Proposed 5 Year CIP - Staff Report and Exhibit 1 PREPARED BY: JOEL PAULSON Community Development Director Reviewed by: Finance Director and Parks and Public Works Director 110 E. Main Street Los Gatos, CA 95030 ● 408-354-6874 www.losgatosca.gov TOWN OF LOS GATOS PLANNING COMMISSION REPORT MEETING DATE: 04/25/2018 ITEM NO: 5 DATE: APRIL 20, 2018 TO: PLANNING COMMISSION FROM: JOEL PAULSON, COMMUNITY DEVELOPMENT DIRECTOR SUBJECT: DRAFT PROPOSED FIVE YEAR CAPITAL IMPROVEMENT PROGRAM FOR FISCAL YEARS 2018/19 TO 2022/23 RECOMMENDATION: Forward a recommendation of approval to Town Council for the FY 2018/19 - 2022/23 draft proposed Capital Improvement Program (CIP). CEQA: The project is Categorically Exempt pursuant to the adopted Guidelines for the Implementation of the California Environmental Quality Act, Section 15061(b)(3), in that it can be seen with certainty that there is no possibility that this CIP action will have a significant effect on the environment, and does not involve approval of any specific project that may have a significant effect on the environment. Each project of the CIP will be evaluated and as applicable each project will conduct the appropriate level of environmental analysis. FINDINGS:  As required, pursuant to the adopted Guidelines for the Implementation of the California Environmental Quality Act, this project is Exempt, Section 15061(b)(3).  That the potential projects in the 2018/19 - 2022/23 draft proposed CIP are consistent with the General Plan, North 40 Specific Plan, Albright Specific Plan, and Hillside Specific Plan. PAGE 2 OF 3 SUBJECT: DRAFT PROPOSED FIVE YEAR CAPITAL IMPROVEMENT PROGRAM FOR FISCAL YEARS JULY 1, 2018 TO JUNE 30, 2023 APRIL 20, 2018 N:\DEV\PC REPORTS\2018\CIP.docx 4/19/2018 12:30 PM ACTION: Forward a recommendation of approval to Town Council for the 2017/18 - 2021/22 draft proposed CIP. DISCUSSION: Section 65401 of the Government Code requires that when a town or city has adopted a General Plan, all proposed public works projects be classified into a coordinated program and submitted to the Planning Commission for review. The Commission is required to report to the Town Council on the conformity of the program with the adopted General Plan and any adopted specific plans. The draft proposed CIP is a five-year program identifying potential investments to the Town’s roads, parks, and other facilities to maintain and/or enhance the infrastructure supporting Los Gatos residents and businesses. The draft proposed CIP is evaluated annually to ensure the mix of potential projects and their timing respond to the ever-changing needs of the community. The draft proposed CIP also reflects a budget forecast that reflects realistic revenue sources. The draft proposed CIP (Exhibit 1) includes potential capital projects proposed for construction during the next five years, 2018/19 - 2021/22. Projects are classified under three programs: Streets; Parks; and Public Facilities. The draft proposed Streets Program implements the General Plan’s Transportation Goals and Policies. Examples of potential street projects within the Streets Program are new crosswalks, bike lanes, and pedestrian improvements as well as annual maintenance projects. The General Plan Open Space, Parks, and Recreation Goals and Policies are implemented through the potential park improvement projects such as park upgrades. The Town’s sustainability goals and policies are being implemented through a variety of potential CIP projects, such as energy efficiency upgrades at Town facilities and stormwater upgrades. Matt Morley, Director of Parks & Public Works, will be available to answer any questions at the meeting. The scope of the Commission’s review is to determine that the draft is consistent with the General Plan, North 40 Specific Plan, Albright Specific Plan, and Hillside Specific Plan. PUBLIC COMMENTS: At this time, the Town has not received any public comment. PAGE 3 OF 3 SUBJECT: DRAFT PROPOSED FIVE YEAR CAPITAL IMPROVEMENT PROGRAM FOR FISCAL YEARS JULY 1, 2018 TO JUNE 30, 2023 APRIL 20, 2018 N:\DEV\PC REPORTS\2018\CIP.docx 4/19/2018 12:30 PM RECOMMENDATION: The Town Council is tentatively scheduled to consider the draft proposed CIP on May 15, 2018. For the reasons stated above, staff recommends that the Planning Commission take the following actions: 1. Receive public testimony; 2. Find that the project is Exempt pursuant to the adopted Guidelines for the Implementation of the California Environmental Quality Act, Section 15061(b)(3); 3. Find that the potential projects in the 2018/19 - 2022/23 draft proposed CIP are consistent with the General Plan, North 40 Specific Plan, Albright Specific Plan, and Hillside Specific Plan; and 4. Recommend that the Town Council approve the 2018/19 - 2022/23 draft proposed CIP. EXHIBIT: 1. Town of Los Gatos Draft Proposed Capital Improvement Projects for Fiscal Years 2018/19 - 2022/23 This Page Intentionally Left Blank Streets Program EXHIBIT 1 STREETS PROGRAM DIRECTORY PROPOSED C-1 STREET RECONSTRUCTION AND RESURFACING PROJECTS PAGE 9901 Street Repair & Resurfacing C – 6 0003 Almond Grove Street Rehabilitation Project C – 10 STREET REPAIRS, MAINTENANCE & SAFETY PROJECTS 9910 Traffic Calming Projects C – 16 9921 Curb, Gutter & Sidewalk Maintenance C – 18 9930 Retaining Wall Repairs C – 20 9902 Annual Street Restriping C – 22 0120 Guardrail Replacement Projects C – 24 0125 Crosswalk Improvements at Santa Cruz Avenue/Blossom Hill Road C – 26 0126 Crosswalk Lighting Upgrade C – 28 STREET IMPROVEMENT PROJECTS 0202 Highway 9/University Avenue Intersection Improvements C – 34 0213 Los Gatos Boulevard/Shannon Road Improvements C – 36 0214 Monument Control Network Update C – 38 0705 Downtown Parking Lots Seal Coat & Restriping C – 40 0409 Hernandez Avenue Storm Drain Improvements C – 42 0212 Blossom Hill Road/Cherry Blossom Lane Intersection Improvements C – 44 0704 224 West Main Property Acquisition (Parking Lot 6) C – 46 0218 Sidewalk Improvements/Shannon/Los Gatos Blvd/Cherry Blossom C – 48 0219 Stonybrook Road & Kennedy Road Sidewalk Improvements C – 50 0221 Sidewalk Improvements – Multiple Locations C – 52 0224 LED Streetlights C – 54 0225 Utility Undergrounding Improvements C – 56 0229 Cut – Through Traffic Mitigation C – 58 0230 Traffic Signal Modernization C – 60 0410 Bicknell Road Storm Drain Improvements C – 62 0231 Bicycle & Pedestrian Improvements C – 64 0413 Stormwater Master Plan C – 66 0414 Stormwater System – Pollution Prevention Compliance C – 68 0232 Public