, INC. TO BE THE LOWEST RESPONSIBLE BIDDER ON THE PROJECT AND AWARD A CONSTRUCTION CONTRACT IN THE AMOUNT OF $48,882. B. AUTHORIZE STAFF TO ISSUE CHANGE ORDERS TO THE CONSTRUCTION CONTRACT UP TO AN AMOUNT OF $5,000. RECOMMENDATION: A. Adopt Resolution (Attachment 1) declaring Duran and Venables, Inc. to be the lowest responsible bidder on the project and award a construction contract (Exhibit A) in the amount of $48,882. B. Authorize staff to issue change orders to the construction contract up to an amount of $5,000. BACKGROUND: The College Avenue Walkway Repair and Resurfacing Project was approved in the FY 2006-07 Capital Improvement Program to replace the asphalt sidewalk and fencing to improve pedestrian safety. Due to the poor condition of the College Avenue sidewalk and railing, pedestrians often walk on the street portion of College Avenue, which is a narrow and steep road with two-way vehicular traffic. PREPARED BY: KEVIN ROHANI Interim Director of Parks and Public Works N:T&E\COUNCIL REPORTS\05-09.college.ave.walkway.repair&resurfacing.awd.doc Reviewed by: Assistant Town Manager Town Attorney Clerk Administrator _ J Finance Community Development PAGE 2 MAYOR AND TOWN COUNCIL SUBJECT: PROJECT 410-0601 (PPW JOB NO. 05-09) AWARD OF CONSTRUCTION CONTRACT FOR COLLEGE AVENUE WALKWAY REPAIR AND RESURFACING JANUARY 4, 2007 This project replaces a damaged fence, repairs the walkway, and places a new asphalt overlay on the walkway. DISCUSSION: For projects under $100,000 construction costs, the Town's informal bid process does not require public advertising and the preparation of a set of complete plans and specifications for a project. This informal bid process allows staff to prepare a scope of work, solicit,bids from minimum of three (3) contractors and award the contract to the lowest responsible bidder. The Town uses this process for small and uncomplicated projects. Bids for the College Avenue Walkway Repair and Resurfacing Project were received on January 3, 2007. The following contractors submitted bids for this project: Duran and Venables, Inc. $48,882 - - Joseph J. Albanese, Inc. - - $70,500 Anderson Pacific Construction, Inc. $80,100 Staff has checked all of the bids received and has determined that Duran and Venables, Inc. is responsible and that its bid is responsive to the Town's informal bid process. It is recommended that the Council adopt the attached Resolution that would declare Duran and Venables, Inc. to be the lowest responsible bidder on the project and award a construction contract to this company in the amount of $48,882. CONCLUSION: Staff recommends that the Council accept the staff recommendations noted above. ENVIRONMENTAL ASSESSMENT: This is a project as defined under CEQA but is Categorically Exempt (Section 15301c). A Notice of Exemption will not be filed. FISCAL IMPACT: The FY 2006-07 Capital Improvement Program budget for the College Avenue Walkway Repair and Resurfacing Project is $77,250, funded with $75,000 in grant funds from the Transportation Development Act (TDA) Article-3 program, (administered by the Metropolitan Transportation Commission (MTC)), and $2,250 in General Funds. The Town was recently awarded additional future year grant funding from MTC in order to complete this project during this fiscal year. PAGE 3 MAYOR AND TOWN COUNCIL SUBJECT: PROJECT 410-0601 (PPW JOB NO. 05-09) AWARD OF CONSTRUCTION CONTRACT FOR COLLEGE AVENUE WALKWAY REPAIR AND RESURFACING JANUARY 4, 2007 This contract and contingency total $53,882. The balance of grant funds ($21,118) will be available in 2008-09 for future sidewalk or trails improvement projects upon project approval by MTC, and the balance of unused general funds ($2,250) will become available for future Capital Improvement Program funds. The following chart describes the project's budget: ---College-Avenue-Walkway-Repair-Project- Approved Amount Remaining Y 2006/07 Fiscal Impact Budget this Contract Balance 00-0601: General Funds 2,250 - 2,250 10-0601: TDA Article-3 g rant 75,000 53,882 21,118 0TALS 77,250 53,882 23,368 7 TOTAL EXPENDITURES BY CATEGORY: Construction 48,882 Construction Contingency 5,000 TOTALS 53,882 Attachments: Resolution declaring Duran and Venables, Inc. to be the lowest responsible bidder (with Exhibit A) Construction Contract RESOLUTION RESOLUTION OF THE TOWN COUNCIL OF THE