Item 2 - Exhibit 01 - Town of Los Gatos Draft Proposed Capital Improvement Program for Fiscal Years 2020-21 - 2024-25Streets Program
EXHIBIT 1
This Page Intentionally Left Blank
STREETS PROGRAM DIRECTORY PROPOSED
C - 1
STREET RECONSTRUCTION AND RESURFACING PROJECTS PAGE
9901 Street Repair & Resurfacing C – 6
STREET REPAIRS, MAINTENANCE & SAFETY PROJECTS
9910 Traffic Calming Projects C – 12
9921 Curb, Gutter & Sidewalk Maintenance C – 14
9930 Retaining Wall Repairs C – 16
9902 Annual Street Restriping C – 18
0120 Guardrail Replacement Projects C – 20
0236 Massol Intersection Improvement C – 22
0008 Shannon Road Repair C – 24
0130 Roadside Fire Fuel Reduction C – 26
0708 Parking Lot 4 Repair & Waterproofing C – 28
STREET IMPROVEMENT PROJECTS
0705 Downtown Parking Lots Seal Coat & Restriping C – 34
0409 Hernandez Avenue Storm Drain Improvements C – 36
0218 Shannon Road Class 1 Multi-Use Path C – 38
0221 Sidewalk Improvements – Multiple Locations C – 40
0225 Utility Undergrounding Improvements C – 42
0227 Traffic Signal Modernization C – 44
0410 Bicknell Road Storm Drain Improvements C – 46
0231 Bicycle & Pedestrian Improvements C – 48
0413 Stormwater Master Plan C – 50
0414 Stormwater System – Pollution Prevention Compliance C – 52
0232 Public Arts Gateway C – 54
0242 Parking Program Implementation C – 56
0420 Annual Storm Drain Improvements C – 58
0128 Pilot School Busing C – 60
0129 ADA Transition Plan C – 62
0237 Highway 17/9 Interchange and Capacity Improvements C – 64
0235 Downtown Streetscape Revitalization C – 66
0131 E. Main Street Speed Table/Raised Crosswalk C - 68
0132 Local Road Safety Plan C -70
0239 Blossom Hill Road Traffic Study C - 72
0240 Winchester Class IV Bikeway C - 74
0133 VMT Mitigation Program C - 76
0241 Kennedy Sidewalk – LGB to Englewood C - 78
0238 Winchester Boulevard Complete Streets Final Design C - 80
BRIDGE PROJECTS
0801 Quito Road – Bridge Replacement C – 86
0803 Highway 17 Bicycle & Pedestrian Bridge – Design C – 88
PROPOSED STREETS PROGRAM
C - 2
PROPOSED STREETS PROGRAM
Street Reconstruction & Resurfacing
C - 3
PROJECT LOCATIONS
A Street Repair & Resurfacing
PROPOSED STREETS PROGRAM
Street Reconstruction & Resurfacing
C - 4
PROGRAM SECTION DIRECTORY PAGE
9901 Street Repair & Resurfacing C – 6
PROPOSED STREETS PROGRAM
Street Reconstruction & Resurfacing
C - 5
The Streets Program’s Street Reconstruction & Resurfacing section contains Capital Improvement Program projects that
resurface or repave the Town’s streets as the primary scope of work. Projects may also encompass minor components of
streetscape or street improvements; however, to be categorized in the Street Reconstruction & Resurfacing section, projects
must have pavement rehabilitation as their main purpose. Safety issues, traffic levels, the Pavement Condition Index,
available funding sources, project costs, and community impacts are all considerations in prioritizing Street Reconstruction &
Resurfacing projects in the five-year Capital Improvement Program.
This section contains an annual ongoing street rehabilitation project. The dedicated ongoing funding sources for street
repair are the Gas Tax, which was increased by SB 1, and Proposition 42, which total approximately $1.2 million for FY
2020/21. In addition, Countywide Measure B (Nov 2016) increased the sales tax by ½ cent for 30 years to fund
transportation related projects. One part of 2016 Measure B is a formulaic distribution of funds for roadway maintenance.
The Los Gatos annual allocation will be $580,633. Additional sources include grant funding, if secured, such as state
programs that focus on funding specific street categories or that funds rehabilitation of specific arterial or collector streets.
Other than the funds mentioned above, Los Gatos has limited designated funding sources for maintaining the Town’s roadway
system. The Town has a Construction Impact Fee (approximately $110,000 annually) and a Refuse Vehicle Road Impact Fee
(approximately $610,000 annually). Both of these sources recover costs for additional street and roadway repairs due to the
disproportionate amount of wear and tear caused by construction and other heavy vehicles.
STREET RECONSTRUCTION & RESURFACING PROJECTS SUMMARY
* Total FY 2019/20 Carryforward $3,305,576
Carryforward Projects
9901 Street Repair & Resurfacing 18,311,531$ 5,517,291$ 2,836,393$ 2,962,517$ 2,962,517$ 2,962,517$ 35,552,766$
New Projects
Total Street Reconstruction Projects 18,311,531$ 5,517,291$ 2,836,393$ 2,962,517$ 2,962,517$ 2,962,517$ 35,552,766$
Expended Through
2019/20
FY 2020/21 - 2024/25 CAPITAL IMPROVEMENT PROGRAM
STREET RECONSTRUCTION PROJECTS
Total
Budgeted
2020/21 Budget &
Carryfwd*
2024/25
Budget
2022/23
Budget
2023/24
Budget
2021/22
Budget
PROPOSED STREETS PROGRAM
Street Reconstruction & Resurfacing
C - 6
Town Wide
Project Name Street Repair & Resurfacing Project Number 811-9901
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description
This is an ongoing annual project for street rehabilitation throughout Town to enhance vehicle safety
and to maintain the Town’s roadway infrastructure.
Location This project occurs in various locations including Town-wide arterials, collectors, and neighborhood
streets. To meet the SB1 requirements, every year the Council adopts a resolution identifying the
streets needing repair. The final streets for the current construction season are identified at the time
the specifications are brought forward for Council approval, which generally occurs in the spring.
Project
Background
Street rehabilitation projects are identified and prioritized according to pavement quality reflected by
the Pavement Condition Index (PCI), field inspection, traffic level, and safety issues. Every three years,
the Town conducts a full assessment on the condition of the streets through a consultant who
specializes in the field. This assessment is funded through a grant from the Metropolitan
Transportation Commission. The PCI information that results from the survey feeds into a street
maintenance software program called StreetSaver. Every jurisdiction in the Bay Area uses the same
program and methodology, making it the best practice in the industry.
With the PCI information in the StreetSaver database, the program can provide future high-level
maintenance programs for the Town. The program emphasizes maintaining streets that have a good
(above 70) PCI at that level as ongoing preventive maintenance is more cost efficient than allowing
streets to reach lower PCI levels. As with many computer-generated reports, the output requires some
validation and adjustment. Staff conducts this element of the work through field observations and
consideration of project proximity, all with an eye towards maximizing the value to the Town. The
resulting list, sized to the available budget, creates the annual list of streets for this project.
Streets in good condition should be maintained with slurry seals. Streets in worse condition can often
be treated with a rubber cape seal, which is a cost effective solution for these streets, and is especially
suited for residential streets and lower speed collector streets. For arterial streets with a lower PCI, an
asphalt overlay is often the preferred solution with the best return on investment over time. Costs are
much higher for this approach. Streets in the poor condition category often need to be reconstructed.
Reconstruction is the highest cost solution for fixing streets. The Town has focused its resources on
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Reconstruction & Resurfacing
C - 7
arterials and collector streets and has used asphalt overlays, rubber cape seal and slurry seal.
Residential streets are typically treated with rubber cape seal and slurry seal.
The dedicated ongoing funding sources for street repair are the Gas Tax, which was increased by SB 1,
and Proposition 42, which total approximately $1,200,000 for FY 2020/21.
In November 2016, voters passed Countywide Measure B. This Measure increased the sales tax by ½
cent for 30 years to fund transportation related projects. One part of 2016 Measure B is a formulaic
distribution of funds for roadway maintenance. The Los Gatos annual allocation is $580,633.
As part of a voter-approved measure from 2010, the Santa Clara Valley Transportation Agency (VTA)
assesses a $10 per vehicle registration surcharge to repair and rehabilitate streets. Eighty percent of
the revenues collected by the VTA are returned to the local municipality in which they were generated.
The remaining twenty percent is used for regional and County-wide projects. This funding source is
expected to generate approximately $180,000 annually for Los Gatos, which will be used for street
rehabilitation Town-wide.
Other than the annual revenues mentioned above, Los Gatos has limited designated funding sources
for maintaining the Town’s roadway system. The Town has a Construction Impact Fee (approximately
$110,000 annually) and a Refuse Vehicle Road Impact Fee (approximately $610,000 annually). Both of
these sources recover costs for additional street and roadway repairs due to the disproportionate
amount of wear and tear caused by construction and other heavy vehicles.
Operating
Budget Impacts
Conducting preventive maintenance on the Town’s roadways extends the life of the streets and
reduces the need for extensive reconstruction in the future, reducing staff time spent on road
maintenance. Engineering staff time for project design and oversight is addressed in the FY 2020/21
Operating Budget.
PROPOSED STREETS PROGRAM
Street Reconstruction & Resurfacing
C - 8
Project
Components &
Estimated
Timeline
Fall 2020 Design Prepare plans and specifications
Winter 2021 Bid Process Council approves plans and authorizes bidding the project
Summer 2021 Construction Council awards the contract and construction process begins
Fall 2021 Completion Project completed
Senate Bill 1 (2017-2018, Beall) Road Repair and Accountability Act project list:
Location Description Scheduled
Completion
Estimated
Useful Life
Winchester from Lark to Santa Cruz Placement of rubber cape seal or overlay to
maintain pavement surface. These are arterial
roads and are critical for transit needs in the
Town.
Fall 2021 10 - 25
years
Union Avenue from Blossom Hill Road to
Los Gatos-Almaden Road
Placement of rubber cape seal or overlay to
maintain pavement surface. This is an arterial
road and is critical for transit needs in the Town.
Fall 2022 10 - 25
years
Quito Road from Bicknell to Woodbank
Placement of rubber cape seal or overlay to
maintain pavement surface. This is an arterial
road and is critical for transit needs in the Town.
Fall 2023 10 - 25
years
Santa Cruz Avenue from Blossom Hill
Road to Highway 9
Placement of rubber cape seal or overlay to
maintain pavement surface. This is a collector
road and is critical for transit needs in the Town.
Fall 2024 10 - 25
years
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Vehicle License Fee - 2010 Measure B 1,173,355$ 8,185$ 255,088$ 180,000$ 435,088$ 180,000$ 180,000$ 180,000$ 180,000$ 2,336,628$
VTA Allocation - 2016 Measure B - 1,507,338 234,651 580,663 815,314 580,663 580,663 580,663 580,663 4,645,304
Other GFAR 6,954,529 (1,013,825) 2,815,837 240,998 3,056,835 865,676 991,800 991,800 991,800 12,838,615
Total GFAR 8,127,884$ 501,698$ 3,305,576$ 1,001,661$ 4,307,237$ 1,626,339$ 1,752,463$ 1,752,463$ 1,752,463$ 19,820,547$
GAS TAX & PROP 42
Road Maintenance and Rehabilitation Account (RMRA) -$ 570,895$ -$ 585,265$ 585,265$ 585,265$ 585,265$ 585,265$ 585,265$ 3,497,220$
Other Gas Tax & Prop 42 7,880,666 1,230,387 - 624,789 624,789 624,789 624,789 624,789 624,789 12,234,999
TOTAL GAS TAX & PROP 42 7,880,666$ 1,801,282$ -$ 1,210,054$ 1,210,054$ 1,210,054$ 1,210,054$ 1,210,054$ 1,210,054$ 15,732,219$
TOTAL SOURCE OF FUNDS 16,008,551$ 2,302,980$ 3,305,576$ 2,211,715$ 5,517,291$ 2,836,393$ 2,962,517$ 2,962,517$ 2,962,517$ 35,552,766$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 8,127,884 501,698 3,305,576 1,001,661 4,307,237 1,626,339 1,752,463 1,752,463 1,752,463 19,820,547
TOTAL GFAR 8,127,884$ 501,698$ 3,305,576$ 1,001,661$ 4,307,237$ 1,626,339$ 1,752,463$ 1,752,463$ 1,752,463$ 19,820,547$
GAS TAX & PROP 42
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 7,880,666 1,801,282 - 1,210,054 1,210,054 1,210,054 1,210,054 1,210,054 1,210,054 15,732,219
TOTAL GAS TAX & PROP 42 7,880,666$ 1,801,282$ -$ 1,210,054$ 1,210,054$ 1,210,054$ 1,210,054$ 1,210,054$ 1,210,054$ 15,732,219$
TOTAL USE OF FUNDS 16,008,551$ 2,302,980$ 3,305,576$ 2,211,715$ 5,517,291$ 2,836,393$ 2,962,517$ 2,962,517$ 2,962,517$ 35,552,766$
STREET REPAIR & RESURFACING Project 811-9901
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 9
PROJECT LOCATIONS
A Traffic Calming Projects F Massol Intersection Improvements
B Curb, Gutter, & Sidewalk Maintenance G Shannon Road Repair
C Retaining Wall Repairs H Roadside Fire Fuel Reduction
D Annual Street Restriping I Parking Lot 4 Repair & Waterproofing
E Guardrail Replacement Project
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 10
PROGRAM SECTION DIRECTORY PAGE
9910 Traffic Calming Projects C – 12
9921 Curb, Gutter, & Sidewalk Maintenance C – 14
9930 Retaining Wall Repairs C – 16
9902 Annual Street Restriping C – 18
0120 Guardrail Replacement Project C – 20
0236 Massol Intersection Improvements C – 22
0008 Shannon Road Repair C – 24
0130 Roadside Fire Fuel Reduction C - 26
0708 Parking Lot 4 Repair & Waterproofing C – 28
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 11
The Streets Program’s Street Repair, Maintenance & Safety Projects section contains Capital Improvement Program projects
that repair, maintain, or enhance safety features of the Town’s streets and parking lots as the primary scope of work. Projects
may also encompass minor components of streetscape or street improvements; however, to be categorized in this section,
street repair, maintenance, or safety enhancements must be the project’s main purpose. Safety issues, available funding
sources, project costs, and community impacts are all considerations in prioritizing Street Repair, Maintenance & Safety
projects in the five-year Capital Improvement Program.
This section contains annual ongoing projects as well as one-time projects. GFAR funding is utilized for the Traffic Calming
Projects, which are funded at $10,000 annually. The Annual Street Restriping Project is funded at $25,000 per year. The Curb,
Gutter, and Sidewalk Maintenance Project is funded at $300,000 per year. The Retaining Wall Repairs Project is typically
funded with an ongoing GFAR stream of $100,000 per year. While annual appropriations are planned for these ongoing
projects, funding adjustments may occur from year to year to align with changing priorities and schedules.
One-time projects are prioritized by safety factors, community impacts, and the availability of grant funding. GFAR funds may
also be utilized to fund a portion of grant driven projects as a grant’s local “match requirement.”
Los Gatos does not have an ongoing designated funding source for projects in this section.
STREET REPAIRS, MAINTENANCE & SAFETY PROJECTS SUMMARY
* Total FY 2019/20 Carryforward $3,413,980
Carryforward Projects
9910 Traffic Calming Projects 215,750$ 19,250$ 10,000$ 10,000$ 10,000$ 10,000$ 275,000$
9921 Curb, Gutter & Sidewalk Maintenance 2,863,403 1,667,395 300,000 300,000 300,000 300,000 5,730,798
9930 Retaining Wall Repairs 1,426,291 536,486 100,000 100,000 100,000 100,000 2,362,777
9902 Annual Street Restriping 180,228 169,772 25,000 25,000 25,000 25,000 450,000
0120 Guardrail Replacement Projects 137,191 1,072,909 - - - - 1,210,100
0125 Massol Intersection Improvements 66,833 383,167 - - - - 450,000
New Projects
0008 Shannon Road Repair - 1,500,000 - - - - 1,500,000
0130 Roadside Fire Fuel Reduction - 250,000 - - - - 250,000
0708 Parking Lot 4 Repair/Waterproofing - 250,000 - - - - 250,000
Total Maintenance & Safety Projects 4,889,696$ 5,848,980$ 435,000$ 435,000$ 435,000$ 435,000$ 12,478,676$
2022/23
Budget
2020/21 Budget &
Carryfwd*
2021/22
Budget
Total
Budgeted
2024/25
Budget
2023/24
Budget
Expended Through
2019/20
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 12
Project Name Traffic Calming Projects Project Number 812-9910
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description In accordance with the Town’s Traffic Calming Policy, this project involves conducting minor traffic
studies, developing and implementing traffic improvements, and installing roadway devices to further
enhance school pedestrian and roadway safety near high-use crosswalks.
Location In FY 2020/21, funds will be used to develop a traffic calming project for Shannon Road between Los
Gatos Boulevard and Short Road. The process begins with neighborhood meetings for staff to work
with residents to develop a temporary traffic calming plan (TTCP). Staff will then poll the residents to
determine if the devices should be installed as temporary devices. If a super majority supports the
TTCP, staff will have the proposed devices installed. Four to six months after installation, staff will
conduct another traffic study in the area to determine the effectiveness of these devices. Upon the
completion of this study, staff will poll the residents to determine if the devices should be made
permanent. If necessary, funds will be used to remove these devices.
Project
Background
In 2002, the Town implemented a Traffic Calming Policy to address and mitigate neighborhood traffic
and pedestrian safety issues, such as speeding and cut-through traffic. This program relies on residents
to bring projects forward at the neighborhood level. At the time the Policy was adopted, twelve project
areas were under review for traffic calming improvements. To date, 14 projects have been processed,
completed, or closed. Traffic calming improvements such as speed bumps, traffic circles, center
medians, and bulb-outs were installed where appropriate to slow vehicles or enhance pedestrian
safety.
Operating
Budget Impacts
Engineering staff time associated with these projects will be charged to the project as they are
identified and delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 13
Project Components
& Estimated Timeline
Summer 2020 Construct the speed hump for Massol Avenue removed by the Almond Grove
Roadway Project. Schedule, notify residents and hold Neighborhood Traffic
Calming meetings for Shannon Road.
Fall 2020 Hold Neighborhood Traffic Calming meeting(s) for Shannon Road
Winter 2020 Poll Shannon Road residents
Spring 2021 Install temporary traffic calming devices for Shannon Road
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 195,301$ 20,449$ 9,250$ 10,000$ 19,250$ 10,000$ 10,000$ 10,000$ 10,000$ 275,000$
TOTAL SOURCE OF FUNDS 195,301$ 20,449$ 9,250$ 10,000$ 19,250$ 10,000$ 10,000$ 10,000$ 10,000$ 275,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 195,301 20,449 9,250 10,000 19,250 10,000 10,000 10,000 10,000 275,000
TOTAL GFAR 195,301$ 20,449$ 9,250$ 10,000$ 19,250$ 10,000$ 10,000$ 10,000$ 10,000$ 275,000$
TOTAL USE OF FUNDS 195,301$ 20,449$ 9,250$ 10,000$ 19,250$ 10,000$ 10,000$ 10,000$ 10,000$ 275,000$
TRAFFIC CALMING PROJECTS Project 812-9910
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 14
TOWN-WIDE
Project Name Curb, Gutter, & Sidewalk Maintenance Project Number 813-9921
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This is an ongoing annual project for the repair and replacement of hazardous curbs, gutters, and
sidewalks throughout Town to enhance pedestrian and bicyclist safety and to improve water runoff
infrastructure.
Location Curb, gutter, and sidewalk repair projects occur throughout the Town based on priority needs.
Project
Background
Curb, gutter, and sidewalk improvements in public parking lots and rights-of-way have historically been
funded by the Town. The intent of this project is to keep pace with the deterioration of sidewalks and
curbs. Specific project locations are identified and prioritized based on the level of damage and
accompanying potential safety issues.
The primary source of damage to sidewalks, curbs and gutters is tree root intrusion. Most of the streets
in Town have mature trees in the planter areas between the sidewalks and curbs. These trees were
planted many years ago without consideration of root growth and its impacts to the sidewalk, curb,
and street. Over time, the tree roots cause cracks and raised concrete, leading to uneven surfaces. Staff
develops an annual plan for sidewalk repair based on the level of damage as observed and reported by
staff and residents, confirmed by staff inspection. The level of repair and maintenance performed in
any given year has been limited by available annual funding. Funds are utilized predominantly to
address locations where paving projects create a requirement for curb ramps and curb and gutter
repair.
In addition to sidewalk, curb and gutter maintenance, this project is used for installing Americans with
Disabilities Act (ADA) accessible curb ramps on Town streets as required by federal law following Town
street maintenance projects. Title II of the ADA obligates a jurisdiction to provide compliant curb ramps
whenever streets are resurfaced from one intersection to another. ADA compliance has required a
substantial portion of the annual funding allocation.