Arts Gateway Project C – 70 0415 Jones Road Strom Drain Improvements C – 72 0233 Downtown Parking Study C – 74 0234 One-Way Downtown Street Pilot C – 76 0420 Annual Storm Drain Improvements C – 78 0128 Pilot School Busing Program C – 80 0803 Highway 17 Bicycle & Pedestrian Bridge C – 82 BRIDGE PROJECTS 0801 Quito Road – Bridge Replacement C – 88 PROPOSED STREETS PROGRAM C - 2 PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 3 PROJECT LOCATIONS A Street Repair & Resurfacing B Almond Grove Street Rehabilitation Project LO S G A T O S - S A R A T O G A R D LOS GATOS BLVDE MAIN STHWY 17HWY 17N SANTA CRUZ AVWINCHESTER BLVDBLOSSOM HILL RDLOS GATOS BLVDHW Y 8 5 KENNE D Y R D SHA N N O N R D LA R K A V LOS GATOS-ALMADEN RD UNIVERSITY AVWEDGEWOOD KNOWLES B "A" IS A TOWN-WIDE PROJECT HICKSRD PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 4 PROGRAM SECTION DIRECTORY PAGE 9901 Street Repair & Resurfacing C – 6 0003 Almond Grove Street Rehabilitation Project C – 10 PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 5 The Streets Program’s Street Reconstruction & Resurfacing section contains Capital Improvement Program projects that resurface or repave the Town’s streets as the primary scope of work. Projects may also encompass minor components of streetscape or street improvements; however, to be categorized in the Street Reconstruction & Resurfacing section, projects must have pavement rehabilitation as their main purpose. Safety issues, traffic levels, the Pavement Condition Index, available funding sources, project costs, and community impacts are all considerations in prioritizing Street Reconstruction & Resurfacing projects in the five-year Capital Improvement Program. This section contains an annual ongoing street rehabilitation project as well as an identified one-time project. The dedicated ongoing funding sources for street repair are the Gas Tax, which was recently increased by SB 1, and Proposition 42, which total approximately $1.2 million for FY 2018/19. In addition, Countywide Measure B (Nov 2016) increased the sales tax by ½ cent for 30 years to fund transportation related projects. One part of 2016 Measure B is a formulaic distribution of funds for roadway maintenance. The Los Gatos annual allocation would be $580,633. However, Measure B funds have been delayed due to a legal challenge to the ballot measure. Staff anticipates the funds should become available in FY 2018/19. Additional sources include grant funding, if secured, such as state programs that focus on funding specific street categories or that funds rehabilitation of specific arterial or collector streets. Other than the funds mentioned above, Los Gatos has limited designated funding sources for maintaining the Town’s roadway system. The Town has a Construction Impact Fee, which is expected to generate approximately $110,000 annually and a Refuse Vehicle Road Impact Fee for additional street and roadway repairs due to the disproportionate amount of wear and tear caused by construction and other heavy vehicles (estimated $490,000). STREET RECONSTRUCTION & RESURFACING PROJECTS SUMMARY * Total FY 2017/18 Carryforward $11,098,348 Carryforward Projects 9901 Street Repair & Resurfacing 12,122,615$ 4,393,954$ 2,412,226$ 2,496,447$ 2,616,447$ 2,616,447$ 26,658,136$ 0003 Almond Grove Street Rehabilitation 5,138,797 9,053,161 - - - - 14,191,959 New Projects Total Street Reconstruction Projects 17,261,413$ 13,447,115$ 2,412,226$ 2,496,447$ 2,616,447$ 2,616,447$ 40,850,095$ 2021/22 Budget 2019/20 Budget 2020/21 Budget STREET RECONSTRUCTION PROJECTS Total Budgeted 2018/19 Budget & Carryfwd* 2022/23 Budget Expended Through 2017/18 FY 2018/19- 2022/23 CAPITAL IMPROVEMENT PROGRAM PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 6 Town Wide Project Name Street Repair & Resurfacing Project Number 811-9901 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This is an ongoing annual project for street rehabilitation throughout Town to enhance vehicle safety and to maintain the Town’s roadway infrastructure. Location This project occurs in various locations including Town-wide arterials, collectors, and neighborhood streets. To meet the SB1 requirements, every year the Council adopts a resolution identifying the streets needing repair. The final streets for the current construction season are identified at the time the specifications are brought forward for Council approval, which generally occurs in the spring. Project Background Street rehabilitation projects are identified and prioritized according to pavement quality reflected by the Pavement Condition Index (PCI), field inspection, traffic level, and safety issues. Every four years, the Town conducts a full assessment on the condition of the streets through a consultant who specializes in the field. This assessment is funded through a grant from the Metropolitan Transportation Commission. The PCI information that results from the survey feeds into a street maintenance software program called StreetSaver. Every jurisdiction in the Bay Area uses the same program and methodology, making it the best practice in the industry. With the PCI information in the StreetSaver database, the program can provide future high level maintenance programs for the Town. The program emphasizes maintaining streets that have a good (above 70) PCI at that level as ongoing preventive maintenance is more cost efficient than allowing streets to reach lower PCI levels. As with many computer-generated reports, the output requires some validation and adjustment. Staff conducts this element of the work through field observations and consideration of project proximity, all with an eye towards maximizing the value to the Town. The resulting list, sized to the available budget, creates the annual list of streets for this project. Historically, the Town invested approximately $11.7 million from FY 2000/01 to FY 2007/08 to address the backlog of deferred street maintenance. This investment raised the average PCI of Town streets from 64 in 2001 to nearly 74 in 2008. Due to budget challenges that followed, Town streets have been resurfaced by the application of a rubber cape seal or a slurry seal. This method is typically utilized for streets in better condition to provide a seal to the surface below. The solution is cost effective and can provide some limited protection to streets in worse condition, but for a shorter timeframe. TOWN-WIDE PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 7 For the streets with a