TOWN OF LOS GATOS AWARDING A CONSTRUCTION CONTRACT TO DURAN AND VENABLES, INC. FOR PPW JOB NO. 05-09 COLLEGE AVENUE WALKWAY REPAIR AND RESURFACING PROJECT 410-0601 WHEREAS, bids were sought in conformance with State and Town law for PPW job No. 05-09 - College Avenue Walkway Repair and Resurfacing Project; and WHEREAS, Duran and Venables, Inc. submitted the lowest bid which the Town Council deems to be responsive to the Town's solicitation. NOW, THEREFORE, BE IT RESOLVED by the Town Council of the Town of Los Gatos, County of Santa Clara, State of California, that Duran and Venables, Inc. is declared to be the lowest responsible bidder for PPW Job No. 05-09 - College Avenue Walkway Repair and Resurfacing Project. BE IT FURTHER RESOLVED that the Town Manager is hereby authorized and directed to execute a construction contract (Attached as Exhibit A) for said project on behalf of the Town in the amount of $48,882. BE IT FURTHER RESOLVED that staff is authorized to execute future change orders, as necessary, up to an amount of $5,000. PASSED AND ADOPTED at a regular meeting of the Town Council of the Town of Los Gatos, California, held on the 16th day of January, 2007, by the following vote: COUNCIL MEMBERS: AYES: NAYS ABSENT: ABSTAIN: SIGNED: MAYOR OF THE TOWN OF LOS GATOS LOS GATOS, CALIFORNIA ATTEST: CLERK ADMINISTRATOR OF THE TOWN OF LOS GATOS LOS GATOS, CALIFORNIA CONTRACT THIS AGREEMENT is between the Town of Los Gatos (hereinafter referred to as "Owner") and Duran and Venables, Inc. (hereinafter referred to as "Contractor"). Owner and Contractor, for the consideration hereinafter named, agree as follows: A. SCOPE OF WORK Contractor shall furnish all materials and perform all of the work for the construction of PPW JOB No. 05-09 - College Avenue Walkway Repair and Resurfacing Project in accordance with the Contract Documents. B. CONTRACT PRICE As full compensation for furnishing all materials and for doing all the work contemplated and embraced in this Contract, also for all loss or damage arising out of the nature of the work aforesaid, or from the actions of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its acceptance by Owner, and for all risks of every description connected with the Work, also for all expenses incurred by or in consequence of the suspension or discontinuance of work, and for well and faithfully completing the Work, and the whole thereof, in the manner and according to the Contract Documents, Owner shall pay (forty eight thousand eight hundred and eighty two dollars) ($48,882.00), which shall supersede any other amount specified in the Contract Documents. C. CONTRACT DOCUMENTS All rights and obligations of Owner and Contractor are fully set forth and described in the Contract Documents. All parts of the Contract Documents are intended to be correlated so that any work called for in one part and not mentioned in the other, or vice versa, is to be executed the same as if mentioned in all said documents. D. BEGINNING OF WORK Following the execution of this Contract and the approval of bonds and insurance policies and certificates, Owner shall issue a Notice to Proceed with the Work. Commencing work or the entrance of equipment or materials on the site of the Work by Contractor before receipt of the Notice to Proceed is at the sole risk and expense of Contractor, and the Contractor shall be fully liable for any damage or injury sustained by Owner or third persons resulting therefrom. E. TIME OF COMPLETION The Work called for herein shall be fully completed within Forty (40) working days of Contractor's receipt of the Notice to Proceed. EXHIBIT A F. CORRECTION OF WORK AFTER ACCEPTANCE AND FINAL PAYMENT BY TOWN Contractor shall remedy any defects due to faulty materials and/or workmanship and pay for any damages to other work and/or existing facilities resulting therefrom which shall appear within a period of 2 years from the date of recording of the Notice of Completion. IN WITNESS WHEREOF, the parties hereto have executed this Agreement as of day of , 20 TOWN OF LOS GATOS, by: CONTRACTOR, by: Duran and Venables, 1-n.c. Debra J. Figone Town Manager RECOMMEND BY: Kevin Rohani, Interim Director Parks and Public Works Department APPROVED AS TO FORM: Orry P. Korb Town Attorney ATTEST: (Signature) (Contractor's License Number) Jackie Rose Clerk Administrator