Operating
Budget Impacts
Potential trip and fall injuries and lawsuits against the Town should be reduced by eliminating
hazardous curb, gutter, and sidewalk conditions. Engineering staff time associated with these projects
will be charged to the project as it is delivered.
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 15
Project Components
& Estimated Timeline
Fall 2020 Design Project design & development
Winter 2021 Bid Process Project bidding & contract award
Spring 2021 Construction Project construction
Summer 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 2,856,864$ 6,539$ 1,367,395$ 300,000$ 1,667,395$ 300,000$ 300,000$ 300,000$ 300,000$ 5,730,798$
TOTAL SOURCE OF FUNDS 2,856,864$ 6,539$ 1,367,395$ 300,000$ 1,667,395$ 300,000$ 300,000$ 300,000$ 300,000$ 5,730,798$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 2,856,864 6,539 1,367,395 300,000 1,667,395 300,000 300,000 300,000 300,000 5,730,798
TOTAL GFAR 2,856,864$ 6,539$ 1,367,395$ 300,000$ 1,667,395$ 300,000$ 300,000$ 300,000$ 300,000$ 5,730,798$
TOTAL USE OF FUNDS 2,856,864$ 6,539$ 1,367,395$ 300,000$ 1,667,395$ 300,000$ 300,000$ 300,000$ 300,000$ 5,730,798$
CURB, GUTTER & SIDEWALK MAINTENANCE Project 813-9921
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 16
Project Name Retaining Wall Repairs Project Number 815-9930
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description The Retaining Wall Repair and Replacement Program focuses on the repair and/or replacement of
retaining walls that have become structurally deficient.
Location Retaining wall repair projects are identified throughout the Town and are prioritized in order of repair
based on safety issues, roadway impacts, retaining wall damage, and project costs.
Project
Background
Retaining walls are installed to hold a hillside from sliding and are placed alongside a street at strategic
locations where hillside erosion is anticipated. If the retaining wall fails, the street subsequently fails;
therefore, it is important to maintain the retaining walls as they are an integral part of the hillside
roadway system. Some existing retaining walls have reached the end of their serviceable life and
require replacement. Hillside locations are prioritized over smaller roadside embankments in
accordance with the potential impacts from failures.
Retaining walls are visually inspected annually; however, unanticipated weather events can quickly
erode a wall’s integrity and cause failure. Town staff continues to monitor and schedule retaining wall
installation and replacement as needed. Due to limited yearly funding for this project, projects are
typically bid every two or three years.
Operating
Budget Impacts
Once repaired, improved retaining walls reduce ongoing operating costs associated with maintenance
and emergency response. Engineering staff time associated with these projects will be charged to the
project as it is delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 17
Project
Components &
Estimated Timeline
Fall 2021 Design Project design & development
Winter 2022 Bid Process Project bidding & contract award
Summer 2022 Construction Project construction
Fall 2022 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 1,422,178$ 4,113$ 436,486$ 100,000$ 536,486$ 100,000$ 100,000$ 100,000$ 100,000$ 2,362,777$
TOTAL SOURCE OF FUNDS 1,422,178$ 4,113$ 436,486$ 100,000$ 536,486$ 100,000$ 100,000$ 100,000$ 100,000$ 2,362,777$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 1,422,178 4,113 436,486 100,000 536,486 100,000 100,000 100,000 100,000 2,362,777
TOTAL GFAR 1,422,178$ 4,113$ 436,486$ 100,000$ 536,486$ 100,000$ 100,000$ 100,000$ 100,000$ 2,362,777$
TOTAL USE OF FUNDS 1,422,178$ 4,113$ 436,486$ 100,000$ 536,486$ 100,000$ 100,000$ 100,000$ 100,000$ 2,362,777$
RETAINING WALL REPAIRS Project 815-9930
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 18
Project Name Annual Street Restriping Project Number 811-9902
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project is an annual program that restripes a portion of the Town’s streets, ensuring the safety of
vehicles and pedestrians.
Location Roadway restriping work is done at various locations throughout the Town based on conditions and
available funds.
Project
Background
The Town initiated Town-wide striping in FY 2006/07. Due to deferred striping and marking of the
Town’s public streets, any striping that had been accomplished previously was done in conjunction with
the resurfacing of specific streets in the Town’s annual street paving project.
This annual street restriping program installs new striping and marking for center lanes, bicycle lanes,
crosswalks, stop sign and signal light markings, and other roadway signage as needed. Roadway stripes
wear out due to traffic and weather which creates a safety concern. The goal is to have Town streets
that are properly striped for safe operation and use by the public.
Under this project, locations that are not scheduled for street repaving will be prioritized for restriping.
The restriping of repaved streets will continue to occur in conjunction with paving contracts.
Since FY 2007/08, the ongoing annual GFAR appropriation has been $25,000.
Operating
Budget Impacts
Engineering staff time associated with these projects will be charged to the project as the project is
delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 19
Project
Components &
Estimated Timeline
Winter 2021 Design Project Design & development
Spring 2021 Bid Process Project bidding & contract award
Summer 2021 Construction Project construction
Fall 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 180,228$ -$ 144,772$ 25,000$ 169,772$ 25,000$ 25,000$ 25,000$ 25,000$ 450,000$
TOTAL SOURCE OF FUNDS 180,228$ -$ 144,772$ 25,000$ 169,772$ 25,000$ 25,000$ 25,000$ 25,000$ 450,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 180,228 - 144,772 25,000 169,772 25,000 25,000 25,000 25,000 450,000
TOTAL GFAR 180,228$ -$ 144,772$ 25,000$ 169,772$ 25,000$ 25,000$ 25,000$ 25,000$ 450,000$
TOTAL USE OF FUNDS 180,228$ -$ 144,772$ 25,000$ 169,772$ 25,000$ 25,000$ 25,000$ 25,000$ 450,000$
ANNUAL STREET RESTRIPING Project 811-9902
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 20
Project Name
Guardrail Replacement Project Project Number 812-0120
Department
Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description The project will construct a new metal beam guardrail and replace old and damaged guardrails along
sections of Town roadways.
Location This project will take place in various locations where guardrails are present and are in need of repair.
The list of guardrails will be identified and will be brought forward to Council for approval.
Project
Background
There are many roadways throughout Town that are located near hillside areas where guardrails are
present. Guardrails are often located on narrow stretches of roadway and protect vehicles and
pedestrians from steep hillside embankments. Over the years, due to hillside erosion and years of
deferred maintenance, the guardrails have worn out and are in need of repair or replacement. Staff will
assess guardrails and determine which ones are in the most need of repair, budget permitting.
In FY 2018/19, the Town was awarded $980,100 in grant funds for additional guardrail work throughout
the Town, which is being carried forward to FY 2020/21.
Operating
Budget Impacts
Engineering staff time associated with these projects will be charged to the project as they are identified
and delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 21
Project Components
& Estimated Timeline
Winter 2020 Design Project design & development
Fall 2020 Bid Process Project bidding & contract award
Winter 2021 Construction Project construction
Spring 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 136,986$ 205$ 92,809$ -$ 92,809$ -$ -$ -$ -$ 230,000$
GRANTS & AWARDS - - 980,100 - 980,100 - - - - 980,100
TOTAL SOURCE OF FUNDS 136,986$ 205$ 1,072,909$ -$ 1,072,909$ -$ -$ -$ -$ 1,210,100$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 136,986 205 92,809 - 92,809 - - - - 230,000
TOTAL GFAR 136,986$ 205$ 92,809$ -$ 92,809$ -$ -$ -$ -$ 230,000$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 980,100 - 980,100 - - - - 980,100
TOTAL GFAR -$ -$ 980,100$ -$ 980,100$ -$ -$ -$ -$ 980,100$
TOTAL USE OF FUNDS 136,986$ 205$ 1,072,909$ -$ 1,072,909$ -$ -$ -$ -$ 1,210,100$
Project 812-0120GUARDRAIL REPLACEMENT PROJECTS
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 22
Project Name Massol Intersection Improvements
Project Number 813-0236
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will add intersection safety improvements.
Location This project will take place at the intersection of Massol Avenue and Highway 9.
Project
Background
The intersection as Massol Avenue currently has no traffic control but does have a pedestrian activated
flashing beacon that is intended to alert drivers when a pedestrian is crossing. Looking at accident
history, this intersection experiences collisions at a higher level than other uncontrolled intersections,
including a pedestrian fatality on September 1, 2017.
This project will provide green bike lanes approaching the crosswalk from both directions to alert
drivers of the changing conditions and help to reduce speeds. In addition, the project will upgrade the
existing flashing beacon to a LED rectangular rapidly flashing beacon (RRFB), which are utilized at many
of the Town’s other crosswalks. These beacons are much more intense than the existing beacon and
would greatly improve the visibility of the crosswalk for drivers. This improvement has the advantage
of improving safety while not impacting the flow of traffic.
Operating
Budget Impacts
There will be no Operating Budget impact as a result of this project. Project delivery costs for this
project are included in the CIP project’s total cost, which is approximately 12%.
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 23
Project
Components &
Estimated Timeline
Fall 2019 Design Project design & development
Spring 2020 Bid process Project bidding & contract award
Summer 2020 Construction Project construction
Winter 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 31,250$ 35,583$ 383,167$ -$ 383,167$ -$ -$ -$ -$ 450,000$
TOTAL SOURCE OF FUNDS 31,250$ 35,583$ 383,167$ -$ 383,167$ -$ -$ -$ -$ 450,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 31,250 35,583 383,167 - 383,167 - - - - 450,000
TOTAL GFAR 31,250$ 35,583$ 383,167$ -$ 383,167$ -$ -$ -$ -$ 450,000$
TOTAL USE OF FUNDS 31,250$ 35,583$ 383,167$ -$ 383,167$ -$ -$ -$ -$ 450,000$
MASSOL INTERSECTION IMPROVEMENTS Project 813-0236
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 24
Project Name Shannon Road Repair
Project Number 811-0008
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will repair the roadway on Shannon Road.
Location This project will take place on Shannon Road between Santa Rosa Drive and Diduca Way.
Project
Background
This portion of Shannon road has experienced long-term pavement cracking and settlement issues
related to the downslope portion of approximately 1,300 linear feet of the paved road along Shannon
Road between Santa Rosa Drive and Diduca Way. The section of the road was recently annexed into
the Town of Los Gatos from unincorporated Santa Clara County. Routine maintenance undertaken by
the County had typically consisted of sealing of asphalt pavement cracks and placement of additional
asphalt concrete along the settling portions of the roadway to relevel the driving surface. There is
reportedly up to 12 feet of asphalt along the outer edge of the road in some locations. Approximately
two years ago, measures were undertaken by the County to stabilize the problematic areas of the
roadway by injecting polyurethane foam below the outer half of the road embankment within the areas
of historic settlement and cracking. The road was annexed to the Town from the County shortly after
the completion of this repair. Despite the foam injection work, the road embankment has continued
to move downslope and significant pavement distress has re-developed. The settlement has caused
some of the injection pipes that were left following injection to protrude up through the pavement
surface.
Operating
Budget Impacts
Engineering staff time associated with this project will be charged to the project as they are identified
and delivered.
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 25
Project
Components &
Estimated Timeline
Fall 2020 Design Project design & development
Fall 2020 Bid process Project bidding & contract award
Spring 2021 Construction Project construction
Summer 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ 1,500,000$ 1,500,000$ -$ -$ -$ -$ 1,500,000$
TOTAL SOURCE OF FUNDS -$ -$ -$ 1,500,000$ 1,500,000$ -$ -$ -$ -$ 1,500,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 1,500,000 1,500,000 - - - - -
TOTAL GFAR -$ -$ -$ 1,500,000$ 1,500,000$ -$ -$ -$ -$ 1,500,000$
TOTAL USE OF FUNDS -$ -$ -$ 1,500,000$ 1,500,000$ -$ -$ -$ -$ 1,500,000$
SHANNON ROAD REPAIR Project 811-0008
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 26
Project Name Roadside Fire Fuel Reduction
Project Number 812-0130
Department Parks & Public Works Project Manager PPW Superintendent: Jim Harbin
Description This project will perform brush/vegetation management work along hillside roadways.
Location This project will take place on hillside roadways in Town.
Project
Background
The Town will award a contract to perform brush/vegetation management work along hillside
roadways to reduce the fuel risk in Town. These roadways are critical as ingress and egress routes in
the Town, essential for both resident evacuation and emergency first responders. Fuel reduction will
provide enhanced safety on these routes this project will benefit approximately 1,300 structures and
will involve 11 miles of roadside clearing.
Operating
Budget Impacts
Staff time associated with this project will be charged to the project as they are identified and delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 27
Project
Components &
Estimated Timeline
Fall 2020 Design Project design & development
Fall 2020 Bid process Project bidding & contract award
Spring 2021 Construction Project construction
Spring 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
TOTAL SOURCE OF FUNDS -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 250,000 250,000 - - - - 250,000
TOTAL GFAR -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
TOTAL USE OF FUNDS -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
ROADSIDE FIRE FUEL REDUCTION Project 812-0130
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 28
Project Name Parking Lot 4 Repair & Waterproofing
Project Number 817-0708
Department Parks & Public Works Project Manager PPW Superintendent: Jim Harbin
Description This project will remove and replace sections of concrete, waterproof the upper deck, and rework the
planters of Parking Lot 4.
Location This project is located at Parking Lot 4 which is located on Railroad Way between Elm Street and
Gray’s Lane
Project
Background
Parking Lot 4, which includes an underground parking garage, was constructed nearly 25 years ago and
there have not been any major infrastructure improvements to this facility since then. The concrete
deck has deteriorated to the point that has caused water leaking from the upper section to the
underground garage below. This project will replace sections of concrete, waterproof the upper deck,
and rehabilitate the planting areas.
Operating
Budget Impacts
Staff time associated with this project will be charged to the project as they are identified and delivered.
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 29
Project
Components &
Estimated Timeline
Summer 2019 Design Project design & development
Spring 2020 Bid process Project bidding & contract award
Summer 2020 Construction Project construction
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
TOTAL SOURCE OF FUNDS -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 250,000 250,000 - - - - 250,000
TOTAL GFAR -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
TOTAL USE OF FUNDS -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
PARKING LOT 4 REPAIR & WATERPROOFING Project 817-0708
PROPOSED STREETS PROGRAM
Street Repairs, Maintenance & Safety Projects
C - 30
PROPOSED STREETS PROGRAM
Street Improvements
C - 31
PROJECT LOCATIONS
A Downtown Parking Lots Seal Coat & Restriping M Annual Storm Drain Improvements
B Hernandez Avenue Storm Drain Improvements N Pilot School Busing Program
C Shannon Road Class 1 Multi-use Path O ADA Transition Plan Update
D Sidewalk Improvements – Multiple Locations P Highway 17/9 Interchange and Capacity Improvements
E Utility Undergrounding Improvements Q Downtown Streetscape Revitalization
F Traffic Signal Modernization R E. Main Street Speed Table/Raised Crosswalk
G Bicknell Road Storm Drain Improvements S Local Road Safety Plan
H Bicycle & Pedestrian Improvements T Blossom Hill Road Traffic Study
I Stormwater Master Plan U Winchester Class IV Bikeway
J Stormwater System – Pollution Prevention Compliance V VMT Mitigation Program
K Public Arts Gateway W Kennedy Sidewalk – LGB to Englewood
L Parking Program Implementation X Winchester Boulevard Complete Streets Final Design
PROPOSED STREETS PROGRAM
Street Improvements
C - 32
PROGRAM SECTION DIRECTORY PAGE
0705 Downtown Parking Lots Seal Coat & Restriping C – 34
0409 Hernandez Avenue Storm Drain Improvements C – 36
0218 Shannon Road Class 1 Multi-Use Path C – 38
0221 Sidewalk Improvements – Multiple Locations C – 40
0225 Utility Undergrounding Improvements C – 42
0227 Traffic Signal Modernization C – 44
0410 Bicknell Road Storm Drain Improvements C – 46
0231 Bicycle & Pedestrian Improvements C – 48
0413 Stormwater Master Plan C – 50
0414 Stormwater System – Pollution Prevention Compliance C – 52
2009 Public Arts Gateway C – 54
0242 Parking Program Implementation C – 56
0420 Annual Storm Drain Improvements C – 58
0128 Pilot School Busing C – 60
0129 ADA Transition Plan C – 62
0237 Highway 17/9 Interchange and Capacity Improvements C – 64
0235 Downtown Streetscape Revitalization C – 66
0131 E. Main Street Speed Table/Raised Crosswalk C – 68
0132 Local Road Safety Plan C – 70
0239 Blossom Hill Road Traffic Study C – 72
0240 Winchester Class IV Bikeway C - 74
0133 VMT Mitigation Program C – 76
0241 Kennedy Sidewalk – LGB to Englewood C - 78
0238 Winchester Boulevard Complete Streets Final Design C – 80
PROPOSED STREETS PROGRAM
Street Improvements
C - 33
The Streets Program’s Street Improvements section contains Capital Improvement Program projects that improve a roadway’s
function or structure, other than paving, as the primary scope of work. Typical Street Improvements projects include sidewalk,
curb, and gutter improvements, storm drain improvements, the undergrounding of utilities, intersection improvements,
sidewalk and median ramps, crosswalk improvements, street lighting, and retaining walls.
In this CIP, the Street Improvements section contains one-time projects and no ongoing projects. One-time Street
Improvements projects are prioritized based on safety needs, traffic levels, available funding sources, project costs, and
community impacts.
Traffic Mitigation Funds, Storm Drain Funds, and the Utility Underground Fund all provide designated funding revenue
through development fee charges for their related project categories. Los Gatos does not have a designated funding source
for other street improvements which do not fall into these categories; however, grants, in-lieu fees, CDBG funds, and
community benefit funds are utilized when available.
STREET IMPROVEMENT PROJECTS SUMMARY
* Total FY 2019/20 Carryforward $8,870,133
Unfunded Projects for future consideration
• Montebello Way Island Removal
• Blossom Hill Road & Union Avenue Improvements
• Los Gatos-Almaden Road Improvements
• Union Avenue Widening and Sidewalks
• North Santa Cruz Avenue Curb and Gutter Improvements north of Highway 9
• Sidewalk infill across from Fisher Middle School
• Downtown Parking Sign Enhancements
Carryforward Projects
0705 Downtown Parking Lots Seal Coat & Restriping 47,415$ 52,585$ -$ -$ -$ -$ 100,000$
0409 Hernandez Avenue Storm Drain Improvements 17,180 - - - - 65,000 82,180
0218 Shannon Road Class 1 Multi-use Path 69,104 1,120,200 - - - - 1,189,304
0221 Sidewalk Improvements - Multiple Locations - 60,000 - - - - 60,000
0225 Utility Undergrounding Improvements - 6,766,000 - - - - 6,766,000
0227 Traffic Signal Modernization 181,982 2,747,707 - - - - 2,929,689
0410 Bicknall Avenue Storm Drain Improvements 160,932 60,258 - - - - 221,190
0420 Annual Storm Drain Improvements 29,700 420,300 - - - - 450,000
0231 Bicycle & Pedestrian Improvements 540,783 305,745 - - - - 846,527
0413 Stormwater Master Plan 20,000 180,000 - - - - 200,000
0414 Stormwater System - Pollution Prevention Compliance 1,422 298,578 - - - - 300,000
2009 Public Art Gateway 4,500 25,004 - - - - 29,504
0128 Pilot School Busing Program 372,718 442,056 87,000 - - - 901,774
0129 ADA Transition Plan - 110,000 - - - - 110,000
0237 Highway 17/9 Interchange and Capacity Improvements - 600,000 - - - - 600,000
0235 Downtown Streetscape Revitalization - 1,972,384 - - - - 1,972,384
0238 Winchester Boulevard Complete Streets (Final Design)200,053 79,948 1,459,250 - - - 1,739,250
New Projects ``
0131 E. Main St. Speed Table/Raised Crosswalk - 169,200 - - - - 169,200
0132 Local Road Safety Plan - 100,000 - - - - 100,000
0239 Blossom Hill Road Traffic Study - 125,000 - - - - 125,000
0240 Winchester Class IV Bikeway - 982,455 - - - - 982,455
0133 VMT Mitigation Program - 250,000 - - - - 250,000
0241 Kennedy Sidewalk - LGB to Englewood - - - 1,162,390 - - 1,162,390
0242 Parking Program Implementation - 198,500 - - - - 198,500
Total Street Improvement Projects 1,645,788$ 17,065,919$ 1,546,250$ 1,162,390$ -$ 65,000$ 21,485,347$
2024/25
Budget
Expended Through
2019/20
2022/23
Budget
2021/22
Budget
STREET IMPROVEMENT PROJECTS
Total
Budgeted
2023/24
Budget
2020/21 Budget &
Carryfwd*
FY 2020/21 - 2024/25 CAPITAL IMPROVEMENT PROGRAM
PROPOSED STREETS PROGRAM
Street Improvements
C - 34
HWY
9
E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV
Project Name Downtown Parking Lots Seal Coat &
Restriping
Project Number 817-0705
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will resurface downtown parking lots by applying a seal coat and then restriping.