lower PCI, an asphalt overlay is often the preferred solution with the best return on investment over time. Costs are much higher for this solution. Given the small amount of asphalt overlay work performed, and decreased funding from FY 2008/09 to FY 2015/16 of $9.9 million, the Town’s PCI dropped from 74 to 69 between 2008 and 2010, and has further decreased to its current level of 67. To mitigate this decline, the Town has focused its resources on arterials and collector streets, and has used a rubber cape seal and slurry seal approach to slow the decline of the PCI rating. This approach was the most economical and prudent treatment to resurface several residential neighborhoods. The dedicated ongoing funding sources for street repair are the Gas Tax, which was recently increased by SB 1, and Proposition 42, which total approximately $1,200,000 for FY 2018/19. In November 2016, voters passed Countywide Measure B. This Measure increased the sales tax by ½ cent for 30 years to fund transportation related projects. One part of 2016 Measure B is a formulaic distribution of funds for roadway maintenance. The Los Gatos annual allocation would be $580,633. The distribution of funds is awaiting resolution of a legal challenge. As part of a voter-approved measure from 2010, the Santa Clara Valley Transportation Agency (VTA) assesses a $10 per vehicle registration surcharge to repair and rehabilitate streets. Eighty percent of the revenues collected by the VTA are returned to the local municipality in which they were generated. The remaining twenty percent is used for regional and County-wide projects. This funding source is expected to generate approximately $180,000 annually for Los Gatos, which will be used for street rehabilitation Town-wide. Other than the annual revenues mentioned above, Los Gatos has limited designated funding sources for maintaining the Town’s roadway system. The Town has a Construction Impact Fee, which is expected to generate approximately $110,000 annually and a Refuse Vehicle Road Impact Fee for additional street and roadway repairs due to the disproportionate amount of wear and tear caused by construction and other heavy vehicles (estimated $490,000). Operating Budget Impacts Conducting preventive maintenance on the Town’s roadways extends the life of the streets and reduces the need for extensive reconstruction in the future, reducing staff time spent on road maintenance. Engineering staff time for project design and oversight is addressed in the FY 2018/19 Operating Budget. PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 8 Project Components & Estimated Timeline Winter 2018 Design Prepare plans and specifications Spring 2019 Bid Process Council approves plans and authorizes bidding the project Summer 2019 Construction Council awards the contract and construction process begins Fall 2019 Completion Project completed Senate Bill 1 (2017-2018, Beall) Road Repair and Accountability Act project list: Location Description Scheduled Completion Estimated Useful Life National from Samaritan to Los Gatos- Almaden Road Placement of rubber cape seal or overlay to maintain pavement surface. This is a collector road and is critical for transit needs in the Town. Fall 2019 10 -25 years Knowles from Dardanelli to Dell Placement of rubber cape seal or overlay to maintain pavement surface. This is an arterial road and is critical for transit needs in the Town Fall 2020 10 - 25 years Union Avenue from Blossom Hill Road to Los Gatos-Almaden Road Placement of rubber cape seal or overlay to maintain pavement surface. This is an arterial road and is critical for transit needs in the Town Fall 2021 10 - 25 years Quito Road from Bicknell to Woodbank Placement of rubber cape seal or overlay to maintain pavement surface. This is a collector road and is critical for transit needs in the Town. Fall 2022 10 - 25 years Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR Vehicle License Fee - 2010 Measure B*-$ -$ -$ 180,000$ 180,000$ 180,000$ 180,000$ 180,000$ 180,000$ 900,000$ VTA Allocation - 2016 Measure B*- - - 580,633 580,633 580,633 580,633 580,633 580,633 2,903,165 Other GFAR 3,984,249 2,220,034 1,656,514 550,000 2,206,514 613,459 733,459 853,459 853,459 11,464,633 Total GFAR 3,984,249$ 2,220,034$ 1,656,514$ 1,310,633$ 2,967,147$ 1,374,092$ 1,494,092$ 1,614,092$ 1,614,092$ 15,267,798$ GAS TAX & PROP 42 Road Maintenance and Rehabilitation Account (RMRA) *-$ -$ 178,590$ 520,002$ 698,592$ 520,002$ 520,002$ 520,002$ 520,002$ 2,778,600$ Other Gas Tax & Prop 42 6,169,821 22,635 1,012,587 698,132 1,710,719$ 698,132 662,353 662,353 662,353 10,588,366 TOTAL GAS TAX & PROP 42 6,169,821$ 22,635$ 1,191,177$ 1,218,134$ 2,409,311$ 1,218,134$ 1,182,355$ 1,182,355$ 1,182,355$ 13,366,966$ TOTAL SOURCE OF FUNDS 10,154,071$ 2,242,669$ 2,847,690$ 2,528,767$ 5,376,457$ 2,592,226$ 2,676,447$ 2,796,447$ 2,796,447$ 28,634,764$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 3,984,249 2,220,034 1,656,514 1,310,633 2,967,147 1,374,092 1,494,092 1,614,092 1,614,092 15,267,798 TOTAL GFAR 3,984,249$ 2,220,034$ 1,656,514$ 1,310,633$ 2,967,147$ 1,374,092$ 1,494,092$ 1,614,092$ 1,614,092$ 15,267,798$ GAS TAX & PROP 42 Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 6,169,821 22,635 1,191,177 1,218,134 2,409,311 1,218,134 1,182,355 1,182,355 1,182,355 13,366,966 TOTAL GAS TAX & PROP 42 6,169,821$ 22,635$ 1,191,177$ 1,218,134$ 2,409,311$ 1,218,134$ 1,182,355$ 1,182,355$ 1,182,355$ 13,366,966$ TOTAL USE OF FUNDS 10,154,071$ 2,242,669$ 2,847,690$ 2,528,767$ 5,376,457$ 2,592,226$ 2,676,447$ 2,796,447$ 2,796,447$ 28,634,764$ STREET REPAIR & RESURFACING Project 811-9901 PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 9 PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 10 Project Name Almond Grove Street Rehabilitation Project Number 811-0003 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project provides design and construction for the rehabilitation of street infrastructure in the Almond Grove District. Location This project is located within the former Almond Grove District Redevelopment Area. Project Background The streets in the Almond Grove District have deteriorated over the years and due to funding and maintenance constraints, no repairs or resurfacing activities have been performed. The proposed project to rehabilitate the street infrastructure in this area will not only provide safe and functional streets and sidewalks for the community, but also reduce trip and fall accidents. Due to the scale and