Location This project is located at various Town-owned parking lots in downtown Los Gatos.
Project
Background
The public parking lots in downtown Los Gatos are heavily used on a daily basis. In order to keep their
surfaces in good condition and prevent long term wear and damage, the parking lots need to be
resurfaced and restriped. This project is necessary to prevent possible drainage or broken pavement
problems in the future.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 35
Project
Components &
Estimated Timeline
Winter 2020 Preliminary Design Project design & development.
Spring 2020 Final Design Project bidding & contract award.
Summer 2020 Completion Project completion.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 24,915$ 22,500$ 52,585$ -$ 52,585 -$ -$ -$ -$ 100,000$
TOTAL SOURCE OF FUNDS 24,915$ 22,500$ 52,585$ -$ 52,585$ -$ -$ -$ -$ 100,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 24,915 22,500 52,585 - 52,585 - - - - 100,000
TOTAL GFAR 24,915$ 22,500$ 52,585$ -$ 52,585$ -$ -$ -$ -$ 100,000$
TOTAL USE OF FUNDS 24,915$ 22,500$ 52,585$ -$ 52,585$ -$ -$ -$ -$ 100,000$
DOWNTOWN PARKING LOTS SEAL COAT & RESTRIPING Project 817-0705
PROPOSED STREETS PROGRAM
Street Improvements
C - 36
Project Name Hernandez Avenue Storm Drain
Improvements
Project Number 816-0409
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will improve the Hernandez Avenue storm drain system with the installation of an
underground storm drain pipe and sidewalk above.
Location The storm drain project is located on the south side of Hernandez Avenue, between Walnut Avenue
and Wissahickon Avenue.
Project
Background
Hernandez Avenue is a hillside collector street with an incomplete sidewalk network and storm drain
systems alongside the roadway. This street averages over 1,000 vehicles per day, a normal amount
for a collector street. At previous neighborhood meetings, residents indicated an interest in having
continuous sidewalks, particularly in the area where an open storm drain exists.
This project proposes to install an underground storm drain pipe into the existing ditch and put a
concrete sidewalk, curb, and gutter system along the roadway to feed runoff water into the storm
drain pipe. This street improvement addresses several neighborhood needs, including an improved
drainage system, a safer pedestrian area, and an improved appearance of the neighborhood.
This project will be funded by the Storm Basin Fund. This project is scheduled for construction in FY
2022/23.
Operating
Budget Impacts
Ongoing operating costs would be significantly reduced as this project would eliminate the need to
clean or repair the existing open ditch. Engineering staff time associated with these projects will be
charged to the project as it is delivered in FY 2022/23.
L
O
S
G
A
T
O
S
-
S
A
R
A
T
O
G
A
R
D
HWY 17N SANTA CRUZ AVUNIVERSITY AV
PROPOSED STREETS PROGRAM
Street Improvements
C - 37
Project
Components &
Estimated Timeline
Fall 2021 Design Design project, include alternative methods and estimated
costs, and determine best outcome.
Winter 2022 Bid Process Obtain bids from licensed contractors and submit to Council
for approval.
Summer 2023 Construction Construction of storm drains and related street
improvements.
Fall 2023 Completion Project completed.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
STORM BASIN #3 17,180$ -$ -$ -$ -$ -$ -$ -$ 65,000$ 82,180$
TOTAL SOURCE OF FUNDS 17,180$ -$ -$ -$ -$ -$ -$ -$ 65,000$ 82,180$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
STORM BASIN #3
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 17,180 - - - - - - - 65,000 82,180
TOTAL STORM BASIN 17,180$ -$ -$ -$ -$ -$ -$ -$ 65,000$ 82,180$
TOTAL USE OF FUNDS 17,180$ -$ -$ -$ -$ -$ -$ -$ 65,000$ 82,180$
HERNANDEZ AVENUE STORM DRAIN IMPROVEMENTS Project 816-0409
PROPOSED STREETS PROGRAM
Street Improvements
C - 38 LOS GATOS BLVDBLOSSOM HILL RD
SHANNON
R
D
Project Name Shannon Road Class 1 Multi-Use Path Project Number 813-0218
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will construct a Class I multi-use path on one side of Shannon Road between Los Gatos Blvd.
and Cherry Blossom Lane. The project will demolish approximately 500 feet of existing sidewalk, fill in
approximately 860 feet of sidewalk gap, construct a Class I multi-use path approximately 1360’ length x
10’ width with a 3’ buffer between the path and the travel lane, install new ADA curb ramps, and complete
sharrows on Shannon Road within the project limits. The work scope also includes new curb and gutter
and utility underground work. These are necessary items to upgrade the street.
Location The project is located on Shannon Road between Los Gatos Boulevard and Cherry Blossom Lane.
Project
Background
Shannon Road is a heavily traveled two-lane roadway, especially when the schools are in session. Shannon
Road is used by residents dropping off students at various schools, such as Blossom Hill Elementary, Van
Meter Elementary, and Fisher Middle Schools. In addition, many parents walk their children to school
along this segment of roadway.
Shannon Road currently has intermittent sections of sidewalk on the south side of the roadway between
Los Gatos Boulevard and Cherry Blossom Lane. Most pedestrians cross Shannon Road to walk along the
south side, while some walk along the unimproved shoulder on the north side. This project will complete
the sidewalk segment on the north side of the roadway and reduce congestion at Shannon Road and
Cherry Blossom Lane, where a 3-way stop is inundated by crossing students, crossing guards, and vehicle
traffic during peak school hours.
In June 2018 the Town was awarded federal funding of $940,100 by the Santa Clara Valley Transportation
Authority (VTA) in the Vehicle Emissions Reductions Based at Schools (VERBS) Grant Program to support
this project. Grants are awarded on a reimbursement basis. Although the Town was informed of the
award in 2018, the funding will be recognized in the year it is received and will be shifted to the current
year as the project progresses.
Operating
Budget
Impacts
Engineering staff time for design and construction of this project will be addressed in the FY 2020/21
Operating Budget.
PROPOSED STREETS PROGRAM
Street Improvements
C - 39
Project
Components &
Estimated Timeline
Fall 2021 Design Project design & development
Winter 2022 Bid process Project bidding & contract award
Summer 2022 Construction Project construction
Fall 2022 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 104 20,000 109,896 - 109,896 - - - - 130,000$
GRANTS & AWARDS - - - 940,100 940,100 - - - - 940,100$
UTILITY UNDERGROUNDING - 49,000 70,204 - 70,204 - - - - 119,204$
TOTAL SOURCE OF FUNDS 104$ 69,000$ 180,100$ 940,100$ 1,120,200$ -$ -$ -$ -$ 1,189,304$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed $ -
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 104 20,000 109,896 - 109,896 - - - - 130,000
TOTAL GFAR 104$ 20,000$ 109,896$ -$ 109,896$ -$ -$ -$ -$ 130,000$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 940,100 940,100 - - - - 940,100
TOTAL GRANTS & AWARDS -$ -$ -$ 940,100$ 940,100$ -$ -$ -$ -$ 940,100$
UNDERGROUND UTILITIES
Salaries and Benfits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acqusition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - 49,000 70,204 - 70,204 - - - - 119,204$
TOTAL UNDERGROUND UTILITIES -$ 49,000$ 70,204$ -$ 70,204$ -$ -$ -$ -$ 119,204$
TOTAL USE OF FUNDS 104$ 69,000$ 180,100$ 940,100$ 1,120,200$ -$ -$ -$ -$ 1,189,304$
SHANNON ROAD CLASS 1 MULTI-USE PATH Project 813-0218
PROPOSED STREETS PROGRAM
Street Improvements
C - 40
TOWN-WIDE
Project Name Sidewalk Improvements – Multiple
Locations
Project Number 813-0221
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will construct sidewalk, curb, and gutter on the north side of Kennedy Road from Ferris
Avenue to Los Gatos Boulevard and on the south side of Mitchell Avenue from George Street to Fisher
Avenue.
Location This project is located in the following areas: Kennedy Road from Ferris Avenue to Los Gatos Boulevard;
Mitchell Avenue from George Street to Fisher Avenue; and Los Gatos Boulevard/Shannon Road.
Project
Background
Kennedy Road from Ferris Avenue to Los Gatos Boulevard currently has a shoulder that is heavily
utilized by parents and students walking and biking to school in the morning and afternoons. The
sidewalk improvements will complete the connection in this residential block.
In 2009, the Town completed the sidewalk installation on the north side of Mitchell Avenue from
George Street to Fisher Avenue. Then in 2012, sidewalk was constructed on north and south side of
Mitchell Avenue between Los Gatos Boulevard and George Street as part of the redevelopment of the
former Honda site. This project will complete the last component of the sidewalks in this heavily
utilized pedestrian area between Van Meter Elementary and Fisher Middle Schools.
Operating
Budget Impacts
Engineering staff time for design and construction of this project will be addressed in the FY 2019/20
Operating Budget.
PROPOSED STREETS PROGRAM
Street Improvements
C - 41
Project
Components &
Estimated
Timeline
Fall 2019 Design Project design & development
Winter 2019 Bid process Project bidding & contact award
Spring 2020 Construction Project construction
Summer 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$
TOTAL SOURCE OF FUNDS -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 60,000 - 60,000 - - - - -
TOTAL GFAR -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$
TOTAL USE OF FUNDS -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$
SIDEWALK IMPROVEMENTS - MULTIPLE LOCATIONS Project 813-0221
PROPOSED STREETS PROGRAM
Street Improvements
C - 42 HWY 17LOS GATOS BLVDLOS GAT
O
S-
ALMADEN RD
Project Name Utility Undergrounding Improvements
Project Number 813-0225
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will remove utilities from above ground poles and install them underground.
Location This project is located on Los Gatos Boulevard between Lark Avenue and Chirco Drive.
Project
Background
Through the State of California’s Public Utilities Commission, Pacific Gas & Electric (PG&E) collects funds
from ratepayers to provide for the undergrounding of utilities. These funds grow in reserve called Rule
20A funds, until such time that local jurisdictions identify an area for this project and begin working
with PG&E. The funds are limited to use on roadways where traffic is heavy, making Los Gatos
Boulevard a viable location.
The Town’s allocation of Rule 20A funds has grown to the point where there is now approximately
$3.8M available for programming. These funds will never actually come to the Town, but rather PG&E
will deliver the project with coordination from Town staff.
In addition to the Rule 20A funds, the Town collects developer fees for utility undergrounding. These
funds are held by the Town for future projects. Staff has asked PG&E to look at an expanded project
scope utilizing some or all of the Town funds as well. This will take full advantage of economies of scale
through design and construction.
The timeframe for PG&E to deliver Rule 20A projects has been between seven and ten years; however,
indications are that this project may begin sooner, depending upon other PG&E priorities, such as fire
safety make identifying firm dates difficult.
Operating
Budget Impacts
There will be no Operating Budget impact as a result of this project. Project delivery costs for this
project are included in the CIP project’s total cost. Project delivery costs are estimated at $266,000
over the five-year term of the project or 4% of the total project cost. Project costs are significantly
lower on this project due to the efficiencies in the project size and a larger proportion of work that will
be coordinated by PG&E.
PROPOSED STREETS PROGRAM
Street Improvements
C - 43
Project
Components &
Estimated Timeline
Winter 2020 Design Project design & development
Fall 2020 Construction Project construction begins
Spring 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
UTILITY UNDERGROUNDING -$ -$ 2,330,000$ 4,436,000$ 6,766,000$ -$ -$ -$ -$ 6,766,000$
TOTAL SOURCE OF FUNDS -$ -$ 2,330,000$ 4,436,000$ 6,766,000$ -$ -$ -$ -$ 6,766,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
UTILITY UNDERGORUNDING
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 2,330,000 4,436,000 6,766,000 - - - - 6,766,000
TOTAL GFAR -$ -$ 2,330,000$ 4,436,000$ 6,766,000$ -$ -$ -$ -$ 6,766,000$
TOTAL USE OF FUNDS -$ -$ 2,330,000$ 4,436,000$ 6,766,000$ -$ -$ -$ -$ 6,766,000$
UTILITY UNDERGROUNDING IMPROVEMENTS Project 813-0225
PROPOSED STREETS PROGRAM
Street Improvements
C - 44
Project Name Traffic Signal Modernization
Project Number 813-0227
Department Parks & Public Works Project Manager Transportation and Mobility
Manager: Ying Smith
Description This project will modernize the Town’s traffic signal controllers.
Location This project is located Town-wide.
Project
Background
This project will modernize the Town’s traffic signal controllers to allow for greater control depending
on traffic conditions, ensure that the current system meets current safety standards, and increase the
traffic flow. The Town was awarded several grants through the VTA and the MTC to complement the
Town’s investment of Traffic Impact Mitigation Funds.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Improvements
C - 45
Project
Components &
Estimated Timeline
Summer 2018 Design Project design & development
Fall 2019 Bid Process Project bidding & contract award
Fall 2020 Construction Project construction
Spring 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
TRAFFIC MITIGATION 22,594$ 102,406$ 563,262$ 415,027$ 978,289$ -$ -$ -$ -$ 1,103,289$
GRANTS & AWARDS 41,381 15,601 1,769,418 - 1,769,418$ - - - - 1,826,400
TOTAL SOURCE OF FUNDS 63,975$ 118,007$ 2,332,680$ 415,027$ 2,747,707$ -$ -$ -$ -$ 2,929,689$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
TRAFFIC MITIGATIONS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 22,594 102,406 563,262 415,027 978,289 - - - - 1,103,289
TOTAL TRAFFIC MITIGATIONS 22,594$ 102,406$ 563,262$ 415,027$ 978,289$ -$ -$ -$ -$ 1,103,289$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 41,380.58 15,601 1,769,418 - 1,769,418 - - - - 1,826,400
TOTAL GRANTS & AWARDS 41,381$ 15,601$ 1,769,418$ -$ 1,769,418$ -$ -$ -$ -$ 1,826,400$
TOTAL USE OF FUNDS 63,975$ 118,007$ 2,332,680$ 415,027$ 2,747,707$ -$ -$ -$ -$ 2,929,689$
TRAFFIC SIGNAL MODERNIZATION Project 813-0227
PROPOSED STREETS PROGRAM
Street Improvements
C - 46
Project Name Bicknell Road Storm Drain Improvements
Project Number 816-0410
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will reroute a Town storm drain line.
Location This project is located on Bicknell Road near Montclair.
Project
Background
This project will provide design services for the rerouting of an existing Town storm drain line from
private property, after it was determined that the Town does not have a storm drain easement.
This project has provided challenges due to right-of-way constraints and connection to the adjacent
creek. Over this fiscal year, staff will monitor the project for performance and identify any additional
adjustments necessary.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. The staff time for this
project is included in the Department’s FY 2020/21 Operating Budget.
QUITO RDBICKNELL RD
HWY 9
PROPOSED STREETS PROGRAM
Street Improvements
C - 47
Project
Components &
Estimated Timeline
Fall 2019 Design Project design & development
Fall 2019 Construction Project construction
Winter 2020 Monitoring Monitoring and adjustment
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
STORM BASIN #3 145,432$ 15,500$ 35,258$ 25,000$ 60,258$ -$ -$ -$ -$ 221,190$
TOTAL SOURCE OF FUNDS 145,432$ 15,500$ 35,258$ 25,000$ 60,258$ -$ -$ -$ -$ 221,190$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
STORM BASIN #2
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 145,432 15,500 35,258 25,000 60,258 - - - - 221,190
TOTAL STORM BASIN 145,432$ 15,500$ 35,258$ 25,000$ 60,258$ -$ -$ -$ -$ 221,190$
TOTAL USE OF FUNDS 145,432$ 15,500$ 35,258$ 25,000$ 60,258$ -$ -$ -$ -$ 221,190$
BICKNELL ROAD STORM DRAIN IMPROVEMENTS Project 816-0410
PROPOSED STREETS PROGRAM
Street Improvements
C - 48
Project Name Bicycle & Pedestrian Improvements
Project Number 813-0231
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will enhance bicycle and pedestrian safety and mobility throughout the Town.
Location This project is located Town-wide.
Project
Background
This project will enhance bicycle and pedestrian safety and mobility Town-wide in the form of multiple
projects. As has been done in the previous years, staff will continue to work with Safe Routes to School,
Town Commissions, the Town Council, and the general public on prioritizing projects that have been
recommended in the Council adopted Bicycle and Pedestrian Master Plan. In addition, this money will
be used as matching funds for available grants related to Town bicycle and pedestrian projects.
In the past the Town received Transportation Fund for Clean Air Grants for bicycle and pedestrian
improvements.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Improvements
C - 49
Project
Components &
Estimated Timeline
Summer 2019 Design Project design & development
Fall 2019 Bid Process Project bidding & contract award
Winter 2019 Construction Project construction
Spring 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 95,694$ 122,211$ 272,095$ -$ 272,095$ -$ -$ -$ -$ 490,000$
GRANTS & AWARDS 112,627 168,900 - - - - - - - 281,527
TRAFFIC MITIIGATION 40,972 378 33,650 - 33,650 - - - - 75,000
TOTAL SOURCE OF FUNDS 249,293$ 291,489$ 305,745$ -$ 305,745$ -$ -$ -$ -$ 846,527$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 95,694 122,211 272,095 - 272,095 - - - - 490,000
TOTAL GFAR 95,694$ 122,211$ 272,095$ -$ 272,095$ -$ -$ -$ -$ 490,000$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - -
Consultant Services - - - - - - - - -
Project Construction Expenses 112,627 168,900 - - - - - - - 281,527
TOTAL GRANTS & AWARDS 112,627$ 168,900$ -$ -$ -$ -$ -$ -$ -$ 281,527$
TRAFFIC MITIGATION
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - -
Consultant Services - - - - - - - - -
Project Construction Expenses 40,972 378 33,650 - 33,650 - - - - 75,000
TOTAL TRAFFIC MITIGATION 40,972$ 378$ 33,650$ -$ 33,650$ -$ -$ -$ -$ 75,000$
TOTAL USE OF FUNDS 249,293$ 291,489$ 305,745$ -$ 305,745$ -$ -$ -$ -$ 846,527$
BICYCLE & PEDESTRIAN IMPROVEMENTS Project 813-0231
PROPOSED STREETS PROGRAM
Street Improvements
C - 50
Project Name Stormwater Master Plan
Project Number 816-0413
Department Parks & Public Works Project Manager PPW Director: Matt Morley
Description This project will develop a Stormwater Master Plan.
Location This project is located Town-wide.
Project
Background
The Town of Los Gatos does not currently have an adopted Stormwater Master Plan. This project will
develop a Stormwater Collection System Master Plan and provides the Town of Los Gatos with the
necessary planning tools and capital improvement projects to address flood management and water
quality within the collector portion of the storm drainage system.
The Plan will be developed to help the Town meet its overarching environmental and economic goals.
The goal of the Stormwater Master Plan is to manage stormwater runoff proactively to protect water
quality and to minimize impacts of localized and downstream flooding by identifying infrastructure
improvements for the collection, conveyance, and treatment of stormwater runoff within the Town.
The Stormwater Master Plan will prioritize storm drain and water quality improvements within the
Town and provides an implementation plan for the construction of conveyance and water quality
improvements.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Improvements
C - 51
Project
Components &
Estimated Timeline
Summer 2019 Design Develop request for proposals
Fall 2019 Bid Process Award consultant agreement
Spring 2020 Report Conduct study
Fall 2020 Completion Finalize report
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 3,060$ 16,940$ 180,000$ -$ 180,000$ -$ -$ -$ -$ 200,000$
TOTAL SOURCE OF FUNDS 3,060$ 16,940$ 180,000$ -$ 180,000$ -$ -$ -$ -$ 200,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 3,060 16,940 180,000 - 180,000 - - - - 200,000$
TOTAL GFAR 3,060$ 16,940$ 180,000$ -$ 180,000$ -$ -$ -$ -$ 200,000$
TOTAL USE OF FUNDS 3,060$ 16,940$ 180,000$ -$ 180,000$ -$ -$ -$ -$ 200,000$
STORMWATER MASTER PLAN Project 816-0413
PROPOSED STREETS PROGRAM
Street Improvements
C - 52
Project Name Stormwater System – Pollution Prevention
Compliance
Project Number 816-0414
Department Parks & Public Works Project Manager PPW Director: Matt Morley
Description This project will install improvements, such as trash capture devices, to reduce pollution in the storm
water system.
Location This project is located Town-wide.
Project
Background
This project will install solutions, such as multiple trash capture devices in storm inlets, throughout the
Town to meet the Municipal Regional Permit Provision C.10 trash reduction requirements. The Town
has submitted a plan to meet the requirement to reduce trashload impacts to creeks which are 70% by
2017 and 100% by 2022.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Improvements
C - 53
Project
Components &
Estimated Timeline
Fall 2020 Design Project design & development
Winter 2021 Bid Process Project bidding & contact award
Spring 2021 Construction Project construction
Summer 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 1,422$ -$ 298,578$ -$ 298,578$ -$ -$ -$ -$ 300,000$
TOTAL SOURCE OF FUNDS 1,422$ -$ 298,578$ -$ 298,578$ -$ -$ -$ -$ 300,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 1,422 - 298,578 - 298,578 - - - - 300,000
TOTAL GFAR 1,422$ -$ 298,578$ -$ 298,578$ -$ -$ -$ -$ 300,000$
TOTAL USE OF FUNDS 1,422$ -$ 298,578$ -$ 298,578$ -$ -$ -$ -$ 300,000$
STORMWATER SYSTEM - POLLUTION PREVENTION COMPLIANCE Project 816-0414
PROPOSED STREETS PROGRAM
Street Improvements
C - 54
Project Name Public Arts Gateway
Project Number 821-2009
Department Library Project Manager Library Director: Ryan Baker
Description This project will install a public art at a gateway location.
Location This project is located on Highway 9 near Alberto Way.
Project
Background
The Arts and Culture Commission identified this project as a way to enhance the appearance of the
entrances into Los Gatos. At the January 31, 2017 Priority Setting, Council identified $25,000 for public
art and on April 18, 2017 the Arts and Culture Commission proposed the gateway project as the best
use of the funds, which Council approved. This project will install the first phase of artwork at Town
entrances based on the Town’s Public Art Selection Policy and Procedures.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. The staff time for this
project is included in the Department’s FY 2020/21 Operating Budget.
PROPOSED STREETS PROGRAM
Street Improvements
C - 55
Project
Components &
Estimated Timeline
Winter 2018 Call for artist Project design & award
Fall 2019 Award Select final design & award
Summer 2020 Construction Project construction
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ 4,500$ 20,500$ 4,504$ 25,004$ -$ -$ -$ -$ 29,504$
TOTAL SOURCE OF FUNDS -$ 4,500$ 20,500$ 4,504$ 25,004$ -$ -$ -$ -$ 29,504$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - 4,500 20,500 4,504 25,004 - - - - 29,504
TOTAL GFAR -$ 4,500$ 20,500$ 4,504$ 25,004$ -$ -$ -$ -$ 29,504$
TOTAL USE OF FUNDS -$ 4,500$ 20,500$ 4,504$ 25,004$ -$ -$ -$ -$ 29,504$
PUBLIC ARTS GATEWAY PROJECT Project 821-2009
PROPOSED STREETS PROGRAM
Street Improvements
C - 56
Project Name Parking Program Implementation
Project Number 813-0242
Department Parks & Public Works Project Manager PPW Director: Matt Morley
Description This project consists of the phased implementation of the recommendations found in the
Comprehensive Parking Study that concluded in early 2020. First phases may include an employee
permit program and a design for enhanced signage.
Location This project is located downtown and nearby neighborhoods.
Project
Background
In 2019 the Town conducted a Parking Study to identify the needs for parking in Los Gatos. The Parking
Study provided a series of recommendations that should be implemented over time. The
recommendations include adjustments to time limits, permitting programs, wayfinding or signage
enhancements, and other ideas that ensure the existing inventory is utilized effectively. Later stages
of the program may look at supply enhancements based on ongoing analysis.
Operating
Budget Impacts
This project will use staff time for project management. Engineering staff time associated with these
projects will be charged to the project as it is delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 57
Project
Components &
Estimated Timeline
Fall 2020 Employee
Permit Program
Implement employee permit program
Spring 2021 Signage design Design signage
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ 198,500$ 198,500$ -$ -$ -$ -$ 198,500$
TOTAL SOURCE OF FUNDS -$ -$ -$ 198,500$ 198,500$ -$ -$ -$ -$ 198,500$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 198,500 198,500 - - - - 198,500
TOTAL GFAR -$ -$ -$ 198,500$ 198,500$ -$ -$ -$ -$ 198,500$
TOTAL USE OF FUNDS -$ -$ -$ 198,500$ 198,500$ -$ -$ -$ -$ 198,500$
PARKING PROGRAM IMPLEMENTATION Project 813-0242
PROPOSED STREETS PROGRAM
Street Improvements
C - 58
Project Name Annual Storm Drain Improvement Project
Project Number 816-0420
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will install infill storm drain systems that are required to enhance safety and improve
infrastructure to accept water runoff.
Location This project is located Town-wide.
Project
Background
The Town is responsible for keeping Town roads clear of excessive water and managing storm water
running down Town streets. Storm drain improvements in the Town right of ways and parking lots are
necessary to manage water drainage issues within these Town locations. The intent of this project is
to keep pace with the needs of the Town’s storm drain system to prevent flooding in the Town right of
ways.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Improvements
C - 59
Project
Components &
Estimated Timeline
Summer 2020 Design Project design & development
Winter 2020 Bid Process Project bidding & contract award
Spring 2021 Construction Project construction
Summer 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
STORM BASIN #1 -$ -$ 100,000$ 50,000$ 150,000$ -$ -$ -$ -$ 150,000$
STORM BASIN #2 -$ -$ 100,000$ 50,000$ 150,000$ -$ -$ -$ -$ 150,000$
STORM BASIN #3 29,700$ -$ 70,300$ 50,000$ 120,300$ -$ -$ -$ -$ 150,000$
TOTAL SOURCE OF FUNDS 29,700$ -$ 270,300$ 150,000$ 420,300$ -$ -$ -$ -$ 450,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
STORM BASIN #1
Project Construction Expenses - - 100,000 50,000 150,000 - - - - 150,000$
TOTAL STORM BASIN #1 -$ -$ 100,000$ 50,000$ 150,000$ -$ -$ -$ -$ 150,000$
STORM BASIN #2
Project Construction Expenses -$ -$ 100,000$ 50,000$ 150,000$ -$ -$ -$ -$ 150,000$
TOTAL STORM BASIN #2 -$ -$ 100,000$ 50,000$ 150,000$ -$ -$ -$ -$ 150,000$
STORM BASIN #3
Project Construction Expenses 29,700$ -$ 70,300$ 50,000$ 120,300$ -$ -$ -$ -$ 150,000$
TOTAL STORM BASIN #3 29,700$ -$ 70,300$ 50,000$ 120,300$ -$ -$ -$ -$ 150,000$
TOTAL USE OF FUNDS 29,700$ -$ 270,300$ 150,000$ 420,300$ -$ -$ -$ -$ 450,000$
ANNUAL STORM DRAIN IMPROVEMENT PROJECT Project 816-0420
PROPOSED STREETS PROGRAM
Street Improvements
C - 60
Project Name Pilot School Busing
Project Number 812-0128
Department Parks & Public Works Project Manager Transportation & Mobility
Manager: Ying Smith
Description This project explores congestion relief through piloting school bus service. The pilot school bus service
provides morning and afternoon routes to and from school with neighborhood-based stops.
The Town is contracting with a qualified school bus transportation provider through a RFP process. The
service schedule and designated pick up and drop off locations are published. Interested families may
purchase an annual pass to reserve a seat. The pilot program will provide two routes for a total of 2 ½
years from January 2019 to June 2021.
Location This project is located Town-wide.
Project
Background
The Town of Los Gatos and the school community have been exploring new transit services customized
to meet the needs of students traveling to and from schools. The primary areas of interest are corridors
with the highest level of traffic congestion. Town staff and a consulting team completed a Congestion
Relief School Bus Feasibility Study in 2018. The Town Council, at its June 5, 2018 meeting, authorized
staff to proceed with a school bus pilot program. At its September 18, 2018 meeting, the Town Council
authorized funding to provide a pilot service consisting of two routes for 18 months of service. At its
March 3, 2020 meeting, Town Council directed staff to continue the School Bus Pilot Program for an
additional year and to return to Council with options to transition the service to a different model.
The two-route pilot service started on January 7, 2019 and will continue for school year 2020/21.
Operating
Budget Impacts
The pilot program is funded by the Town as well as fare revenue. This project will use staff time for
service design. PPW staff time associated with these projects will be charged to the project as it is
delivered.
TOWN-WIDE
PROPOSED STREETS PROGRAM
Street Improvements
C - 61
Project
Components &
Estimated Timeline
Summer 2018 Design Service plan design, marketing, customer sign up
Fall 2018 Bid Process RFP & service contract award, finalize service plan
Winter 2019 Service Launch Provide Pilot Service
Summer 2021 Completion Completion of 2 and ½ years of pilot service
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 148,683$ 224,035$ 42,056$ 313,000$ 355,056$ -$ -$ -$ -$ 727,774$
GRANTS & AWARDS -$ -$ -$ 87,000$ 87,000$ 87,000$ -$ -$ -$ 174,000$
TOTAL SOURCE OF FUNDS 148,683$ 224,035$ 42,056$ 400,000$ 442,056$ 87,000$ -$ -$ -$ 901,774$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 148,683 224,035 42,056 313,000 355,056 - - - - 727,774
TOTAL GFAR 148,683$ 224,035$ 42,056$ 313,000$ 355,056$ -$ -$ -$ -$ 727,774$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 87,000 87,000 87,000 - - - 174,000
TOTAL GRANTS & AWARDS -$ -$ -$ 87,000$ 87,000$ 87,000$ -$ -$ -$ 174,000$
TOTAL USE OF FUNDS 148,683$ 224,035$ 42,056$ 400,000$ 442,056$ 87,000$ -$ -$ -$ 901,774$
PILOT SCHOOL BUSING Project 812-0128
PROPOSED STREETS PROGRAM
Street Improvements
C - 62
TOWN-WIDE
Project Name ADA Transition Plan
Project Number 812-0129
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project will update the Town’s ADA Transition Plan as required.
Location This project is located Town-wide.
Project
Background
The Americans with Disabilities Act (ADA), enacted on July 26, 1990, provides comprehensive rights to
persons with disabilities in different areas including access to public accommodations and
transportation. The ADA requires that all public agencies develop a transition plan for eliminating
barriers for persons with disabilities. The Town’s ADA Transition Plan has not been updated since 1994,
and it is necessary to develop programs that comply with the new standards
Operating
Budget Impacts
This project will use staff time for management. Engineering staff time associated with these projects
will be charged to the project as it is delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 63
Project
Components &
Estimated Timeline
Summer 2020 Design Develop request for proposals
Fall 2020 Bid Process Award consultant agreement
Winter 2021 Report Conduct study
Spring 2021 Completion Finalize report
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ 110,000$ -$ 110,000$ -$ -$ -$ -$ 110,000$
TOTAL SOURCE OF FUNDS -$ -$ 110,000$ -$ 110,000$ -$ -$ -$ -$ 110,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 110,000 - 110,000 - - - - 110,000
TOTAL GRANTS & AWARDS -$ -$ 110,000$ -$ 110,000$ -$ -$ -$ -$ 110,000$
TOTAL USE OF FUNDS -$ -$ 110,000$ -$ 110,000$ -$ -$ -$ -$ 110,000$
ADA TRANSITION PLAN Project 812-0129
PROPOSED STREETS PROGRAM
Street Improvements
C - 64
Project Name Highway 17/9 Interchange and Capacity
Improvements
Project Number 813-0237
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description These funds will be used as a local match necessary to begin a conceptual study for improvements at
Highway 9 and Highway 17.
Location This project is located on Highway 9 and Highway 17.
Project
Background
The Countywide 2016 Measure B sales tax measure includes investments in the regional transportation
infrastructure across nine program areas. The Santa Clara Valley Transportation Authority (VTA)
manages the 2016 Measure B program and the VTA Board approves project prioritization and funding.
The VTA approved the first set of projects on a two-year budget cycle with a ten-year look ahead at
potential projects.
Through the process to establish the structure of and projects included in the 2016 Measure B, the
Town proposed upgrades to the interchange at Highway 9 and Highway 17 as its major project in the
Highway category. In reviewing the project with VTA, an opportunity exists to include two options for
modifications to Highway 17 through Los Gatos. The first includes efficiency improvements such as
adding auxiliary lanes and realigning existing lanes. Auxiliary lanes might include continuing the on-
ramp from Lark Avenue south to the Highway 9 off-ramp, facilitating a smoother transition of traffic.
The second is an expanded version that could include the addition of travel lanes on Highway 17 within
the existing right of way. VTA approved 2016 Measure B funds to bring the project through preliminary
design and environmental review. The allocation of 2016 Measure B funds requires at least a 10 percent
contribution from non-2016 Measure B sources. While the Town is pursuing outside funds for the
match, this project would set aside Town funds if needed.
Operating
Budget Impacts
This project will use staff time for project management. Engineering staff time associated with these
projects will be charged to the project as it is delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 65
Project
Components &
Estimated Timeline
Summer 2020 Design Project design & development
Summer 2021 Design Review Review of Design
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
TRAFFIC MITAGATION -$ -$ 600,000$ -$ 600,000$ -$ -$ -$ -$ 600,000$
TOTAL SOURCE OF FUNDS -$ -$ 600,000$ -$ 600,000$ -$ -$ -$ -$ 600,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
TRAFFIC MITAGATION
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 600,000 - 600,000 - - - - 600,000
TOTAL TRAFFIC MITIGATION -$ -$ 600,000$ -$ 600,000$ -$ -$ -$ -$ 600,000$
TOTAL USE OF FUNDS -$ -$ 600,000$ -$ 600,000$ -$ -$ -$ -$ 600,000$
HIGHWAY 17/9 INTERCHANGE & CAPACITY IMPROVEMENTS Project 813-0237
PROPOSED STREETS PROGRAM
Street Improvements
C - 66
HWY
9
E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV
Project Name Downtown Streetscape Revitalization
Project Number 813-0235
Department Parks & Public Works Project Manager PPW Director: Matt Morley
Description These funds will be used as initial funding for a larger Downtown Streetscape Revitalization project.
Location This project is located downtown.
Project
Background
The Downtown Streetscape infrastructure has aged and needs updating to continue to attract
customers and facilitate maintenance. This initial funding set aside is in preparation for a future project
to reinvent the Downtown. Past efforts that inform this project include a one-way street pilot on North
Santa Cruz Avenue and a Comprehensive Downtown Parking Study. In addition, the Town’s Operating
Budget provides for increased attention to the maintenance of landscape and hardscape. Progress and
expenditures on this project will occur only following ongoing discussion and direction from the Town
Council.
Operating
Budget Impacts
This project will use staff time for project management. Engineering staff time associated with these
projects will be charged to the project as it is delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 67
Project
Components &
Estimated Timeline
Summer 2020 Design Project design & development
TBD Future project milestones
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ 1,972,384$ -$ 1,972,384$ -$ -$ -$ -$ 1,972,384$ .
TOTAL SOURCE OF FUNDS -$ -$ 1,972,384$ -$ 1,972,384$ -$ -$ -$ -$ 1,972,384$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 1,972,384 - 1,972,384 - - - - 1,972,384
TOTAL GFAR -$ -$ 1,972,384$ -$ 1,972,384$ -$ -$ -$ -$ 1,972,384$
TOTAL USE OF FUNDS -$ -$ 1,972,384$ -$ 1,972,384$ -$ -$ -$ -$ 1,972,384$
DOWNTOWN STREETSCAPE REVITALIZATION Project 813-0235
PROPOSED STREETS PROGRAM
Street Improvements
C - 68
Project Name E. Main Street Speed Table/Raised
Crosswalk
Project Number 812-0131
Department Parks & Public Works Project Manager PPW Assistant Director/Town
Engineer: Lisa Petersen
Description The project will install two speed tables, raised crosswalks, and bulb outs on East Main Street in front
of Los Gatos High School.
Location East Main Street in front of Los Gatos High School, between High School Court and Chicago Avenue.
Project
Background
The East Main Street Speed Table/Raised Crosswalk project includes installing two speed tables on East
Main Street in front of Los Gatos High School, combined with raised crosswalks and the construction
of bulb outs at all three crosswalks.
The Town received a Transportation Fund for Clean Air (TFCA) grant in the amount of $86,200 from the
Santa Clara Valley Transportation Authority (VTA) for the construction of this project.
Operating
Budget Impacts
Engineering staff time for design and construction of this project will be addressed in the FY 2020/21
Operating Budget.
PROPOSED STREETS PROGRAM
Street Improvements
C - 69
Project
Components &
Estimated Timeline
Summer 2020 Design Project plans & specifications
Winter 2021 Bid Process Council approves plans & authorizes bidding the project
Summer 2021 Construction Council awards the contract & construction process begins
Fall 2021 Completion Project completed
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ 83,000$ 83,000$ -$ -$ -$ -$ 83,000$
GRANTS & AWARDS - - - 86,200 86,200 - - - - 86,200
TOTAL SOURCE OF FUNDS -$ -$ -$ 169,200$ 169,200$ -$ -$ -$ -$ 169,200$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 83,000 83,000 - - - - 83,000
TOTAL GFAR -$ -$ -$ 83,000$ 83,000$ -$ -$ -$ -$ 83,000$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 86,200 86,200 - - - - 86,200
TOTAL GRANTS & AWARDS -$ -$ -$ 86,200$ 86,200$ -$ -$ -$ -$ 86,200$
TOTAL USE OF FUNDS -$ -$ -$ 169,200$ 169,200$ -$ -$ -$ -$ 169,200$
E. MAIN ST. SPEED TABLE/RAISED CROSSWALK Project 812-0131
PROPOSED STREETS PROGRAM
Street Improvements
C - 70
TOWN-WIDE
Project Name Local Road Safety Plan
Project Number 812-0132
Department Parks & Public Works Project Manager PPW Assistant Director/Town
Engineer: Lisa Petersen
Description This project will prepare a Local Road Safety Plan for the Town.
Location This project is located Town-wide.
Project
Background
A Local Road Safety Plan (LRSP) is a new initiative in the State’s Highway Safety Improvement Program
(HSIP). Preparing a LRSP is an opportunity for jurisdictions to address unique local roadway safety needs
while contributing to the success of the Strategic Highway Safety Plan. The process of preparing an
LRSP creates a framework to systematically identify and analyze safety problems and recommend
safety improvements. Preparing an LRSP facilitates the development of local agency partnerships and
collaboration, resulting in a prioritized list of improvements and actions that can demonstrate a defined
need and contribute to the statewide plan. The LRSP offers a proactive approach to addressing safety
needs and demonstrates agency responsiveness to safety challenges. In the future Highway Safety
Improvement Program (HSIP) Calls-for-Projects, an LRSP (or its equivalent) will be preferred or required
for an agency to be eligible to apply for federal HSIP funds. The Town has received HSIP grants in the
past for this Plan. Completing a LRSP will ensure the Town’s eligibility to apply and receive future HSIP
funds.
The Town was awarded a HSIP grant for completing the LRSP in an amount of $72,000, the maximum
grant amount allowed per agency. A minimum of 10% local match is required. Staff is recommending
a higher match amount of $28,000 to have sufficient funds to prepare a high-quality product with
extensive community engagement.
Operating
Budget Impacts
This project will use staff time for project management. Engineering staff time associated with these
projects will be charged to the project as it is delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 71
Project
Components &
Estimated Timeline
Summer 2020 Design Project design & development
Fall 2020 RFP & Selection
Process
Council authorizes issuing RFP Proposal evaluation and vendor
selection. Council awards the contract and study begins.
Winter 2020 Study Study, analysis and community engagement.
Summer 2021 Completion Project completed.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ 28,000$ 28,000$ -$ -$ -$ -$ 28,000$
GRANTS & AWARDS - - - 72,000 72,000 - - - - 72,000
TOTAL SOURCE OF FUNDS -$ -$ -$ 100,000$ 100,000$ -$ -$ -$ -$ 100,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 28,000 28,000 - - - - 28,000
TOTAL GFAR -$ -$ -$ 28,000$ 28,000$ -$ -$ -$ -$ 28,000$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 72,000 72,000 - - - - 72,000
TOTAL GRANTS & AWARDS -$ -$ -$ 72,000$ 72,000$ -$ -$ -$ -$ 72,000$
TOTAL USE OF FUNDS -$ -$ -$ 100,000$ 100,000$ -$ -$ -$ -$ 100,000$
LOCAL ROAD SAFETY PLAN Project 812-0132
PROPOSED STREETS PROGRAM
Street Improvements
C - 72
Project Name Blossom Hill Road Traffic Study
Project Number 813-0239
Department Parks & Public Works Project Manager PPW Assistant Director/Town
Engineer: Lisa Petersen
Description These funds will be used to conduct a safety study on Blossom Hill Road.