magnitude of this project, proposed street rehabilitations will be phased over several years to minimize construction impacts to the community and to reflect project funding as determined by the Town Council. Phase 1 of this project included Bachman Avenue and Broadway Avenue. Construction started in Summer 2016 and was substantially complete in the fall of 2016 with minor project close out work continuing into the spring of 2017. The Almond Grove Phase 2 project addresses the eight additional streets in the project, with project bidding completed in April 2017 and construction beginning in the summer of 2017 and continuing over the next two summer construction seasons. Construction bids for this project were very favorable to the Town. The Council awarded the bid in April 2017 allowing for approximately $2.9M in savings within the project. Operating Budget Impacts This project will use staff time for construction inspection and management. Operating costs associated with this project will be reimbursed from the project budget. Project delivery costs for phase one of this project are included in the CIP project’s total cost, and are estimated at 8% of the construction cost. Project delivery costs for Phase 2 of the project are included in the CIP project’s total cost and are estimated at 12% for this more complex part of the project. PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 11 Project Components & Estimated Timeline Summer 2016 Construction Phase 1 project construction Fall 2016 Completion Phase 1 project completion & closeout Winter 2017 Design Phase 2 Completion of plans and specifications Spring 2017 Bid process Phase 2 Council approves plans and authorizes bidding the project Summer 2017 Construction Phase 2 project construction Summer 2018 Construction Phase 2 project construction Summer 2019 Construction Phase 2 project construction Winter 2020 Project Closeout Phase 2 project closeout Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 3,837,375$ 1,301,423$ 9,053,161$ -$ 9,053,161$ -$ -$ -$ -$ 14,191,959$ TOTAL SOURCE OF FUNDS 3,837,375$ 1,301,423$ 9,053,161$ -$ 9,053,161$ -$ -$ -$ -$ 14,191,959$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 3,837,375 1,301,423 9,053,161 - 9,053,161 - - - - 14,191,959 TOTAL GFAR 3,837,375$ 1,301,423$ 9,053,161$ -$ 9,053,161$ -$ -$ -$ -$ 14,191,959$ TOTAL USE OF FUNDS 3,837,375$ 1,301,423$ 9,053,161$ -$ 9,053,161$ -$ -$ -$ -$ 14,191,959$ ALMOND GROVE STREET REHABILITION PROJECT Project 811-0003 PROPOSED STREETS PROGRAM Street Reconstruction & Resurfacing C - 12 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-13 LO S G A T O S - S A R A T O G A R D LOS GATOS BLVDE MAIN STHWY 17HWY 17N SANTA CRUZ AVWINCHESTER BLVDBLOSSOM HILL RDLOS GATOS BLVDHW Y 8 5 KENNE D Y R D SHA N N O N R D LA R K A V LOS GATOS-ALMADEN RD UNIVERSITY AVWEDGEWOOD KNOWLES A, B, C, D, E AND G ARE TOWN-WIDE PROJECTS HICKSRD F PROJECT LOCATIONS A Traffic Calming Projects B Curb, Gutter & Sidewalk Maintenance C Retaining Wall Repairs D Annual Street Restriping E Guardrail Replacement Project F Crosswalk Improvements – Santa Cruz/Blossom Hill G Crosswalk Lighting Upgrades PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-14 PROGRAM SECTION DIRECTORY PAGE 9910 Traffic Calming Projects C – 16 9921 Curb, Gutter & Sidewalk Maintenance C – 18 9930 Retaining Wall Repairs C – 20 9902 Annual Street Restriping C – 22 0120 Guardrail Replacement Project C – 24 0125 Crosswalk Improvements - Santa Cruz Avenue/Blossom Hill Road C – 26 0126 Crosswalk Lighting Upgrades C – 28 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-15 The Streets Program’s Street Repair, Maintenance & Safety Projects section contains Capital Improvement Program projects that repair, maintain, or enhance safety features of the Town’s streets and parking lots as the primary scope of work. Projects may also encompass minor components of streetscape or street improvements; however, to be categorized in this section, street repair, maintenance, or safety enhancements must be the project’s main purpose. Safety issues, available funding sources, project costs, and community impacts are all considerations in prioritizing Street Repair, Maintenance & Safety projects in the five-year Capital Improvement Program. This section contains annual ongoing projects as well as one-time projects. GFAR funding is utilized for the Traffic Calming Projects, which are funded at $10,000 annually. The Annual Street Restriping Project is funded at $25,000 per year. The Curb, Gutter, and Sidewalk Maintenance Project is funded at $300,000 per year. The Retaining Wall Repairs Project is typically funded with an ongoing GFAR stream of $100,000 per year. While annual appropriations are planned for these ongoing projects, funding adjustments may occur from year to year to align with changing priorities and schedules. One-time projects are prioritized by safety factors, community impacts, and the availability of grant funding. GFAR funds may also be utilized to fund a portion of grant driven projects as a grant’s local “match requirement.” Los Gatos does not have an ongoing designated funding source for repairing, maintaining, and improving the Town’s roadway system. STREET REPAIRS, MAINTENANCE & SAFETY PROJECTS SUMMARY Carryforward Projects 9910 Traffic Calming Projects 166,714$ 78,286$ 10,000$ 10,000$ 10,000$ 10,000$ 285,000$ 9921 Curb, Gutter & Sidewalk Maintenance 2,315,761 598,733 300,000 300,000 300,000 300,000 4,114,494 9930 Retaining Wall Repairs 1,371,251 391,526 100,000 100,000 100,000 100,000 2,162,777 9902 Annual Street Restriping 180,228 119,772 25,000 25,000 25,000 25,000 400,000 0120 Guardrail Replacement Projects 136,958 93,043 - - - - 230,000 0125 Crosswalk Improvements - Santa Cruz/Blossom Hill 1,102 108,898 - - - - 110,000 0126 Crosswalk Lighting Upgrade 22,936 88,368 - - - - 111,304 New Projects Total Maintenance & Safety Projects 4,194,951$ 1,478,624$ 435,000$ 435,000$ 435,000$ 435,000$ 7,413,575$ Expended Through 2017/18 2019/20 Budget 2020/21 Budget 2018/19 Budget & Carryfwd* 2021/22 Budget FY 2018/19- 2022/23 CAPITAL IMPROVEMENT PROGRAM Total Budgeted 2022/23 Budget STREET REPAIRS, MAINTENANCE & SAFETY PROJECTS * Total FY 2017/18 Carryforward $1,043,624 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-16 Project Name Traffic Calming Projects Project Number 812-9910 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description In accordance with the Town’s Traffic Calming Policy, this project involves conducting