Location This project is located on Blossom Hill Road from Camelia Terrace to Hillbrook Drive.
Project
Background
This project would conduct a safety study on Blossom Hill Road focusing on the areas from Camelia
Terrace to Hillbrook Drive. The study would identify opportunities for improvements to the corridor to
benefit multi-modal transportation, provide traffic calming, and increase safety. The study would
include information on potential impacts to surrounding streets, especially residential streets, that may
occur as a result of changes to Blossom Hill Road.
Operating
Budget Impacts
This project will use staff time for project management. Engineering staff time associated with these
projects will be charged to the project as it is delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 73
Project
Components &
Estimated Timeline
Summer 2020 RFP Process Conduct Request for Proposals process.
Fall 2020 Study Study and analysis.
Fall 2020 Completion Study result brought to Council for consideration.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ 125,000$ 125,000$ -$ -$ -$ -$ 125,000$
TOTAL SOURCE OF FUNDS -$ -$ -$ 125,000$ 125,000$ -$ -$ -$ -$ 125,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 125,000 125,000 - - - - 125,000
TOTAL GFAR -$ -$ -$ 125,000$ 125,000$ -$ -$ -$ -$ 125,000$
TOTAL USE OF FUNDS -$ -$ -$ 125,000$ 125,000$ -$ -$ -$ -$ 125,000$
BLOSSOM HILL ROAD TRAFFIC STUDY Project 813-0239
PROPOSED STREETS PROGRAM
Street Improvements
C - 74
Project Name Winchester Class IV Bikeway
Project Number 813-0240
Department Parks & Public Works Project Manager PPW Assistant Director/Town
Engineer: Lisa Petersen
Description The project will install Class IV protected bike lines on Winchester Boulevard.
Location This project is located on Winchester Boulevard between Blossom Hill Road and Albright Way.
Project
Background
Winchester Boulevard is a major arterial street parallel to Highway 17, which borders both the Town
of Los Gatos and the City of Monte Sereno. The Los Gatos Bicycle and Pedestrian Master Plan (BPMP)
identifies the construction of Class IV bike lanes along Winchester Boulevard as an important
improvement project for the Town. On January 29,2020, the Town was awarded a grant award of
$293,900 from the Transportation Fund for Clean Air (TFCA) Regional Fund for the Winchester
Boulevard Class IV Protected Bike Lanes Project. The TFCA funds will be applied to the construction
phase.
Operating
Budget Impacts
This project will use staff time for design and construction of this project. Engineering staff time
associated with this project will be changed to the project as delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 75
Project
Components &
Estimated Timeline
Summer 2020 Design and Bid Prepare plans & specifications. Council approves plans &
authorizes bidding the project. Council awards the project.
Summer 2021 Construction Construction process begins.
Fall 2021 Completion Project completed.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ 688,555$ 688,555$ -$ -$ -$ -$ 688,555$
GRANTS & AWARDS - - - 293,900 293,900 - - - - 293,900
TOTAL SOURCE OF FUNDS -$ -$ -$ 982,455$ 982,455$ -$ -$ -$ -$ 982,455$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 688,555 688,555 - - - - 688,555
TOTAL GFAR -$ -$ -$ 688,555$ 688,555$ -$ -$ -$ -$ 688,555$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 293,900 293,900 - - - - 293,900
TOTAL GRANTS & AWARDS -$ -$ -$ 293,900$ 293,900$ -$ -$ -$ -$ 293,900$
TOTAL USE OF FUNDS -$ -$ -$ 982,455$ 982,455$ -$ -$ -$ -$ 982,455$
WINCHESTER CLASS IV BIKEWAY Project 813-0240
PROPOSED STREETS PROGRAM
Street Improvements
C - 76
HWY
9
E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV
Project Name VMT Mitigation Program
Project Number 812-0133
Department Parks & Public Works Project Manager PPW Assistant Director/Town
Engineer: Lisa Petersen
Description This project will fund a required nexus study to establish a Vehicle Miles Travelled fee program.
Location This project is located Town-wide.
Project
Background
Staff is working a Transportation Analysis Policy and Guidelines in compliance with state law and the
CEQA Guidelines. The Town will need to establish a robust VMT reduction program to lower VMT
Town-wide. Based on other jurisdictions’ experience and considering the local setting, the most
effective and feasible actions will likely include bike and pedestrian improvements, Transportation
Demand Management actions, parking and policy changes, shuttles, and financial incentives. The final
policy and guidelines are expected to be adopted by the Town Council in June 2020, with follow up
work on local policies through the 2020 calendar year.
It is anticipated that the new Transportation Analysis Policy and Guidelines will make it necessary for
the Town to establish a new VMT Mitigation program. The current Traffic Impact Mitigation Fee is
based on roadway capacity analysis. The transition to VMT as a metric will necessitate different
mitigation measures to address impacts from driving. A nexus study will be required to establish a
mitigation fee program.
Operating
Budget Impacts
This project will use staff time for management of this project. Engineering staff time associated with
this project will be changed to the project as delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 77
Project
Components &
Estimated Timeline
Summer 2020 Design Develop scope and RFP.
Winter 2020 RFP & Selection
Process
Council authorizes issuing RFP. Proposal evaluation and vendor
selection. Council awards the contract and study begins.
Spring 2021 Study Study, analysis, and community engagement.
Fall 2021 Completion Study and recommendations completed. Council adopts the
VMT Mitigation Program and Fee.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
TOTAL SOURCE OF FUNDS -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - 250,000 250,000 - - - - 250,000
TOTAL GFAR -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
TOTAL USE OF FUNDS -$ -$ -$ 250,000$ 250,000$ -$ -$ -$ -$ 250,000$
VMT MITIGATION PROGRAM AND FEE NEXUS STUDY Project 812-0133
PROPOSED STREETS PROGRAM
Street Improvements
C - 78
Project Name Kennedy Sidewalk – LGB to Englewood
Project Number 813-0241
Department Parks & Public Works Project Manager PPW Assistant Director/Town
Engineer: Lisa Petersen
Description The project will install sidewalks and Class II bike lanes on Kennedy Road.
Location This project location is Kennedy Road Between Los Gatos Boulevard and Englewood Avenue.
Project
Background
The Kennedy Road Sidewalk improvement project will provide safe connections to Los Gatos
Boulevard, a destination point in Town for employment. The project is in a residential neighborhood
that will provide benefits to Louise Van Meter Elementary School, R.J. Fisher Middle School, and Los
Gatos High School. The project location is in close proximity to the Los Gatos and Fillmer stop on the
VTA Route 27 providing access to further destinations within the Town and Blossom Hill Road.
Staff submitted a Measure B grant application to seek funding for the final design and construction of
this project. The local match amount is included in this project budget. The project schedule is
contingent upon Measure B award.
Operating
Budget Impacts
This project will use staff time for design and management. Engineering staff time associated with this
project will be changed to the project as delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 79
Project
Components &
Estimated Timeline
Fall 2020 Design Prepare plans & specifications.
Spring 2021 Bid Process Council approves plans authorizes bidding the project.
Summer 2021 Construction Council awards the contract and construction process begins.
Fall 2021 Completion Project completed.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ -$ -$ -$ 356,700$ -$ -$ 356,700$
GRANTS & AWARDS - - - - - - 805,690 - - 805,690
TOTAL SOURCE OF FUNDS -$ -$ -$ -$ -$ -$ 1,162,390$ -$ -$ 1,162,390$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - - - - 356,700 - - 356,700
TOTAL GFAR -$ -$ -$ -$ -$ -$ 356,700$ -$ -$ 356,700$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - - - - 805,690 - - 805,690
TOTAL GRANTS & AWARDS -$ -$ -$ -$ -$ -$ 805,690$ -$ -$ 805,690$
TOTAL USE OF FUNDS -$ -$ -$ -$ -$ -$ 1,162,390$ -$ -$ 1,162,390$
KENNEDY SIDEWALK BETWEEN LGB AND ENGELWOOD Project 813-0241
PROPOSED STREETS PROGRAM
Street Improvements
C - 80
Project Name Winchester Boulevard Complete Streets
Final Design
Project Number 813-0238
Department Parks & Public Works Project Manager Transportation & Mobility
Manager: Ying Smith
Description This project will fund the conceptual engineering and final design for Complete Streets improvements
on Winchester Boulevard.
Location This project location is Winchester Boulevard between Blossom Hill Road and Knowles Drive (Town
limits).
Project
Background
Winchester Boulevard is a major arterial street parallel to Highway 17, which borders both the Town
of Los Gatos and the City of Monte Sereno. The Los Gatos Bicycle and Pedestrian Master Plan (BPMP)
identifies the construction of Class IV bike lanes along Winchester Boulevard as an improvement
project. The construction of Winchester Class IV Bikeway is included as a separate project (813-0240).
Complete Streets treatments will likely include enhanced bike lanes, pedestrian crossing, sidewalk
improvements, pedestrian refuse islands, landscaped medians, intersection modifications, and
stormwater retention.
In December 2019, the Town selected Kimley-Horn and Associates, Inc. as the consultant to complete
engineering design. The conceptual engineering work is expected to be completed by the end of 2020.
The Final Design for the Winchester Boulevard Complete Streets improvements is one of the five
candidate projects submitted to the Measure B Bicycle and Pedestrian Competitive Grant Program.
The local funds included in this project’s budget is the estimated local match amount. In future years,
additional funds will be needed for construction. Staff will continue to seek grant funding to complete
this project.
Operating
Budget Impacts
Engineering staff time for the design, construction inspection, and management will be charged to the
project as it is delivered.
PROPOSED STREETS PROGRAM
Street Improvements
C - 81
Project
Components &
Estimated Timeline
Fall 2020 Conceptual
Design
Complete Conceptual design
Fall 2021 Final Design Complete right-of-way certificate and final design (pending
funding)
TBD Construction Begin and complete construction
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ 200,053$ 79,948$ -$ 79,948$ 463,250$ -$ -$ -$ 743,250$
GRANTS & AWARDS - - - - - 996,000 - - - 996,000
TOTAL SOURCE OF FUNDS -$ 200,053$ 79,948$ -$ 79,948$ 1,459,250$ -$ -$ -$ 1,739,250$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - 200,053 79,948 - 79,948 463,250 - - - 743,250
TOTAL GFAR -$ 200,053$ 79,948$ -$ 79,948$ 463,250$ -$ -$ -$ 743,250$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consul;tant Services - - - - - - - - - -
Project Construction Expenses - - - - - 996,000 - - - 996,000
TOTAL GRANTS & AWARDS -$ -$ -$ -$ 996,000$ -$ -$ -$ 996,000$
TOTAL USE OF FUNDS -$ 200,053$ 79,948$ -$ 79,948$ 1,459,250$ -$ -$ -$ 1,739,250$
WINCHESTER BOULEVARD COMPLETE STREETS Project 813-0238
PROPOSED STREETS PROGRAM
Street Improvements
C - 82
PROPOSED STREETS PROGRAM
Bridge Projects
C - 83
PROJECT LOCATIONS
A Quito Road - Bridge Replacement
B Highway 17 Bicycle & Pedestrian Bridge – Design
PROPOSED STREETS PROGRAM
Bridge Projects
C - 84
PROGRAM SECTION DIRECTORY PAGE
0801 Quito Road - Bridge Replacement C – 86
0803 Highway 17 Bicycle & Pedestrian Bridge - Design C – 88
PROPOSED STREETS PROGRAM
Bridge Projects
C - 85
The Streets Program’s Bridge Projects section contains Capital Improvement Program projects that repair, replace, or
rehabilitate a deficient bridge structure as the primary scope of work.
Bridge structure safety falls under the guidance of state and federal regulations, and bridge projects are often driven by
available funding from these jurisdictions, such as Caltrans grant programs or the federal Highway Bridge Replacement and
Rehabilitation (HBRR) program. Los Gatos does not have a designated funding source for repairing, maintaining, and
improving the Town’s bridges, and relies upon grant programs for major bridge improvement projects.
BRIDGE PROJECTS SUMMARY
Carryforward Projects
0801 Quito Road - Bridge Replacement 64,594$ 285,087$ -$ -$ -$ -$ 349,681$
0803 Hwy 17 Bicycle & Pedestrian Bridge-Design 234,000 - 5,430,303 - - - 5,664,303
Total Bridge Projects 298,594$ 285,087$ 5,430,303$ -$ -$ -$ 6,013,984$
Expended Through
2019/20
Total
Budgeted
2023/24
Budget
2022/23
Budget
2021/22
Budget
2020/21 Budget &
Carryfwd*
FY 2020/21 - 2024/25 CAPITAL IMPROVEMENT PROGRAM
BRIDGE PROJECTS
2024/25
Budget
* Total FY 2019/20 Carryforward $235,087
PROPOSED STREETS PROGRAM
Bridge Projects
C - 86
Project Name Quito Road - Bridge Replacement Project Number 818-0801
Department Parks & Public Works Project Manager Assistant Director/Town
Engineer: Lisa Petersen
Description This project funds the Town’s portion of the replacement cost for two bridges on Quito Road to
improve roadway safety and provide adequate storm water flow capacity in the creek under the
bridge.
Location The two Quito Road bridges span a tributary of San Tomas Aquino Creek. The bridges are located on
Quito Road in the vicinity of Old Adobe Road, approximately 1½ miles north of Highway 9, on the
common boundary line between the City of Saratoga and the Town of Los Gatos.
Project
Background
San Tomas Aquino Creek is under the jurisdiction of the Santa Clara Valley Water District (SCVWD),
while the replacement of the bridges is the shared responsibility of the City of Saratoga and the Town
of Los Gatos. Both bridges are approximately ninety years old and have been classified “structurally
deficient” under Caltrans guidelines. In addition, both bridges are not adequate to receive 100-year
flood flows.
In 2001, the City of Saratoga, the project sponsor, secured partial funding (80%) through the federal
Highway Bridge Replacement and Rehabilitation (HBRR) program to replace both bridges with wider
span structures that will allow the 100-year design flood flow to pass underneath. Saratoga is the
lead agency to oversee the design, environmental, right-of-way acquisition, and construction services
for the project. The City of Saratoga, the Town of Los Gatos, and SCVWD agreed to share the duties
and responsibilities for the project and the remaining 20% local match funding requirement.
After further evaluation of the bridges, it was determined that Quito Road would require
reconstruction at each end of the bridge, which in turn requires additional right-of-way acquisitions
and environmental reviews under both the State of California (Caltrans) and federal regulations.
These changes have made it necessary to redesign this project, significantly increasing the estimated
costs. The City of Saratoga has applied for additional funding from Caltrans due to the redesign. As a
result of the additional project costs, the local funding match from the City of Saratoga, the Town of
Los Gatos, and the SCVWD has increased from $155,000 to $238,000 for each agency. Based on the
April 2019 schedule from the City of Saratoga, the construction of these bridges is anticipated to be
completed by 2021.
Operating
Budget Impacts
Engineering staff time for coordination of this project with the City of Saratoga is incorporated into
the Saratoga Operating Budget.
HW
Y
8
5
POLLARD
R
D
QUITO RD
PROPOSED STREETS PROGRAM
Bridge Projects
C - 87
Project
Components &
Estimated
Timeline
Jan 2001 Grant Funding The City of Saratoga obtained grant funding from the federal
HBRR program.
Oct 2001 Cooperative
Agreement
Council approved a cooperative agreement with the City of
Saratoga and SCVWD for the replacement of the two bridges.
May 2002 Preliminary Design City of Saratoga started preliminary design.
2013 Right of way Right of way acquisition process is ongoing and environmental
permitting is underway.
2015 Final Design Design completed and project bidding by the City of Saratoga.
April 2020 Construction Start Begin reconstruction of bridge.
Summer
2021
Completion Construction is anticipated to be complete in 2021.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 64,594$ -$ 235,087$ 50,000$ 285,087$ -$ -$ -$ -$ 349,681$
TOTAL SOURCE OF FUNDS 64,594$ -$ 235,087$ 50,000$ 285,087$ -$ -$ -$ -$ 349,681$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 64,594 - 235,087 50,000 285,087 - - - - 349,681
TOTAL GFAR 64,594$ -$ 235,087$ 50,000$ 285,087$ -$ -$ -$ -$ 349,681$
TOTAL USE OF FUNDS 64,594$ -$ 235,087$ 50,000$ 285,087$ -$ -$ -$ -$ 349,681$
QUITO ROAD - BRIDGE REPLACEMENT Project 818-0801
PROPOSED STREETS PROGRAM
Bridge Projects
C - 88 LOS GATOS BLVDHWY 17N SANTA CRUZ AVBLOSSOM H
I
L
L
R
D
SHANNO
N
R
D
UNIVERSITY AV
Project Name Highway 17 Bicycle & Pedestrian Bridge -
Design
Project Number 818-0803
Department Parks & Public Works Project Manager Transportation & Mobility
Manager: Ying Smith
Description This project will fund the preliminary design, environmental clearance, and final design for potential
bicycle and pedestrian bridge over Highway 17.
Location This project is located at Blossom Hill Road or Nino Way over Highway 17.
Project
Background
Highway 17 presents a barrier for bicyclists and pedestrians wanting to cross from one side of Los
Gatos to the other. Current crossings are largely vehicle focused and often uncomfortable for other
transportation modes. This is a suggested path included in the Safe Routes to School Phase 1 Study.
In September 2019, the Town selected BKF Engineers as the consultant and officially kicked off the
project. The feasibility analysis and conceptual engineering work is expected to be completed by the
end of 2020. At its March 3, 2020 meeting, the Town Council approved the project’s Purpose and
Need and authorized proceeding with design alternatives for a separate bicycle and pedestrian
overcrossing.
The Final Design phase will include environmental clearance, right-of-way, and final design, estimated
to be approximately $3.7 million. Staff submitted a Measure B grant application to seek funding for
the final design of this project. The local match amount is included in this project’s budget. The
project schedule is contingent upon the Measure B award.
In future years, additional funds will be needed for construction. The construction cost will be in the
$20 to $30 million range. Staff will continue to seek grant funding to complete this project.
Operating
Budget Impacts
This project will use staff time for project management. Staff time associated with these projects will
be charged to the project as it is delivered.
PROPOSED STREETS PROGRAM
Bridge Projects
C - 89
Project
Components &
Estimated
Timeline
Spring 2020 Preliminary
Design
Project design & development
Spring 2023 Environmental
Clearance and
Final Design
Complete environmental clearance and final design
TBD Construction Complete construction
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ -$ -$ -$ 946,210$ -$ -$ -$ 946,210$
TRAFFIC MITIGATION - 147,005 - - - - - - - 147,005
GRANTS & AWARDS - 86,995 - - - 4,484,093 - - - 4,571,088
TOTAL SOURCE OF FUNDS -$ 234,000$ -$ -$ -$ 5,430,303$ -$ -$ -$ 5,664,303$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - - - 946,210 - - - 946,210
TOTAL GFAR -$ -$ -$ -$ -$ 946,210$ -$ -$ -$ 946,210$
TRAFFIC MITIGATION
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - 147,005 - - - - - - - 147,005
TOTAL TRAFFIC MITIGATION -$ 147,005$ -$ -$ -$ -$ -$ -$ -$ 147,005$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - 86,995 - - - 4,484,093 - - - 4,571,088
TOTAL GRANTS & AWARDS -$ 86,995$ -$ -$ -$ 4,484,093$ -$ -$ -$ 4,571,088$
TOTAL USE OF FUNDS -$ 234,000$ -$ -$ -$ 5,430,303$ -$ -$ -$ 5,664,303$
HIGHWAY 17 BICYCLE AND PEDESTRIAN BRIDGE - DESIGN Project 818-0803
PROPOSED STREETS PROGRAM
Bridge Projects
C - 90
Parks Program
This Page Intentionally Left Blank
PROPOSED PARKS AND TRAILS PROGRAM
D - 1
PARK PROJECT DIRECTORY
4605 Parks Playground Fibar Project D – 6
4609 Creek Trail & Parks Pathway & Parking Lot Seal Coat and Striping D – 8
4202 Town Plaza Turf Repairs D – 10
4006 Outdoor Fitness Equipment D – 12
4508 Vegetation Management – Town-wide D – 14
TRAIL PROJECT DIRECTORY
4504 Open Space Trail Upgrades D – 20
4507 Forbes Mill Footbridge Improvements D – 22
4503 Charter Oaks Trail Repair D – 24
4505 Trailhead Connector Project D – 26
PROPOSED PARKS AND TRAILS PROGRAM
Park Improvement Projects
D - 2
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 3
PROJECT LOCATIONS
A Parks Playground Fibar Project
B Creek Trail & Parks Pathway & Parking Lot Seal Coat and Striping
C Town Plaza Turf Repairs
D Outdoor Fitness Equipment – Balzer Field
E Vegetation Management – Town-wide
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 4
PROGRAM SECTION DIRECTORY PAGE
4605 Parks Playground Fibar Project D – 6
4609 Creek Trail & Parks Pathway & Parking Lot Seal Coat & Striping D – 8
4202 Town Plaza Turf Repairs D – 10
4006 Outdoor Fitness Equipment D – 12
4508 Vegetation Management – Town-wide D – 14
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 5
The Parks Program’s Park Improvement Projects section contains Capital Improvement Program projects that repair or
improve a Town park as the primary scope of work. Typical park improvement projects include parking lot, walkway, and
basketball or tennis court resurfacing; and park equipment or facility upgrades.
The Park Improvement Projects section does not have ongoing programs; all projects are considered one-time projects. The
exception to this is the Parks Fibar replacement project. Because Fibar requires regular replacement and infill, this project is
scheduled as a bi-annual project. One-time park improvement projects are prioritized based on health and safety issues,
available funding sources, infrastructure impacts, project costs, and community impacts.
Los Gatos does have Park Construction Tax Revenue as a designated funding source for the Parks operating program budget;
however, tax receipts are limited to approximately $11,000 per year, and are not sufficient for a capital program. In addition
to GFAR funding, grants, in-lieu fees, and CDBG funds are pursued and utilized for park improvements when available.
PARK IMPROVEMENT PROJECTS SUMMARY
* Total FY 2019/20 Carryforward $850,247
Unfunded Projects
• Oak Meadow Park Upgrades
• Civic Center Irrigation System Replacement & Upgrade
• Turf Renovations - Various Parks
• Oak Meadow Park Fencing Upgrades
• Oak Meadow Park Restroom Expansion
• Park Rehabilitation – La Rinconada Park
• Park Rehabilitation – Live Oak Manor Park
• Park Rehabilitation – Blossom Hill Park
• Plaza Park Improvements
PARKS
Carryforward Projects
4605 Parks Playground Fibar Project 63,460$ 61,540$ -$ 25,000$ -$ 25,000$ 175,000$
4609 Creek Trail & Parks Path & Parking Lot Seal & Striping - 225,000 - - - - 225,000
4202 Town Plaza Turf Repairs 8,116 28,000 - - - - 36,116
4006 Outdoor Fitness Equipment - 60,000 - - - - 60,000
4508 Vegetation Management - Town-wide - 500,707 - - - - 500,707
New Projects
Total Park Improvement Projects 71,575$ 875,247$ -$ 25,000$ -$ 25,000$ 996,823$
2020/21 Budget &
Carryfwd*
2021/22
Budget
2022/23
Budget
2023/24
Budget
FY 2020/21 - 2024/25 CAPITAL IMPROVEMENT PROGRAM
PARK IMPROVEMENT PROJECTS
Expended Through
2019/20
2024/25
Budget
Total
Budgeted
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 6
Project Name Parks Playground Fibar Project Project Number 831-4605
Department Parks & Public Works Project Manager Superintendent: Jim Harbin
Description This project will replace fibar material at all Town playgrounds.
Location This project will be completed at various parks in Los Gatos.
Project
Background
Several Town parks have playground structures that are heavily used by children and their families.
Playground safety codes require that the fibar material be spread under and around playground
structures to prevent injury to children.
Fibar replacement is required when the material is below a specific depth near the playground
structure. Fibar is a wood product that degrades over time based on foot traffic and weather
conditions. This material should be replaced on a regular, as needed basis. This is an annual CIP project
to improve the safety of the Town’s playgrounds.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. The staff time for this
project is included in the Parks and Public Works Department’s FY 2020/21 Operating Budget.
TOWN-WIDE
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 7
Project
Components &
Estimated Timeline
Summer 2019 Scope Project development
Spring 2020 Bid Process Project bidding & contract award
Summer 2020 Construction Project construction
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
G FAR 63,460$ -$ 36,540$ 25,000$ 61,540$ -$ 25,000$ -$ 25,000$ 175,000$
TOTAL SOURCE OF FUNDS 63,460$ -$ 36,540$ 25,000$ 61,540$ -$ 25,000$ -$ 25,000$ 175,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
G FAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 63,460 - 36,540 25,000 61,540 - 25,000 - 25,000 175,000
TOTAL GFAR 63,460$ -$ 36,540$ 25,000$ 61,540$ -$ 25,000$ -$ 25,000$ 175,000$
TOTAL USE OF FUNDS 63,460$ -$ 36,540$ 25,000$ 61,540$ -$ 25,000$ -$ 25,000$ 175,000$
PARKS PLAYGROUND FIBAR PROJECT Project 831-4605
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 8
H
W
Y
9
W
M
A
I
N
S
T HWY 17N SANTA CRUZ AVUNIVERSITY AV
TOWN-WIDE
Project Name Creek Trail & Park Pathway & Parking Lot
Seal Coat & Striping
Project Number 831-4609
Department Parks & Public Works Project Manager Superintendent: Jim Harbin
Description The project will resurface and restripe park parking lots, pathways, and sections of the Los Gatos Creek
Trail.
Location The project is located at Belgatos Park, Blossom Hill Park, Live Oak Manor Park, Oak Meadow Park, and
the Los Gatos Creek Trail.
Project
Background
The parking lots located in parks and the Los Gatos Creek Trail are heavily used on a daily basis. In
order to keep their surfaces in good condition and prevent long term wear and damage, the parking
lots and trails need to be resurfaced and striped. This project is necessary to prevent future damages
to existing pavement surfaces in the future.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 9
Project
Components &
Estimated Timeline
Summer 2019 Design Project design & development
Summer 2020 Bid Process Project bidding & contract award
Summer 2020 Construction Project construction
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ 225,000$ -$ 225,000$ -$ -$ -$ -$ 225,000$
TOTAL SOURCE OF FUNDS -$ -$ 225,000$ -$ 225,000$ -$ -$ -$ -$ 225,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 225,000 - 225,000 - - - - 225,000
TOTAL GFAR -$ -$ 225,000$ -$ 225,000$ -$ -$ -$ -$ 225,000$
TOTAL USE OF FUNDS -$ -$ 225,000$ -$ 225,000$ -$ -$ -$ -$ 225,000$
CREEK TRAIL, PARKS PATHS & PARKING LOTS SEAL AND STRIPING Project 831-4609
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 10
E MAIN STHWY 17N SANTA CRUZUNIVERSITY AVAV
Project Name Town Plaza Turf Repairs
Project Number 831-4202
Department Parks & Public Works Project Manager Superintendent: Jim Harbin
Description This project will renovate the turf at Plaza Park.
Location The project is located at Town Plaza Park, at the corner of West Main Street and Santa Cruz Avenue.
Project
Background
Plaza Park, located in the heart of downtown Los Gatos, is a popular park and hosts a variety of
community events, such as Jazz on the Plazz and the Farmer’s Market. Because of the amount of high
foot traffic at this location, the turf is heavily impacted. This project will remove the existing sod and
soil. New soil will be added to the area to enhance root growth and to re-grade the ground to mitigate
standing water issues. Additionally, along with the installation of new turf grass, minor changes to the
irrigation system will be completed to maximize water coverage. The turf was last replaced around
2010.
The project will be completed during a period when there is the least impact on scheduled downtown
events.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 11
Project
Components &
Estimated Timeline
Summer 2020 Design Project design & development
Fall 2020 Bid Process Project bidding & contract award
Spring 2021 Construction Project construction
Spring 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
G FAR 8,116$ -$ 28,000$ -$ 28,000$ -$ -$ -$ -$ 36,116$
TOTAL SOURCE OF FUNDS 8,116$ -$ 28,000$ -$ 28,000$ -$ -$ -$ -$ 36,116$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
G FAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 8,116 - 28,000 - 28,000 - - - - 36,116
TOTAL GFAR 8,116$ -$ 28,000$ -$ 28,000$ -$ -$ -$ -$ 36,116$
TOTAL USE OF FUNDS 8,116$ -$ 28,000$ -$ 28,000$ -$ -$ -$ -$ 36,116$
TOWN PLAZA TURF REPAIRS Project 831-4202
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 12
Project Name Outdoor Fitness Equipment
Project Number 831-4006
Department Parks & Public Works Project Manager Superintendent: Jim Harbin
Description This project will install outdoor fitness equipment.
Location This project is located at the Balzer Field parking area.
Project
Background
The Town was awarded an outdoor fitness rig after attending a California Parks & Recreation Society
conference and participating in a competition. The Town has received equipment that is valued at
$30,000 and Town staff will install the equipment at the Balzer Field Parking Lot.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 13
Project
Components &
Estimated Timeline
Summer 2019 Scope Project design & development
Summer 2020 Bid Process Project bidding & contract award
Summer 2020 Construction Project construction
Summer 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$
TOTAL SOURCE OF FUNDS -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 60,000 - 60,000 - - - - 60,000
TOTAL GFAR -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$
TOTAL USE OF FUNDS -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$
OUTDOOR FITNESS EQUIPMENT Project 831-4006
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 14
Project Name Vegetation Management – Town-wide
Project Number 832-4508
Department Parks & Public Works Project Manager Superintendent: Jim Harbin
Description This project funds an ecological assessment to provide guidance for fuel removal in Town open space
and right-of-way and the first year of open space fuel reduction.
Location The project location is Town open spaces and rights-of-way.
Project
Background
The FEMA-approved Santa Clara Operational Area Hazard Mitigation Plan lists the wildfire hazard for
the Town of Los Gatos as “high.” The funding allows for an ecological assessment to provide guidance
for fuel removal in Town open spaces and rights-of-way, and funding for the first year of open space
fuel reduction. The Town has applied for a FEMA grant for vegetation management work and a portion
of these funds may be used for as a funding match for that grant.
Operating
Budget Impacts
This project will use staff time for coordination of the assessment and fuel reduction. Parks staff time
associated with this project will be charged to the project as it is delivered.
TOWN-WIDE
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 15
Project
Components &
Estimated Timeline
Fall 2019 Scope Project scope development
Winter 2020 RFP Process Project RFP for ecological assessment
Summer 2020 Bid Process Bid to implement fuel reduction
Fall 2020 Implementation First season of fuel reduction
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ 500,707$ -$ 500,707$ -$ -$ -$ -$ 500,707$
TOTAL SOURCE OF FUNDS -$ -$ 500,707$ -$ 500,707$ -$ -$ -$ -$ 500,707$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 500,707 - 500,707 - - - - 500,707
TOTAL GFAR -$ -$ 500,707$ -$ 500,707$ -$ -$ -$ -$ 500,707$
TOTAL USE OF FUNDS -$ -$ 500,707$ -$ 500,707$ -$ -$ -$ -$ 500,707$
VEGETATION MANAGEMENT - TOWN-WIDE Project 832-4508
PROPOSED PARKS & TRAILS PROGRAM
Park Improvement Projects
D - 16
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 17
PROJECT LOCATIONS
A Open Space Trail Upgrades
B Forbes Mill Footbridge Improvements
C Charter Oaks Trail Repair
D Trailhead Connector Project
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 18
PROGRAM SECTION DIRECTORY PAGE
4504 Open Space Trail Upgrades D – 20
4507 Forbes Mill Footbridge Improvements D – 22
4503 Charter Oaks Trail Repair D – 24
4505 Trailhead Connector Project D – 26
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 19
The Parks Program’s Trail Improvement Projects section contains Capital Improvement Program projects that construct,
repair, or improve a Town trail as the primary scope of work. Typical trail improvement projects include pathway construction
or resurfacing.
TRAIL IMPROVEMENT PROJECTS SUMMARY
* Total FY 2019/20 Carryforward $683,812
`
Carryforward Projects
4504 Open Space Trail Upgrades -$ 152,000$ -$ -$ -$ -$ 152,000$
4507 Forbes Mill Footbridge Improvements 30,603 61,224 - - - - 91,828
4503 Charter Oaks Trail Repair Project 72,942 440,109 - - - - 513,051
4505 Trailhead Connector 486,961 30,479 3,262,500 - - - 3,779,940
New Projects
Total Trail Improvement Projects 590,506$ 683,812$ 3,262,500$ -$ -$ -$ 4,536,819$
FY 2020/21 - 2024/25 CAPITAL IMPROVEMENT PROGRAM
2022/23
Budget
Expended Through
2019/20
2023/24
Budget
TRAIL IMPROVEMENT PROJECTS
Total
Budgeted
2020/21 Budget &
Carryfwd*
2021/22
Budget
2024/25
Budget
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 20
Project Name Open Space Trail Upgrades Project Number 832-4504
Department Parks & Public Works Project Manager Superintendent: Jim Harbin
Description This project will repair and replace old damaged retaining walls, fences, and embankments along the
trails in the Town’s open spaces.
Location This project is located at Santa Rosa Open Space, Heintz Open Space, and Belgatos Park.
Project
Background
The Town has a number of open space preserves that are under its jurisdiction. There are several public
trail networks that traverse the open space preserves in the hillsides. The aging process has
deteriorated a number of retaining walls and embankments along some trail sections. Without proper
repair and replacement, the possibility of failure of the trails will increase greatly. This project will
repair and replace several retaining walls that are supporting the trails and their embankments. In
addition, this project will improve the drainage system around the retaining walls to prevent further
erosion of the trails. This project will also address two bridges at Belgatos Park.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
TOWN-WIDE
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 21
Project
Components &
Estimated Timeline
Summer 2020 Design Project design & development
Spring 2021 Bid Process Project bidding & contract award
Summer 2021 Construction Project construction
Winter 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Open Space Reserve Fund -$ -$ 152,000$ -$ 152,000$ -$ -$ -$ -$ 152,000$
TOTAL SOURCE OF FUNDS -$ -$ 152,000$ -$ 152,000$ -$ -$ -$ -$ 152,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 152,000 - 152,000 - - - - 152,000
TOTAL GFAR -$ -$ 152,000$ -$ 152,000$ -$ -$ -$ -$ 152,000$
TOTAL USE OF FUNDS -$ -$ 152,000$ -$ 152,000$ -$ -$ -$ -$ 152,000$
OPEN SPACE TRAIL UPGRADES Project 832-4504
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 22
Project Name Forbes Mill Footbridge Improvements
Project Number 832-4507
Department Parks & Public Works Project Manager Superintendent: Jim Harbin
Description The project will provide pathway lighting across the 400-foot span of the pedestrian bridge and
installation of additional art panels.
Location The project is located on the pedestrian bridge between Forbes Mill and Old Town across Highway
17.
Project
Background
Forbes Mill footbridge is a heavily used pathway crossing Highway 17 between the Main Street
businesses, Civic Center, and high school on the east side of the freeway, and the downtown on the
west. The interior walls of the walkway are decorated with murals painted by students over the past
decades. The pathway structure once had a lighting system but fell into disrepair several years ago and
was removed. This left the pathway dark in the evening, which has prompted concerns from residents.
The installation of footbridge improvements in 2018 included solar LED lighting for the pathway. Staff
is currently monitoring this install to ensure the lights meet long-term needs.
This project will also install additional art panels to occupy the remaining space.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
HWY 9
E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 23
Project
Components &
Estimated Timeline
Fall 2018 Design Project design & development
Fall 2018 Bid Process Project bidding & contract award
Winter 2019 Construction Project construction
Summer 2020 Completion Project completion and monitoring
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 27,397$ 3,207$ 61,224$ -$ 61,224$ -$ -$ -$ -$ 91,828$
TOTAL SOURCE OF FUNDS 27,397$ 3,207$ 61,224$ -$ 61,224$ -$ -$ -$ -$ 91,828$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 27,397 3,207 61,224 - 61,224 - - - - 91,828
TOTAL GFAR 27,397$ 3,207$ 61,224$ -$ 61,224$ -$ -$ -$ -$ 91,828$
TOTAL USE OF FUNDS 27,397$ 3,207$ 61,224$ -$ 61,224$ -$ -$ -$ -$ 91,828$
FORBES MILL FOOTBRIDGE IMPROVEMENTS Project 832-4507
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 24 HWY 17WINCHESTER BLVDLOS GATOS BLVDHW
Y
8
5
LA
R
K
A
V
KNOWLES
Project Name Charter Oaks Trail Repair Project Number 832-4503
Department Parks & Public Works Project Manager PPW Assistant Director/Town
Engineer: Lisa Petersen
Description This project will repair the storm damage on the Los Gatos Creek Trail near Charter Oaks, which includes
damage to the fencing and asphalt pathway.
Location This project is located on the Los Gatos Creek Trail near Charter Oaks.
Project
Background
The existing trail is adjacent to Los Gatos Creek and was damaged by flooding during the winter storms
of 2017. The impacts of the storm included damage to the fencing and to the asphalt concrete
pathway. The trail is well used by the public and the damage has negatively impacted trail users by
making the trail more difficult to use. Funds for this project will be provided by FEMA.
Subsequent to the trail repair work, this project will further evaluate improvements along the trail from
Lark Avenue towards Highway 85 utilizing Community Benefit funds in the amount of $350,000 from
the Albright project. This project scope will be determined through community outreach efforts for
construction in FY 2020/21.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 25
Project
Components &
Estimated Timeline
Summer 2020 Design Project design & development
Spring 2020 Bid Process Project bidding & contract award
Summer 2021 Construction Project construction
Fall 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 109$ -$ 364,891$ -$ 364,891$ -$ -$ -$ -$ 365,000$
GRANTS 72,833 - 75,218 - 75,218 - - - - 148,051$
TOTAL SOURCE OF FUNDS 72,942$ -$ 440,109$ -$ 440,109$ -$ -$ -$ -$ 513,051$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 109 - 364,891 - 364,891 - - - - 365,000
TOTAL GFAR 109$ -$ 364,891$ -$ 364,891$ -$ -$ -$ -$ 365,000$
GRANTS &AWARDS
Salaries and Benefits - - - - - - - - - -
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 72,833 - 75,218 - 75,218 - - - - 148,051
TOTAL GRANTS &AWARDS 72,833$ -$ 75,218$ -$ 75,218$ -$ -$ -$ -$ 148,051$
TOTAL USE OF FUNDS 72,942$ -$ 440,109$ -$ 440,109$ -$ -$ -$ -$ 513,051$
CHARTER OAKS TRAIL REPAIR Project 832-4503
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 26
H
W
Y
9 HWY 17N SANTA CRUZ AVUNIVERSITY AV
Project Name Trailhead Connector Project Project Number 832-4505
Department Parks & Public Works Project Manager PPW Assistant Director/Town
Engineer: Lisa Petersen
Description This project will fund the design and construction of a trailhead connection for Los Gatos Creek Trail to
Highway 9.
Location This project is located on the Los Gatos Creek Trail near Highway 9.
Project
Background
This project will fund the design and construction of a trailhead connection for Los Gatos Creek Trail to
Highway 9. The project is an identified priority within Measure B and the Bicycle and Pedestrian Plan.
The Council approved the staff recommendation for the next steps on this project in June 2017.
Caltrans approved the Authorization to Proceed with Preliminary Engineering, also known as E-76
approval, on December 13, 2018. In February 2019 the Town issued a Request for Proposal for the
preliminary engineering and environmental clearance phase, which will take approximately 12 months.