minor traffic studies, developing and implementing traffic improvements, and installing roadway devices to further enhance school pedestrian and roadway safety near high-use crosswalks. Location In FY 2018/19, funds will be used to install temporary devices on College Avenue. Four to six months after installation, staff will conduct another traffic study in the area to determine the effectiveness of these devices. Upon the completion of this study, staff will poll the residents to determine if the devices should be made permanent. If necessary, funds will be used to remove these devices. Any remaining funds within this project will accumulate until the next project is brought forward. Project Background In 2002, the Town implemented a Traffic Calming Policy to address and mitigate neighborhood traffic and pedestrian safety issues, such as speeding and cut-through traffic. This program relies on residents to bring projects forward at the neighborhood level. At the time the Policy was adopted, twelve project areas were under review for traffic calming improvements. To date, twelve projects have been processed, completed, or closed. Traffic calming improvements such as speed bumps, traffic circles, center medians, and bulb-outs were installed where appropriate to slow vehicles or enhance pedestrian safety. The last project completed was on Wedgewood Avenue. Operating Budget Impacts Engineering staff time associated with these projects will be charged to the project as they are identified and delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-17 Project Components & Estimated Timeline Summer 2018 Install Traffic Calming Devices on College Avenue Fall 2018 Monitor and conduct follow up traffic study for College Avenue Winter 2018 Conclude pilot installation on College Avenue Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 132,059$ 34,655$ 68,286$ 10,000$ 78,286$ 10,000$ 10,000$ 10,000$ 10,000$ 285,000$ TOTAL SOURCE OF FUNDS 132,059$ 34,655$ 68,286$ 10,000$ 78,286$ 10,000$ 10,000$ 10,000$ 10,000$ 285,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 132,059 34,655 68,286 10,000 78,286 10,000 10,000 10,000 10,000 285,000 TOTAL GFAR 132,059$ 34,655$ 68,286$ 10,000$ 78,286$ 10,000$ 10,000$ 10,000$ 10,000$ 285,000$ TOTAL USE OF FUNDS 132,059$ 34,655$ 68,286$ 10,000$ 78,286$ 10,000$ 10,000$ 10,000$ 10,000$ 285,000$ TRAFFIC CALMING PROJECTS Project 812-9910 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-18 TOWN-WIDE Project Name Curb, Gutter, & Sidewalk Maintenance Project Number 813-9921 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This is an ongoing annual project for the repair and replacement of hazardous curbs, gutters, and sidewalks throughout Town to enhance pedestrian and bicyclist safety and to improve water runoff infrastructure. Location Curb, gutter, and sidewalk repair projects occur throughout the Town based on priority needs. Project Background Curb, gutter, and sidewalk improvements in public parking lots and rights-of-way have historically been funded by the Town. The intent of this project is to keep pace with the deterioration of sidewalks and curbs. Specific project locations are identified and prioritized based on the level of damage and accompanying potential safety issues. The primary source of damage to sidewalks, curbs and gutters is tree root intrusion. Most of the streets in Town have mature trees in the planter areas between the sidewalks and curbs. These trees were planted many years ago without consideration of root growth and its impacts to the sidewalk, curb, and street. Over time, the tree roots cause cracks and raised concrete, leading to uneven surfaces. Staff develops an annual plan for sidewalk repair based on the level of damage as observed and reported by staff and residents, confirmed by staff inspection. The level of repair and maintenance performed in any given year has been limited by available annual funding. Funds are utilized predominantly to address locations where paving projects create a requirement for curb ramps and curb and gutter repair. In addition to sidewalk, curb and gutter maintenance, this project is used for installing Americans with Disabilities Act (ADA) accessible curb ramps on Town streets as required by federal law following Town street maintenance projects. Title II of the ADA obligates a jurisdiction to provide compliant curb ramps whenever streets are resurfaced from one intersection to another. ADA compliance has required a substantial portion of the annual funding allocation. To address some of the unmet needs, staff has recommended increasing the annual allocation by $50,000 per year. Operating Budget Impacts Potential trip and fall injuries and lawsuits against the Town should be reduced by eliminating hazardous curb, gutter, and sidewalk conditions. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-19 Project Components & Estimated Timeline Winter 2018 Design Project design & development Spring 2019 Bid Process Project bidding & contract award Spring 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 2,056,466$ 259,296$ 298,733$ 300,000$ 598,733$ 300,000$ 300,000$ 300,000$ 300,000$ 4,114,494$ TOTAL SOURCE OF FUNDS 2,056,466$ 259,296$ 298,733$ 300,000$ 598,733$ 300,000$ 300,000$ 300,000$ 300,000$ 4,114,494$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 2,056,466 259,296 298,733 300,000 598,733 300,000 300,000 300,000 300,000 4,114,494 TOTAL GFAR 2,056,466$ 259,296$ 298,733$ 300,000$ 598,733$ 300,000$ 300,000$ 300,000$ 300,000$ 4,114,494$ TOTAL USE OF FUNDS 2,056,466$ 259,296$ 298,733$ 300,000$ 598,733$ 300,000$ 300,000$ 300,000$ 300,000$ 4,114,494$ CURB, GUTTER & SIDEWALK MAINTENANCE Project 813-9921 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-20 TOWN-WIDE Project Name Retaining Wall Repairs Project Number 815-9930 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description The Retaining Wall Repair and Replacement Program focuses on the repair and/or replacement of retaining walls that have become structurally deficient. Location Retaining wall repair projects are identified throughout the Town and are prioritized in order of repair based on safety issues, roadway impacts, retaining wall damage, and project costs. Project Background Retaining walls are installed to hold a hillside from sliding and are placed alongside a street at strategic locations where hillside erosion is anticipated. If the retaining wall fails, the street subsequently fails; therefore, it is important to maintain the retaining walls as they are an integral part of the hillside roadway system. Some existing retaining walls have reached the end of their serviceable life and require replacement. Hillside locations are prioritized over smaller roadside embankments in accordance with the potential impacts from failures. Retaining walls are visually inspected annually; however, unanticipated weather events can quickly erode a wall’s integrity and cause failure. Town staff continues to monitor and schedule retaining wall installation and replacement as needed. Operating Budget Impacts Once repaired, improved retaining walls reduce ongoing operating costs associated with maintenance and emergency response. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-21 Project Components & Estimated Timeline Spring 2018 Design Project design & development Summer 2018 Bid Process Project bidding & contract award Summer 2018 Construction Project construction Fall 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 1,320,854$ 50,398$ 291,526$ 100,000$ 391,526$ 100,000$ 100,000$ 100,000$ 100,000$ 2,162,777$ TOTAL SOURCE OF FUNDS 1,320,854$ 50,398$ 291,526$ 100,000$ 391,526$ 100,000$ 100,000$ 100,000$ 100,000$ 2,162,777$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 1,320,854 50,398 291,526 100,000 391,526 100,000 100,000 100,000 100,000 2,162,777 TOTAL GFAR 1,320,854$ 50,398$ 291,526$ 100,000$ 391,526$ 100,000$ 100,000$ 100,000$ 100,000$ 2,162,777$ TOTAL USE OF FUNDS 1,320,854$ 50,398$ 291,526$ 100,000$ 391,526$ 100,000$ 100,000$ 100,000$ 100,000$ 2,162,777$ RETAINING WALL REPAIRS Project 815-9930 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-22 TOWN-WIDE Project Name Annual Street Restriping Project Number 811-9902 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project is an annual program that restripes a portion of the Town’s streets, ensuring the safety of vehicles and pedestrians. Location Roadway restriping work is done at various locations throughout the Town based on conditions and available funds. Project Background The Town initiated Town-wide striping in FY 2006/07. Due to deferred striping and marking of the Town’s public streets, any striping that had been accomplished previously was done in conjunction with the resurfacing of specific streets in the Town’s annual street paving project. This annual street restriping program installs new striping and marking for center lanes, bicycle lanes, crosswalks, stop sign and signal light markings, and other roadway signage as needed. Roadway stripes wear out due to traffic and weather, and create a potential safety concern. The goal is to have Town streets that are properly striped for safe operation and use by the public. Under this project, locations that are not scheduled for street repaving will be prioritized for restriping. The restriping of repaved streets will continue to occur in conjunction with paving contracts. Since FY 2007/08, the ongoing annual GFAR appropriation has been $25,000. Operating Budget Impacts Engineering staff time associated with these projects will be charged to the project as the project is delivered. PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-23 Project Components & Estimated Timeline Winter 2018 Design Project Design & development Spring 2019 Bid Process Project bidding & contract award Summer 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 180,228$ -$ 94,772$ 25,000$ 119,772$ 25,000$ 25,000$ 25,000$ 25,000$ 400,000$ TOTAL SOURCE OF FUNDS 180,228$ -$ 94,772$ 25,000$ 119,772$ 25,000$ 25,000$ 25,000$ 25,000$ 400,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 180,228 - 94,772 25,000 119,772 25,000 25,000 25,000 25,000 400,000 TOTAL GFAR 180,228$ -$ 94,772$ 25,000$ 119,772$ 25,000$ 25,000$ 25,000$ 25,000$ 400,000$ TOTAL USE OF FUNDS 180,228$ -$ 94,772$ 25,000$ 119,772$ 25,000$ 25,000$ 25,000$ 25,000$ 400,000$ ANNUAL STREET RESTRIPING Project 811-9902 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-24 Project Name Guardrail Replacement Project Project Number 812-0120 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description The project will construct a new metal beam guardrail and replace old and damaged guardrails along sections of Town roadway. Location This project will take place in various locations where guardrails are present and are in need of repair. The list of guardrails will be identified and will be brought forward to Council for approval. Project Background There are many roadways throughout Town that are located near hillside areas where guardrails are present. Over the years, due to hillside erosion and years of deferred maintenance, the guardrails have worn out and are in need of repair or replacement. Guardrails are often located on narrow stretches of roadway, and protect vehicles and pedestrians from steep hillside embankments. Staff will assess guardrails and determine which ones are in the most need of repair, budget permitting. Operating Budget Impacts Engineering staff time associated with these projects will be charged to the project as they are identified and delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-25 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Spring 2019 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 136,958$ -$ 93,043$ -$ 93,043$ -$ -$ -$ -$ 230,000$ TOTAL SOURCE OF FUNDS 136,958$ -$ 93,043$ -$ 93,043$ -$ -$ -$ -$ 230,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 136,958 - 93,043 - 93,043 - - - - 230,000 TOTAL GFAR 136,958$ -$ 93,043$ -$ 93,043$ -$ -$ -$ -$ 230,000$ TOTAL USE OF FUNDS 136,958$ -$ 93,043$ -$ 93,043$ -$ -$ -$ -$ 230,000$ GUARDRAIL REPLACEMENT PROJECTS Project 812-0120 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-26 LOS GATOS BLVDHWY 17N SANTA CRUZ AVUNIVERSITY AVBLOSSOM H I L L R D Project Name Crosswalk Improvements at Santa Cruz Avenue/Blossom Hill Road Project Number 812-0125 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will install a new crosswalk on the north side of Santa Cruz Avenue at Blossom Hill Road. Location This project is located on Santa Cruz Avenue at Blossom Hill Road. Project Background The intersection at Santa Cruz Avenue and Blossom Hill Road is a well-traveled pedestrian corridor. There is an existing crosswalk on the South side of Santa Cruz Avenue that provides limited crossing access and adding a crosswalk on the North side of Santa Cruz Avenue will enhance crossing access for pedestrians and bicyclists. Operating Budget Impacts There will be no Operating Budget impact as a result