If funding for construction is secured, the project would begin construction in 2020/21 at the earliest.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 27
Project
Components &
Estimated Timeline
Fall 2020 Design Project design & development
Pending Bid Process Project bidding & contract award
Pending Construction Project construction
Pending Completion Project completion
Prior Yrs
Actuals
2019/20
Adjusted
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 214$ 174,226$ 143,747$ 30,479$ -$ 30,479$ -$ -$ -$ -$ 174,440$
GRANTS & AWARDS - 343,000 343,000 - - - 3,262,500 - - - 3,605,500$
TOTAL SOURCE OF FUNDS 214$ 517,226$ 486,747$ 30,479$ -$ 30,479$ 3,262,500$ -$ -$ -$ 3,779,940$
`
2019/20
Adjusted
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 214 174,226 143,747 30,479 - 30,479 - - - - 174,440
TOTAL GFAR 214 174,226 143,747 30,479 - 30,479 - - - - 174,440
GRANTS &AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - - -
Consultant Services - - - - - - - - - - -
Project Construction Expenses - 343,000 343,000 - - - 3,262,500 - - - 3,605,500
TOTAL GRANTS &AWARDS -$ 343,000$ 343,000$ -$ -$ -$ 3,262,500$ -$ -$ -$ 3,605,500$
TOTAL USE OF FUNDS 214$ 517,226$ 486,747$ 30,479$ -$ 30,479$ 3,262,500$ -$ -$ -$ 3,779,940$
TRAILHEAD CONNECTOR PROJECT Project 832-4505
PROPOSED PARKS & TRAILS PROGRAM
Trail Improvement Projects
D - 28
Public Facilities Program
This Page Intentionally Left Blank
PUBLIC FACILITIES DIRECTORY PROPOSED
E - 1
TOWN INFRASTRUCTURE PROJECT DIRECTORY
2302 Building Replacement at Corporation Yard E – 6
2001 Facilities Assessment E – 8
2503 Library Carpet Replacement E – 10
2002 Town Beautification E – 12
2601 ADA Upgrade Public Restrooms – Adult Recreation Building E – 14
2117 ADA Restrooms and HR Offices E – 16
2116 Plaza Level Railings – Code Upgrade E – 18
2010 Waterproofing – Town-wide E – 20
2504 Sound Mitigation in Library Lobby E – 22
6004 Fire Suppression (Halon) for Server Rooms E – 24
2118 Police Headquarters Roof Repair E – 26
2206 Adult Recreation Center – Floor Repair E – 28
EQUIPMENT PROJECT DIRECTORY
6101 Information System Upgrade E – 34
6001 Audio/Video System Upgrade E – 36
6003 Town-Wide Document Imaging Project E – 38
2305 Engineering Document Archiving E – 40
6305 Silicon Valley Regional Interoperability Project (SVRIP) Service E – 42
6103 EOC Communication Upgrade E – 44
6104 IT Disaster Recovery Improvements E – 46
6301 Computer-Aided Dispatch and Records Management System (CAD/RMS) E – 48
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 2
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 3
PROJECT LOCATIONS
A Building Replacement at Corporation Yard G Plaza Level Railing - Code Upgrade
B Facilities Assessment H Waterproofing Town-wide
C Library Carpet Replacement I Sound Mitigation in Library Lobby
D Town Beautification J Fire Suppression (Halon) for Server Room
E ADA Upgrade Public Restrooms – Adult Recreation
Building K Police Headquarters Roof Repair
F ADA Upgrade Staff Restroom – Civic Center L Adult Recreation Center – Floor Repair
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 4
PROGRAM SECTION DIRECTORY PAGE
2302 Building Replacement at Corporation Yard E – 6
2001 Facilities Assessment E – 8
2503 Library Carpet Replacement E – 10
2002 Town Beautification E – 12
2601 ADA Upgrade Public Restrooms – Adult Recreation Building E – 14
2117 ADA Restrooms and HR Offices E – 16
2116 Plaza Level Railing – Code Upgrade E – 18
2010 Waterproofing – Town-wide E – 20
2504 Sound Mitigation in Library Lobby E – 22
6004 Fire Suppression (Halon) for Server Rooms E – 24
2118 Police Headquarters Roof Repair E - 26
2206 Adult Recreation Center – Floor Repair E – 28
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 5
The Town Infrastructure & Facilities Projects section contains Capital Improvement Program projects that maintain or improve
the Town’s public buildings and structures to keep them in a clean, safe, and functional condition. Town-owned buildings
include the Civic Center, Library, Police Operations Center, Parks & Public Works Building, Corporation Yard and associated
structures, and the following buildings leased to other agencies: the Los Gatos-Saratoga Community Education and Recreation
headquarters building and the Adult Recreation Center (formerly the Neighborhood Center). Other Town facilities include
the Venue, Tait Avenue, and Forbes Mill.
Town Infrastructure and Facilities Projects are prioritized in consideration of the user needs, federal and state mandates,
federal and state grant restrictions, and local community standards. The Community Development Department assumes
responsibility for evaluating the overall conformance to the General Plan and the status of environmental assessment. The
Parks & Public Works Department assumes responsibility for project design, planning, and construction.
This section contains annual ongoing improvement projects as well as identified one-time projects. One-time infrastructure
and facilities projects are prioritized based on health and safety issues, infrastructure impacts, available funding sources,
project costs, and community needs.
Los Gatos does not have a designated funding source for repairing, maintaining, and improving the Town’s public facilities;
however, grants, CDBG funds, and donations are pursued and utilized when available.
TOWN INFRASTRUCTURE & FACILITIES PROJECTS SUMMARY
*Total FY 2019/20 Carryforward $1,975,285
Unfunded Projects
• Civic Center Improvements
• Deferred maintenance at Town-owned, leased properties
• Deferred improvements to Town-owned properties
Carryforward Projects
2302 Building Replacement at Corporation Yard 188,187$ 977,613$ 25,000$ 25,000$ 25,000$ 25,000$ 1,265,800$
2001 Facilities Assessment 24,142 80,000 - - - - 104,142
2503 Library Carpet Replacement - 56,500 - - - - 56,500
2002 Town Beautification 102,702 16,924 10,000 10,000 10,000 10,000 159,625
2601 ADA Upgrade Public Restrooms - Adult Recreation Building 51,882 250,000 - - - - 301,882
2504 Sound Mitigation in Library Lobby - 22,000 - - - - 22,000
2118 Police Headquarters Roof Repair 47,752 2,248 - - - - 50,000
2117 ADA Restrooms and HR Offices - 450,000 - - - - 450,000
6004 Fire Suppression (Halon) for Server Rooms - 200,000 - - - - 200,000
2116 Plaza Level Railings - Code Upgrade - 30,000 - - - - 30,000
2010 Waterproofing Town-wide - 75,000 - - - - 75,000
New Projects
2206 Adult Recreation - Floor Repair - 100,000 - - - - 100,000 - -
Total Infrastructure / Facility Projects 414,665$ 2,260,285$ 35,000$ 35,000$ 35,000$ 35,000$ 2,814,950$
2022/23
Budget
TOWN INFRASTRUCTURE & FACILITIES PROJECTS
Total
Budgeted
2023/24
Budget
Expended Through
2019/20
2020/21 Budget &
Carryfwd*
FY 2020/21 - 2024/25 CAPITAL IMPROVEMENT PROGRAM
2024/25
Budget
2021/22
Budget
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 6
Project Name
Building Replacement at Corporation Yard*
Project Number 821-2302
Department
Parks & Public Works Project Manager Facilities Manager: Dan Keller
*This project was presented to Council as part of the Capital Improvement Program in FY 2015/16. A portion of these funds
($200,000) for this project was transferred to provide funding for the Almond Grove Street Reconstruction project.
Description This project will replace an old building at the Parks and Public Works Department (PPW) Corporation
Yard that is used for office space and evidence storage.
Location This project is located at the PPW Corporation Yard (41 Miles Avenue).
Project
Background
The maintenance lead staff has been using a small portable building located at the north side of the
PPW Corporation Yard for their office facility. This building has deteriorated over the years and is
becoming more difficult to maintain because of its aging infrastructure. The existing building has
several problems including a leaky roof and windows, a poor heating and cooling (HVAC) system, and
lacks a restroom facility in the building. This building is also used partially by the Police Department as
their evidence storage facility. Evidence must be stored and kept at a certain room temperature, which
requires an updated HVAC system. To save costs, this project will relocate staffing to another building
and reconstruct the existing building for storage only.
Operating
Budget Impacts
This project will use staff time for construction inspection and management. Engineering staff time
associated with these projects will be charged to the project as it is delivered.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 7
Project
Components &
Estimated Timeline
Summer 2020 Design Project design & development
Fall 2020 Bid Process Project bidding & contract award
Winter 2021 Construction Project construction
Spring 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 75,942$ 112,245$ 952,613$ 25,000$ 977,613$ 25,000$ 25,000$ 25,000$ 25,000$ 1,265,800$
TOTAL SOURCE OF FUNDS 75,942$ 112,245$ 952,613$ 25,000$ 977,613$ 25,000$ 25,000$ 25,000$ 25,000$ 1,265,800$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 75,942 112,245 952,613 25,000 977,613 25,000 25,000 25,000 25,000 1,265,800
TOTAL GFAR 75,942$ 112,245$ 952,613$ 25,000$ 977,613$ 25,000$ 25,000$ 25,000$ 25,000$ 1,265,800$
BUILDING REPLACEMENT AT CORPORATION YARD Project 821-2302
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 8
TOWN-WIDE
Project Name Facilities Assessment
Project Number 821-2001
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will fund a consultant to assess the condition of Town facilities.
Location This project location is Town-wide.
Project
Background
This project will assess the condition of Town facilities to determine current condition of equipment
and building systems to assess priorities for repair versus replacements and to predict capital
expenditures needed year by year for life-cycle scheduled work and replacement.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 9
Project
Components &
Estimated Timeline
Winter 2020 Design Project design & development
Spring 2020 RFP Process Project RFP & contract award
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 24,142$ -$ 80,000$ -$ 80,000$ -$ -$ -$ -$ 104,142$
TOTAL SOURCE OF FUNDS 24,142$ -$ 80,000$ -$ 80,000$ -$ -$ -$ -$ 104,142$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - 80,000 - 80,000 - - - - 80,000
Project Construction Expenses 24,142 - - - - - - - - 24,142
TOTAL GFAR 24,142$ -$ 80,000$ -$ 80,000$ -$ -$ -$ -$ 104,142$
TOTAL USE OF FUNDS 24,142$ -$ 80,000$ -$ 80,000$ -$ -$ -$ -$ 104,142$
FACILITIES ASSESSMENT Project 821-2001
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 10
Project Name Library Carpet Replacement
Project Number 821-2503
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will replace large sections of the carpet squares in the children’s area that have started to
fail.
Location This project location is inside the Library at 100 Villa Avenue.
Project
Background
The carpet in the children’s area of the Library is starting to mat, lift, and stain from extensive foot
traffic, spilled food, and other accidents. This area of the Library is where the young kids play, listen to
stories, and congregate for different activities on the carpet. Replacements of the furniture upholstery
have occurred due to stains and failure, and this project will help complete the restoration of the space
back to a high service level.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 11
Project
Components &
Estimated Timeline
Winter 2019 Design Project design & development
Spring 2020 Bid Process Project bidding & contract award
Summer 2020 Construction Project construction
Summer 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR - - 56,500 - 56,500 - - - - 56,500
TOTAL SOURCE OF FUNDS -$ -$ 56,500$ -$ 56,500$ -$ -$ -$ -$ 56,500$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - 56,500 - 56,500 - - - - 56,500
Project Construction Expenses - - - - - - - - - -
TOTAL GFAR -$ -$ 56,500$ -$ 56,500$ -$ -$ -$ -$ 56,500$
TOTAL USE OF FUNDS -$ -$ 56,500$ -$ 56,500$ -$ -$ -$ -$ 56,500$
LIBRARY CARPET REPLACEMENT Project 821-2503
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 12
TOWN-WIDE
Project Name Town Beautification
Project Number 821-2002
Department Parks & Public Works Project Manager Environmental Specialist:
Marina Chislett
Description This project funds Town-wide beautification projects on an annual, as-needed basis.
Location This project location is Town-wide.
Project
Background
The Town Beautification Program was established to provide improvements to enhance the Town’s
beauty, particularly along public streets, sidewalks, and other Town property.
One example is the Town’s Outside the Box Program which enhances the character of the community
by adding artwork to utility boxes that are often targeted by graffiti vandals. Selected artwork contains
environmental sustainability messages that include: alternative transportation, clean energy, clean
creeks, community sustainability, and healthy lifestyles. In FY 2019/20 four utility boxes will be added
to bring the total to 25, and another four are planned in FY 2020/21.
Operating
Budget Impacts
The project will use staff time for program management and inspection. The staff time for this project
will be included in the department’s FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 13
Project
Components &
Estimated Timeline
Winter 2019 Artist
Recruitment
Project noticing
Summer 2020 Design Project submittals and development
Summer 2020 Installation Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 94,240$ 8,462$ 6,924$ 10,000$ 16,924$ 10,000$ 10,000$ 10,000$ 10,000$ 159,625$
TOTAL SOURCE OF FUNDS 94,240$ 8,462$ 6,924$ 10,000$ 16,924$ 10,000$ 10,000$ 10,000$ 10,000$ 159,625$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 94,240 8,462 6,924 10,000 16,924 10,000 10,000 10,000 10,000 159,625
TOTAL GFAR 94,240$ 8,462$ 6,924$ 10,000$ 16,924$ 10,000$ 10,000$ 10,000$ 10,000$ 159,625$
TOTAL USE OF FUNDS 94,240$ 8,462$ 6,924$ 10,000$ 16,924$ 10,000$ 10,000$ 10,000$ 10,000$ 159,625$
TOWN BEAUTIFICATION PROJECTS Project 821-2002
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 14
Project Name ADA Upgrade Public Restrooms – Adult
Recreation Building
Project Number 821-2601
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will make ADA-compliant upgrades to the public restrooms at the Recreation Building.
Location This project location is at the Adult Recreation Center at 208 E. Main Street.
Project
Background
The upstairs restrooms are beyond their useful life and are very small and non-ADA compliance. The
building serves seniors and having an accessible building is essential.
This project shows the use of Community Development Block Grant (CDBG) funds as a supplemental
funding source. The CDBG Entitlement Program provides grants on a formula basis to develop viable
urban communities by providing a suitable living environment, among other goals. The grant program
has specific requirements, and this is one of the few Town projects that meets the CDBG requirements.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/2021 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 15
Project
Components &
Estimated Timeline
Summer 2020 Design Project design & development
Fall 2020 Bid Process Project bidding & contract award
Spring 2021 Construction Project construction
Summer 2021 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Transfer from Facilities -$ -$ 183,000$ -$ 183,000$ -$ -$ -$ -$ 183,000$
GRANTS 51,882 - 67,000$ -$ 67,000$ - - - - 118,882$
TOTAL SOURCE OF FUNDS 51,882$ -$ 250,000$ -$ 250,000$ -$ -$ -$ -$ 301,882$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 183,000 - 183,000 - - - - 183,000
TOTAL GFAR -$ -$ 183,000$ -$ 183,000$ -$ -$ -$ -$ 183,000$
GRANTS & AWARDS
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - -
Consultant Services - - - - - - - - -
Project Construction Expenses 51,882 - 67,000 - 67,000 - - - - 118,882
TOTAL GRANTS & AWARDS 51,882 - 67,000 - 67,000 - - - - 118,882
TOTAL USE OF FUNDS 51,882$ -$ 250,000$ -$ 250,000$ -$ -$ -$ -$ 301,882$
ADA UPGRADE PUBLIC RESTROOMS - ADULT RECREATION BUILDING PROJECT 821-2601
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 16
Project Name ADA Restrooms and HR Offices
Project Number 821-2117
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will make ADA-compliant upgrades to the staff restrooms at the Civic Center and modify
the HR offices.
Location This project is located at the Civic Center (110 E. Main Street).
Project
Background
The Building Inspectors have moved out of their previous space in the lower level of the Civic Center.
The restrooms adjacent to this space are small non-ADA compliant restrooms. This project will upgrade
the restrooms taking advantage of the available space to meet additional area requirements. In
addition, this project will remodel the HR offices in the Civic Center.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 17
Project
Components &
Estimated Timeline
Winter 2019 Design Project design & development
Spring 2020 Bid Process Project bidding & contract award
Summer 2020 Construction Project construction
Summer 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -
Transfer from Facilities -$ -$ 300,000$ 150,000$ 450,000$ -$ -$ -$ -$ 450,000$
TOTAL SOURCE OF FUNDS -$ -$ 300,000$ 150,000$ 450,000$ -$ -$ -$ -$ 450,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 300,000 150,000 450,000 - - - - 450,000
TOTAL GFAR -$ -$ 300,000$ 150,000$ 450,000$ -$ -$ -$ -$ 450,000$
TOTAL USE OF FUNDS -$ -$ 300,000$ 150,000$ 450,000$ -$ -$ -$ -$ 450,000$
ADA RESTROOMS AND HR OFFICES Project 821-2117
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 18
Project Name Plaza Level Railings – Code Upgrade
Project Number 821-2116
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will adjust the railings around the upper deck of the Civic Center to be code compliant.
Location This project location is on the deck of Town Hall (110 E. Main Street).
Project
Background
The railings around the upper deck of the Civic Center have wide gaps that create a safety hazard with
a risk of children falling through the gaps. This project will adjust the railings to be code compliant.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 19
Project
Components &
Estimated Timeline
Fall 2019 Design Project design & development
Winter 2020 Bid Process Project bidding & contract award
Spring 2020 Construction Project construction
Summer 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
G FAR
Transfer from Facilities -$ -$ 30,000$ -$ 30,000$ -$ -$ -$ -$ 30,000$
TOTAL SOURCE OF FUNDS -$ -$ 30,000$ -$ 30,000$ -$ -$ -$ -$ 30,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
G FAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 30,000 - 30,000 - - - - 30,000
TOTAL GFAR -$ -$ 30,000$ -$ 30,000$ -$ -$ -$ -$ 30,000$
TOTAL USE OF FUNDS -$ -$ 30,000$ -$ 30,000$ -$ -$ -$ -$ 30,000$
PLAZA LEVEL RAILINGS - CODE UPGRADE Project 821-2116
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 20
TOWN-WIDE
Project Name Waterproofing -Town-wide
Project Number 821-2010
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will waterproof a balcony and a roof at two Town facilities.
Location The project is located at the Adult Recreation Center (208 E. Main Street) and the PPW Corporation
Yard at 41 Miles Avenue.
Project
Background
The roof of the engineering building at the PPW Corporation Yard is starting to show signs of age and
potential leakage as it approaches its end of serviceable life. Recent HVAC improvements added new
penetrations through this aging membrane, including relocation of a large HVAC unit in the center of
the roof. The new roof will upgrade the membrane to a single ply cool roof which will also improve the
building's energy conservation.
At the Adult Recreation Center, the rear balcony for the two manager offices upstairs cantilevers over
the activity room below. During heavy rainstorms, water leaks from under the thresholds upstairs into
the middle of the room below. The membrane needs to be replaced which entails significant
reconstruction of the sliding doors, siding, and balcony deck.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 21
Project
Components &
Estimated Timeline
Winter 2019 Design Project design & development
Spring 2020 Bid Process Project bidding & contract award
Summer 2020 Construction Project construction
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Transfer from Facilities -$ -$ 75,000$ -$ 75,000$ -$ -$ -$ -$ 75,000$
TOTAL SOURCE OF FUNDS -$ -$ 75,000$ -$ 75,000$ -$ -$ -$ -$ 75,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 75,000 - 75,000 - - - - 75,000
TOTAL GFAR -$ -$ 75,000$ -$ 75,000$ -$ -$ -$ -$ 75,000$
TOTAL USE OF FUNDS -$ -$ 75,000$ -$ 75,000$ -$ -$ -$ -$ 75,000$
WATERPROOFING - TOWN-WIDE Project 821-2010
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 22
Project Name Sound Mitigation in Library Lobby
Project Number 821-2504
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will install sound baffling to the low ceiling in the Library lobby.
Location This project location is inside the Library at 100 Villa Avenue.
Project
Background
This is the second phase of sound reduction in the Library following successful installation of doors to
the teen area in phase one. This project will install sound baffling to the ceiling in the Library lobby to
help diffuse noise.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 23
Project
Components &
Estimated Timeline
Winter 2020 Design Project design & development
Spring 2020 Bid Process Project bidding & contract award
Summer 2020 Construction Project construction
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Transfer from Library Trust -$ -$ 22,000$ -$ 22,000$ -$ -$ -$ -$ 22,000$
TOTAL SOURCE OF FUNDS -$ -$ 22,000$ -$ 22,000$ -$ -$ -$ -$ 22,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 22,000 - 22,000 - - - - 22,000
TOTAL GFAR -$ -$ 22,000$ -$ 22,000$ -$ -$ -$ -$ 22,000$
TOTAL USE OF FUNDS -$ -$ 22,000$ -$ 22,000$ -$ -$ -$ -$ 22,000$
SOUND MITAGATION IN LIBRARY LOBBY Project 821-2504
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 24
TOWN-WIDE
Project Name Fire Suppression (Halon) for Server
Rooms
Project Number 841-6004
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will install fire suppression systems that are specific for server rooms.
Location This project is located at the Civic Center (110 East Main Street) and the Town of Los Gatos Police
Operations Building (15900 Los Gatos Boulevard).
Project
Background
Basic fire suppression systems use water-based sprinklers to protect infrastructure. Server rooms
require different fire suppression to avoid damaging equipment in case the fire suppression is
triggered. This project will install non-destructive gas suppression systems at main server rooms at
essential facilities.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/2021 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 25
Project
Components &
Estimated Timeline
Spring 2020 Bid process Project bidding & contract award
Summer 2020 Construction Project Construction
Fall 2020 Completion Project completion
FIRE SUPPRESSION (HALON) FOR SERVER ROOMS
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -
Transfer from Facilities -$ -$ 200,000$ -$ 200,000$ -$ -$ -$ -$ 200,000$
TOTAL SOURCE OF FUNDS -$ -$ 200,000$ -$ 200,000$ -$ -$ -$ -$ 200,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - 200,000 - 200,000 - - - - 200,000
TOTAL GFAR -$ -$ 200,000$ -$ 200,000$ -$ -$ -$ -$ 200,000$
TOTAL USE OF FUNDS -$ -$ 200,000$ -$ 200,000$ -$ -$ -$ -$ 200,000$
Project 841-6004
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 26
Project Name Police Headquarters Roof Repair Project Number 821-2118
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will replace the Police Headquarters roof with a new membrane.