of this project. Project delivery costs for this project are included in the CIP project’s total cost, which is approximately 12%. PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-27 Project Components & Estimated Timeline Winter 2017 Design Project design & development Spring 2018 Bid Process Project bidding & contract award Spring 2018 Construction Project construction Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 1,008$ -$ 58,992$ -$ 58,992$ -$ -$ -$ -$ 60,000$ TRAFFIC MITIGATION 94 - 49,906 - 49,906 - - - - 50,000 TOTAL SOURCE OF FUNDS 1,102$ -$ 108,898$ -$ 108,898$ -$ -$ -$ -$ 110,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 1,008 - 58,992 - 58,992 - - - - 60,000 TOTAL GFAR 1,008$ -$ 58,992$ -$ 58,992$ -$ -$ -$ -$ 60,000$ TRAFFIC MITIGATION Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 94 - 49,906 - 49,906 - - - - 50,000 TOTAL TRAFFIC MITIGATIONS 94$ -$ 49,906$ -$ 49,906$ -$ -$ -$ -$ 50,000$ TOTAL USE OF FUNDS 1,102$ -$ 108,898$ -$ 108,898$ -$ -$ -$ -$ 110,000$ CROSSWALK IMPROVEMENTS SANTA CRUZ/BLOSSOM HILL 812-0125 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-28 Project Name Crosswalk Lighting Upgrades Project Number 812-0126 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will upgrade pedestrian crossing lights at multiple locations throughout Town. Location This project will take place at various locations in Town. Project Background Safety improvements are needed at key streets to ensure public safety and safe walking pathways for students and pedestrians. Staff identified areas that have moderate to high levels of pedestrian traffic that are near major roadways that lack safe crosswalk areas. Work has been completed at Massol Avenue and Highway 9, Blossom Hill Road and Hillbrook Road, and Pollard Road and Abbott Avenue. The remaining location is Los Gatos-Almaden Road and Cherry Blossom. The project is anticipated to be completed in the early part of FY 2018/19. As part of these crosswalk lighting upgrades, more enhanced signage with lighting will be installed, as well as concrete median islands, where applicable. For streets with multiple vehicle lanes, the concrete median islands allow pedestrians a safe area mid-way through the street so that crossing is more safe and achievable in high traffic areas. The former Intersection Safety & Traffic Flow Improvements Project (813-0220) has now been combined with the Crosswalk Lighting Upgrade Project as the project vicinity and outcomes for safety overlap significantly. Operating Budget Impacts There will be no Operating Budget impact as a result of this project. Project delivery costs for this project are included in the CIP project’s total cost, which is approximately 12%. TOWN-WIDE PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-29 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid process Project bidding & contract award Winter 2018 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Adjusted 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 7,565$ 53,739$ -$ 53,739$ -$ 53,739$ -$ -$ -$ -$ 61,304$ TRAFFIC MITIGATION 15,371 34,629 - 34,629 - 34,629 - - - - 50,000 TOTAL SOURCE OF FUNDS 22,936$ 88,368$ -$ 88,368$ -$ 88,368$ -$ -$ -$ -$ 111,304$ Prior Yrs Actuals 2017/18 Adjusted 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - - Consultant Services - - - - - - - - - - - Project Construction Expenses 7,565$ 53,739 -$ 53,739$ - 53,739 - - - - 61,304 TOTAL GFAR 7,565$ 53,739$ -$ 53,739$ -$ 53,739$ -$ -$ -$ -$ 61,304$ TRAFFIC MITIGATION Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - - Consultant Services - - - - - - - - - - - Project Construction Expenses 15,371 34,629 - 34,629 - 34,629 - - - - 50,000 TOTAL TRAFFIC MITIGATIONS 15,371$ 34,629$ -$ 34,629$ -$ 34,629$ -$ -$ -$ -$ 50,000$ TOTAL USE OF FUNDS 22,936$ 53,739$ -$ 88,368$ -$ 88,368$ -$ -$ -$ -$ 111,304$ CROSSWALK LIGHTING UPGRADE 812--0126 PROPOSED STREETS PROGRAM Street Repairs, Maintenance & Safety Projects C-30 PROPOSED STREETS PROGRAM Street Improvements C-31 LO S G A T O S - S A R A T O G A R D LOS GATOS BLVDE MAIN STHWY 17HWY 17N SANTA CRUZ AVWINCHESTER BLVDBLOSSOM HILL RDLOS GATOS BLVDHW Y 8 5 KENNE D Y R D SHA N N O N R D LA R K A V LOS GATOS-ALMADEN RD UNIVERSITY AVWEDGEWOOD KNOWLES A HICKSRD B C, J, K, M, N, P, Q, R, S, W AND X ARE TOWN-WIDE PROJECTS E F H I G L O QUITO RDBICKNELL RD T Y D, U, V PROJECT LOCATIONS A Highway 9/University Avenue Intersection Improvements N Traffic Signal Modernization B Los Gatos Boulevard/Shannon Road Improvements O Bicknell Road Storm Drain Improvements C Monument Control Network Update P Bicycle & Pedestrian Improvements D Downtown Parking Lots Seal Coat & Restriping Q Stormwater Master Plan E Hernandez Avenue Storm Drain Improvements R Stormwater System – Pollution Prevention Compliance F Blossom Hill Road/Cherry Blossom Lane Intersection Improvements S Public Arts Gateway G 224 West Main Property Acquisition (Parking Lot 6) T Jones Road Storm Drain Improvements H Shannon Road/Los Gatos Boulevard/Cherry Blossom Lane Sidewalk Improvements U Downtown Parking Study I Stonybrook Road/Kennedy Road Sidewalk Improvements V One-Way Downtown Street Pilot J Sidewalk Improvements – Multiple Locations W Annual Storm Drain Improvements K LED Streetlights X Pilot School Busing Program L Utility Undergrounding Improvements Y Highway 17 Bicycle & Pedestrian Bridge M Cut-Through Traffic Mitigation PROPOSED STREETS PROGRAM Street Improvements C-32 PROGRAM SECTION DIRECTORY PAGE 0202 Highway 9/University Avenue Intersection Improvements C – 38 0213 Los Gatos Boulevard/Shannon Road Improvements C – 40 0214 Monument Control Network Update C – 42 0705 Downtown Parking Lots Seal Coat & Restriping C – 44 0409 Hernandez Avenue Storm Drain Improvements C – 46 0212 Blossom Hill Road/Cherry Blossom Lane Intersection Improvements C – 48 0704 224 West Main Property Acquisition (Parking Lot 6) C – 50 0218 Sidewalk Improvements for Shannon Road/Los Gatos Boulevard/Cherry Blossom Lane C – 52 0219 Stonybrook Road & Kennedy Road Sidewalk Improvements C – 54 0221 Sidewalk Improvements – Multiple Locations C – 56 0224 LED Street Lights C – 58 0225 Utility Undergrounding Improvements C – 60 0229 Cut – Through Traffic Mitigation C – 62 0227 Traffic Signal Modernization C – 64 0410 Bicknell Road Storm Drain Improvements C – 66 0231 Bicycle & Pedestrian Improvements C – 68 0413 Stormwater Master Plan C – 70 0414 Stormwater System – Pollution Prevention Compliance C – 72 0232 Public Arts Gateway C – 74 0415 Jones Road Storm