Location This project is located at the Police Headquarters building (110 East Main Street).
Project
Background
The roof for the Police Headquarters wing of the civic center has reached the end of its useful life. The
roof has a history of water leaks and since the removal of the HVAC system over the old dispatch center,
the leaks have increased. This project will replace the roof with a new roof membrane to match the
museum wing roof completed in 2017.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 27
Project
Components &
Estimated Timeline
Winter 2019 Bid process Project bidding & contract award
Spring 2020 Construction Project Construction
Summer 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Transfer from Facilities -$ 47,752$ 2,248$ -$ 2,248$ -$ -$ -$ -$ 50,000$
TOTAL SOURCE OF FUNDS - 47,752 2,248 - 2,248 - - - - 50,000
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - 47,752 2,248 - 2,248 - - - - 50,000
TOTAL GFAR - 47,752 2,248 - 2,248 - - - - 50,000
TOTAL USE OF FUNDS - 47,752 2,248 - 2,248 - - - - 50,000
POLICE HEADQUARTERS ROOF REPAIR 821-2118
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 28
Project Name Adult Recreation Center – Floor
Repair
Project Number 821-2206
Department Parks & Public Works Project Manager Facilities Manager: Dan Keller
Description This project will replace the flooring in the multi-purpose room at the Adult Recreation Center.
Location This project will take place at the Adult Recreation Center (208 East Main Street).
Project
Background
The floor at the Adult Recreation Center has reached the end of its useful life. This project will replace
the floor.
Operating
Budget Impacts
The project will use staff time for construction management and inspection. The staff time for this
project will be included in the department’s FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 29
Project
Components &
Estimated Timeline
Winter 2020 Bid process Project bidding & contract award
Spring 2021 Construction Project Construction
Summer 2021 Completion Project completion
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR -$ -$ 100,000$ 100,000$ -$ -$ -$ -$ 100,000$
TOTAL SOURCE OF FUNDS -$ -$ 100,000$ 100,000$ -$ -$ -$ -$ 100,000$
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - -
Consultant Services - - - - - - - - -
Project Construction Expenses - - 100,000 100,000 - - - - 100,000
TOTAL GFAR -$ -$ 100,000$ 100,000$ -$ -$ -$ -$ 100,000$
TOTAL USE OF FUNDS -$ -$ 100,000$ 100,000$ -$ -$ -$ -$ 100,000$
ADULT RECREATION CENTER - FLOOR REPAIR 821-2206
PROPOSED PUBLIC FACILITIES PROGRAM
Town Infrastructure & Facilities Projects
E - 30
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 31
PROJECT LOCATIONS
A Information System Upgrade
B Audio/Video System Upgrade
C Town-Wide Document Imaging Project
D Engineering Document Archiving
E
Silicon Valley Regional Interoperability Project (SVRIP)
Service
F EOC Communication Upgrade
G IT Disaster Recovery Improvements
H
Computer-Aided Dispatch and Records Management
System (CAD/RMS)
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 32
PROGRAM SECTION DIRECTORY PAGE
6101 Information System Upgrade E – 34
6001 Audio/Video System Upgrade E – 36
6003 Town-Wide Document Imaging Project E – 38
2305 Engineering Document Archiving E – 40
6305 Silicon Valley Regional Interoperability Project (SVRIP) Service E – 42
6103 EOC Communication Upgrade E – 44
6104 IT Disaster Recovery Improvements E – 46
6301 Computer-Aided Dispatch and Records Management System (CAD/RMS) E – 48
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 33
The Equipment Projects section contains Capital Improvement Program projects that provide new equipment; or replace,
improve, or upgrade existing Town equipment.
This section does not have ongoing equipment programs; all projects are considered one-time projects. One-time equipment
capital improvement projects are prioritized based on service level considerations, available funding sources, project costs,
and community impacts.
Los Gatos does not have a designated funding source for new equipment or the replacement or upgrading of existing
equipment; however, grants are pursued and utilized when available.
EQUIPMENT PROJECTS SUMMARY
Total FY 2019/20 Carryforward $921,291
Carryforward Projects
6101 Information System Upgrade 292,528$ 77,026$ -$ -$ -$ -$ 369,554$
6001 Audio/Video System Upgrade 68,048 42,552 - - - - 110,600
6003 Town-wide Document Imaging Project 198,011 16,990 - - - - 215,000
2305 Engineering Document Archiving 48,284 11,716 - - - - 60,000
6305 Silicon Valley Regional Interoperability Project (SVRIP) Service 395,661 62,967 - - - - 458,628
6103 EOC Communications Upgrade 20,618 29,382 - - - - 50,000
6104 IT Disaster Recovery Improvements 30,155 169,845 - - - - 200,000
6301 Computer-Aided Dispatch and Records Management System 24,476 510,814 - - - - 535,290 New Projects
Total Equipment Projects 1,077,781$ 921,291$ -$ -$ -$ -$ 1,999,072$
2020/21 Budget &
Carryfwd*
FY 2020/21 - 2024/25 CAPITAL IMPROVEMENT PROGRAM
Total
Budgeted
2021/22
Budget
2022/23
Budget
2023/24
Budget
2024/25
Budget
EQUIPMENT PROJECT SUMMARY BY PROGRAM
Expended Through
2019/20
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 34
Project Name Information System Upgrade Project Number 841-6101
Department Finance Project Manager Finance Director: Stephen
Conway
Description This project upgrades the Town’s existing financial/human resources information database, enhancing
its reporting system and providing future web-based online services. This project will be coordinated
with the upgrade of the Town’s existing permit tracking system.
Location The project will enhance the information systems used by the Finance, Human Resources, and Building
Departments. Purchased computer hardware will be located in the IT Department, 110 E. Main Street.
Project
Background
In FY 2008/09, staff completed a significant portion of a multi-year financial information system
upgrade. This project involved the conversion of General Ledgers, Payroll, Budget, and Human
Resources modules, followed by the implementation of the Cashiering and Business License modules.
Planned for FY 2020/21 required system upgrade, cloud hosting, online-timesheet management,
completion of the fixed asset module, and continuation of electronic commerce, including online
permitting and business license applications.
Operating
Budget Impacts
The remaining project balance is estimated to be $77,026. It is anticipated that the maintenance costs
for the Finance/Human Resources information system would be approximately $40,000 annually,
which has been incorporated into the FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 35
Project
Components &
Estimated Timeline
Spring 2020 System
Implementation
Upgrade and test data migration and functionality of
financial/human resources information database.
Fall 2020 System
Implementation
Develop and test fixed assets, electronic commerce and
electronic timesheet functions.
Summer 2020 Implement data migration
Fall 2020 System
Implementation
Implementation of electronic commerce and electronic
timesheet functions.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Transfer from MIS 188,975$ 103,553$ 77,026$ -$ 77,026$ -$ -$ -$ -$ 369,554$
TOTAL SOURCE OF FUNDS 188,975$ 103,553$ 77,026$ -$ 77,026$ -$ -$ -$ -$ 369,554$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services 188,975 103,553 77,026 - 77,026 - - - - 369,554
Project Construction Expenses - - - - - - - - - -
TOTAL GFAR 188,975$ 103,553$ 77,026$ -$ 77,026$ -$ -$ -$ -$ 369,554$
TOTAL USE OF FUNDS 188,975$ 103,553$ 77,026$ -$ 77,026$ -$ -$ -$ -$ 369,554$
INFORMATION SYSTEM UPGRADE Project 841-6101
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 36
Project Name Audio/Video System Upgrade Project Number 841-6001
Department Town Manager Project Manager IT Manager: Chris Gjerde
Description This project provides for the replacement and/or upgrade of Council Chamber video, audio/visual, and
other applicable equipment used for televised and non-televised public meetings.
Location The video production system is located in the audio/video equipment room at the Civic Center, 110 E.
Main Street, and involves various electronic equipment required to cablecast public meetings and
make presentations.
Project
Background
In FY 2008/09, the audio/visual equipment located in the Town Council Chambers was upgraded to
meet the needs at that time. The maintenance of the video production equipment is now the
responsibility of KCAT, who receives Public, Educational, and Governmental (PEG) fees, provided by
local cable operators for this purpose. The remaining funds in this project will be used to replace and/or
upgrade the Town’s A/V equipment in the Council Chambers, as needed. Staff will also explore the
availability of additional audio/visual meeting management enhancements.
Operating
Budget Impacts
This Audio/Video System Upgrade project is funded in the GFAR Fund. It is unknown at this time which
replacements or upgrades will be required during FY 2020/21. Staff oversight of this project will be
included in the FY 2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 37
Project
Components &
Estimated
Timeline
Fiscal Year
2020/21
Monitoring
As needed.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 68,048$ -$ 42,552$ -$ 42,552$ -$ -$ -$ -$ 110,600$
TOTAL SOURCE OF FUNDS 68,048$ -$ 42,552$ -$ 42,552$ -$ -$ -$ -$ 110,600$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment 68,048 - 42,552 - 42,552 - - - - 110,600
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses - - - - - - - - - -
TOTAL GFAR 68,048$ -$ 42,552$ -$ 42,552$ -$ -$ -$ -$ 110,600$
TOTAL USE OF FUNDS 68,048$ -$ 42,552$ -$ 42,552$ -$ -$ -$ -$ 110,600$
AUDIO / VIDEO SYSTEM UPGRADE Project 841-6001
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 38
Project Name Town-Wide Document Imaging Project Project Number 841-6003
Department Community Development/Police Project Manager Community Development
Director: Joel Paulson
Description This is the continuation of the first phase of a Town-wide project to convert existing microfiche and
paper files to electronic storage and provide desktop access.
Location Town of Los Gatos Civic Center complex (110 E. Main Street).
Project
Background
The Community Development Department has an immediate need to provide electronic storage and
retrieval of many archived documents. The electronic retrieval system will allow immediate access to
all building and planning files for members of the Community Development Department via desktop
access. Following implementation, priorities will be identified to expand document imaging to other
departments, subject to available funding.
Operating
Budget Impacts
The Community Development Department collects permit fees, a portion of which will be used to offset
some costs for document storage.
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 39
Project
Components &
Estimated Timeline
FY 2020/21 Production Continue document conversion of Building and Planning
Division files.
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Transfer from MIS 198,011$ -$ 16,990$ -$ 16,990$ -$ -$ -$ -$ 215,000$
TOTAL SOURCE OF FUNDS 198,011$ -$ 16,990$ -$ 16,990$ -$ -$ -$ -$ 215,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 198,011 - 16,990 - 16,990 - - - - 215,000
TOTAL GFAR 198,011$ -$ 16,990$ -$ 16,990$ -$ -$ -$ -$ 215,000$
TOTAL USE OF FUNDS 198,011$ -$ 16,990$ -$ 16,990$ -$ -$ -$ -$ 215,000$
TOWN-WIDE DOCUMENT IMAGING PROJECT Project 841-6003
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 40
HW
Y
9
E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV
Project Name Engineering Document Archiving
Project Number 821-2305
Department Parks & Public Works Project Manager Assistant PPW Director: Lisa
Petersen
Description This project will scan and archive all engineering record documents such as as-builts, federal and state
funded capital improvement projects, and recorded documents, all of which are currently stored in
paper format.
Location This project is located at the Engineering Services office (41 Miles Avenue).
Project
Background
Currently, most files are kept in a hard copy format in the Engineering Services office. These hard
copies have become damaged due to age and need to be preserved through archiving to maintain
pertinent records. By digitally archiving these documents, searching through records becomes much
more efficient. It is anticipated that this project will be implemented over several fiscal years, starting
in FY 2014/15 and completion estimated in FY 2020/21.
Operating
Budget Impacts
This project will use staff time for management. The staff time for this project is included in the
Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 41
Project
Components &
Estimated Timeline
Summer 2015 Design Project development
Fall 2015 Bid process Project bidding & contract award
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 8,284$ 40,000$ 11,716$ -$ 11,716$ -$ -$ -$ -$ 60,000$
TOTAL SOURCE OF FUNDS 8,284$ 40,000$ 11,716$ -$ 11,716$ -$ -$ -$ -$ 60,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 8,284 40,000 11,716 - 11,716 - - - - 60,000
TOTAL GFAR 8,284$ 40,000$ 11,716$ -$ 11,716$ -$ -$ -$ -$ 60,000$
TOTAL USE OF FUNDS 8,284$ 40,000$ 11,716$ -$ 11,716$ -$ -$ -$ -$ 60,000$
ENGINEERING DOCUMENT ARCHIVING Project 821-2305
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 42
Project Name Silicon Valley Regional Interoperability
Project (SVRIP) Service
Project Number 841-6305
Department Police Project Manager Captain D’Antonio
Description This project will update the existing police radio system infrastructure to be compatible with the
regional interoperability requirements.
Location Town of Los Gatos Civic Center Complex (110 E Main Street) and the Town of Los Gatos Police
Operations Building (15900 Los Gatos Boulevard).
Project
Background
The Silicon Valley Radio Interoperability Authority (SVRIA) in conjunction with the City Managers
Association and the County Chiefs Association is moving towards a program for regional
interoperability of public safety communications for police, fire services, and public works across all
jurisdictions. The Police Department, in conjunction with other public safety agencies within Santa
Clara County, will be contributing to radio system infrastructure for a period of three years to allow for
interoperability of public safety communications regionally.
Operating
Budget Impacts
Staff oversight of this SVRIP project will be included in the Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 43
Project
Components &
Estimated Timeline
Summer 2015 Design Project development
Winter 2016 Bid process Project bidding & contract award
Summer 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 395,176$ 486$ 62,967$ -$ 62,967$ -$ -$ -$ -$ 458,628$
TOTAL SOURCE OF FUNDS 395,176$ 486$ 62,967$ -$ 62,967$ -$ -$ -$ -$ 458,628$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 395,176 486 62,967 - 62,967 - - - - 458,628
TOTAL GFAR 395,176$ 486$ 62,967$ -$ 62,967$ -$ -$ -$ -$ 458,628$
TOTAL USE OF FUNDS 395,176$ 486$ 62,967$ -$ 62,967$ -$ -$ -$ -$ 458,628$
SILICON VALLEY REGIONAL INTEROPERABILITY PROJECT (SVRIP) SERVICE Project 841-6305
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 44
TOWN-WIDE
Project Name EOC Communications Upgrade Project Number 841-6103
Department Town Manager Office/IT/PD Project Manager Assistant Town Manager, Arn
Andrews
Description This project upgrades identified deficiencies in the Town’s Emergency Operations Center (EOC)
communication capabilities.
Location The project will enhance the communication systems within the EOC to create better interoperability
between Town staff, Public Safety and citizen volunteers in the event of an emergency.
Project
Background
The recent wildfire disasters in California and lessons learned from prior Town emergency
preparedness exercises continue to identify a lack of adequate communications as a major flaw in
emergency responses. Without robust EOC communication capabilities the situational awareness
necessary to adequately assess, and respond to, an operational area in the event of an emergency is
severely compromised. Staff is seeking to create multiple seamless communication channels between
the Town EOC, County EOC, Town Public Safety staff, Town PPW staff, Town CDD staff, and CERT
volunteers.
Operating
Budget Impacts
This project will use staff time for management. The staff time for this project is included in the FY
2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 45
Project
Components &
Estimated Timeline
Summer 2018 Design Project development
Fall 2018 Procurement Procurement of equipment and installation
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR 19,618$ 1,000$ 29,382$ -$ 29,382$ -$ -$ -$ -$ 50,000$
TOTAL SOURCE OF FUNDS 19,618$ 1,000$ 29,382$ -$ 29,382$ -$ -$ -$ -$ 50,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 19,618 1,000 29,382 - 29,382 - - - - 50,000$
TOTAL GFAR 19,618$ 1,000$ 29,382$ -$ 29,382$ -$ -$ -$ -$ 50,000$
TOTAL USE OF FUNDS 19,618$ 1,000$ 29,382$ -$ 29,382$ -$ -$ -$ -$ 50,000$
EOC COMMUNICATION UPGRADE Project 841-6103
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 46
TOWN-WIDE
Project Name IT Disaster Recovery Improvements Project Number 841-6104
Department IT Project Manager IT Manager: Chris Gjerde
Description This project upgrades the Town’s existing Information Technology infrastructure including windows
servers, storage, and network switches.
Location The project will enhance the IT systems used by all Town departments at all locations. Purchased
computer hardware will be located at 110 E. Main Street and 15900 Los Gatos Boulevard
Project
Background
Annually staff evaluates and replaces older servers and network infrastructure to ensure reliable
operation. In FY 2017/18, staff began an IT disaster recovery inventory, identifying many areas to
improve our disaster preparedness posture and increasing efficiencies with more modern
infrastructure design. These improvements to IT infrastructure require more than a simple staggered
replacement of a small percentage of servers. Improvements include Hypervisor Server Clusters and
Replication, redundant Storage Area Networks, and Public Cloud DR Data Center.
Operating
Budget Impacts
This project will use staff time for management. The staff time for this project is included in the FY
2020/21 Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 47
Project
Components &
Estimated Timeline
Summer 2019 Design Project development
Fall 2019 Procurement Procurement of equipment and installation
Fall 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed Total Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Transfer from MIS 7,942$ 22,213$ 169,845$ -$ 169,845$ -$ -$ -$ -$ 200,000$
TOTAL SOURCE OF FUNDS 7,942$ 22,213$ 169,845$ -$ 169,845$ -$ -$ -$ -$ 200,000$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 7,942 22,213 169,845 - 169,845 - - - - 200,000
TOTAL GFAR 7,942$ 22,213$ 169,845$ -$ 169,845$ -$ -$ -$ -$ 200,000$
TOTAL USE OF FUNDS 7,942$ 22,213$ 169,845$ -$ 169,845$ -$ -$ -$ -$ 200,000$
IT DISASTER RECOVERY IMPROVEMENTS Project 841-6104
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 48
Project Name Computer-Aided Dispatch and Records
Management System (CAD/RMS)
Project Number 841-6301
Department Police Project Manager Captain D’Antonio
Description This project upgrades the Police Departments current Computer Aided Dispatch and Records
Management System (CAD/RMS).
Location This project is located at Police Administration Building.
Project
Background
The Los Gatos Monte Sereno Police Department has an immediate need to replace its Computer Aided
Dispatch and Records Management System (CAD/RMS). The Los Gatos Monte Sereno Police
Department and the City of Sunnyvale have been in a cost sharing agreement since October 2016, and
the Town needs an independent system.
The Department seeks an integrated solution that offers the capability to comply with existing and
upcoming mandates, capture ongoing statistical data, accurately measure performance, better equip
first responders with relevant information, reduce report writing time, enhance internal cross-training,
and be technologically progressive. Enhancements will give CAD/RMS terminal access to sworn and
non-sworn support personnel, including physical access at two sites and mobile access in 14 vehicles.
Operating
Budget Impacts
This project will use staff time for management. The staff time for this project is included in the
Operating Budget.
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 49
Project
Components &
Estimated Timeline
Spring 2019 Bid process Project bidding & contract award
Fall 2019 Procurement Procurement of equipment and installation
Summer 2020 Completion Project completion
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
SOURCE OF FUNDS to 2020/21 (with Carryfwd)
GFAR
Transfer from Equipment Replacement 10,290$ 14,186$ 510,814$ -$ 510,814$ -$ -$ -$ -$ 535,290$
TOTAL SOURCE OF FUNDS 10,290$ 14,186$ 510,814$ -$ 510,814$ -$ -$ -$ -$ 535,290$
Prior Yrs
Actuals
2019/20
Estimated
Estimated
Carryfwd
2020/21
New Funding
2020/21
Budget
2021/22
Proposed
2022/23
Proposed
2023/24
Proposed
2024/25
Proposed
Total
Project
USE OF FUNDS to 2020/21 (with Carryfwd)
GFAR `
Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$
Services/Supplies/Equipment - - - - - - - - - -
Site Acquisition & Preparation - - - - - - - - - -
Consultant Services - - - - - - - - - -
Project Construction Expenses 10,290 14,186 510,814 - 510,814 - - - - 535,290
TOTAL GFAR 10,290$ 14,186$ 510,814$ -$ 510,814$ -$ -$ -$ -$ 535,290$
TOTAL USE OF FUNDS 10,290$ 14,186$ 510,814$ -$ 510,814$ -$ -$ -$ -$ 535,290$
COMPUTER-AIDED DISPATCH AND RECORDS MANAGEMENT SYSTEM Project 841-6301
PROPOSED PUBLIC FACILITIES PROGRAM
Equipment Projects
E - 50