Drain Improvements C – 76 0233 Downtown Parking Study C – 78 0234 One-Way Downtown Street Pilot C – 80 0420 Annual Storm Drain Improvements C – 82 0128 Pilot School Busing C – 84 0803 Highway 17 Bicycle & Pedestrian Bridge C – 86 PROPOSED STREETS PROGRAM Street Improvements C-33 The Streets Program’s Street Improvements section contains Capital Improvement Program projects that improve a roadway’s function or structure, other than paving, as the primary scope of work. Typical Street Improvements projects include sidewalk, curb, and gutter improvements, storm drain improvements, the undergrounding of utilities, intersection improvements, sidewalk and median ramps, crosswalk improvements, street lighting, and retaining walls. In this CIP, the Street Improvements section contains one-time projects and no ongoing projects. One-time Street Improvements projects are prioritized based on safety needs, traffic levels, available funding sources, project costs, and community impacts. Traffic Mitigation Funds, Storm Drain Funds, and the Utility Underground Fund all provide designated funding revenue through development fee charges for their related project categories. Los Gatos does not have a designated funding source for other street improvements which do not fall into these categories; however, grants, in-lieu fees, CDBG funds, and community benefit funds are utilized when available. STREET IMPROVEMENT PROJECTS SUMMARY * Total FY 2017/18 Carryforward $4,803,348 Unfunded Projects for future consideration • Parking Lot 4 Repair & Waterproofing • Montebello Way Island Removal • Blossom Hill Road & Union Avenue Improvements • Los Gatos-Almaden Road Improvements • Union Avenue Widening and Sidewalks Carryforward Projects 0202 Hwy 9/University Intersection 969,790$ 199,211$ -$ -$ -$ -$ 1,169,000$ 0213 Los Gatos Blvd/Shannon Improvements - 20,000 - - - - 20,000 0214 Monument Control Network Update - 30,000 - - - - 30,000 0705 Downtown Parking Lots Seal Coat & Restriping 24,915 75,085 - - - - 100,000 0409 Hernandez Avenue Storm Drain Improvements 17,180 - - - - 65,000 82,180 0212 Blossom Hill Rd/Cherry Blossom Ln Intersection Improvements - 500,000 - - - - 500,000 0704 224 W. Main Street Property Acquisition (Parking Lot 6)24,000 1,214,913 - - - - 1,238,913 0218 Shannon/LGB/Cherry Blossom Sidewalk Improvements 104 129,896 - - - - 130,000 0219 Stonybrook & Kennedy Sidewalk Improvements 63,868 516,132 - - - - 580,000 0221 Sidewalk Improvements - Multiple Locations - 60,000 - - - - 60,000 0224 LED Streetlights 396,178 108,470 - - - - 504,648 0415 Jones Road Storm Drain Improvements 18,700 2,300 - - - - 21,000 0225 Utility Undergrounding Improvements - 2,330,000 4,436,000 - - - 6,766,000 0229 Cut-Through Traffic Mitigation 222,828 106,721 - - - - 329,549 0227 Traffic Signal Modernization 20,250 1,559,525 374,949 415,027 - - 2,369,751 0232 Public Art Gateway - 25,000 - - - - 25,000 0410 Bicknall Avenue Storm Drain Improvements 108,392 63,108 - - - - 171,500 0231 Bicycle & Pedestrian Improvements 63,700 611,300 - - - - 675,000 0413 Stormwater Master Plan - 200,000 - - - - 200,000 0414 Stormwater System - Pollution Prevention Compliance - 300,000 - - - - 300,000 New Projects 0233 Downtown Parking Study - 200,000 - - - - 200,000 0234 One-Way Downtown Street Pilot - 130,000 - - - - 130,000 0412 Annual Storm Drain Improvement Prj - 150,000 150,000 150,000 150,000 150,000 750,000 0128 Pilot School Busing Program - 110,600 221,200 341,880 - - 673,680 0803 Highway 17 Bicycle & Ped Bridge - 200,000 - - - - 200,000 Total Street Improvement Projects 1,929,904$ 8,842,260$ 5,182,149$ 906,907$ 150,000$ 215,000$ 17,226,220$ 2021/22 Budget 2018/19 Budget & Carryfwd* FY 2018/19- 2022/23 CAPITAL IMPROVEMENT PROGRAM 2019/20 Budget STREET IMPROVEMENT PROJECTS Total Budgeted 2020/21 Budget 2022/23 Budget Expended Through 2017/18 PROPOSED STREETS PROGRAM Street Improvements C-34 Project Name Highway 9/University Avenue Intersection Improvements Project Number 813-0202 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project replaced the old and outdated traffic signal at the Highway 9 and University Avenue intersection with a new traffic signal system. Additionally, dedicated left turn lanes were constructed on University Avenue to improve vehicle traffic flow. Sidewalks were repaired to be in compliance with current codes. Construction associated with this project was completed in FY 2015/16 with project closeout, including processing associated documentation lasting into FY 2018/19. Location The project is located at the intersection of Highway 9 and University Avenue. Project Background The lack of an updated traffic signal system and dedicated left turn lanes has impacted vehicle traffic flow, causing vehicle and pedestrian safety and capacity issues. To address these issues, a new traffic signal system, including dedicated left turn lanes, were installed. The sidewalks located at this intersection were also improved to comply with current codes. The project intersection is located in the Caltrans right-of-way and due to state budget challenges, funding has been limited for the past several years. However, the Town secured a grant through the Highway Safety Implementation Program (HSIP). The project was funded through this grant and revenue from development projects in the immediate area. Although all of the work has been done for some time, project closeout has been delayed on this project as staff has struggled with obtaining and providing information to Caltrans for grant documentation. Operating Budget Impacts This project will use staff time grant management. The staff time for this project is included in the Department’s FY 2018/19 Operating Budget. HWY 9 E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV PROPOSED STREETS PROGRAM Street Improvements C-35 Project Components & Estimated Timeline Winter 2014 Construction Project construction Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATION 66,963$ -$ -$ -$ -$ -$ -$ -$ -$ 66,963$ GRANTS & AWARDS 902,827 - 199,211 - 199,211 - - - - 1,102,038 TOTAL SOURCE OF FUNDS 969,790$ -$ 199,211$ -$ 199,211$ -$ -$ -$ -$ 1,169,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATION Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 66,963 - - - - - - - - 66,963 TOTAL TRAFFIC MITIGATION 66,963$ -$ -$ -$ -$ -$ -$ -$ -$ 66,963$ GRANTS & AWARDS Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 902,827 - 199,211 - 199,211 - - - - 1,102,038 TOTAL GRANTS & AWARDS 902,827$ -$ 199,211$ -$ 199,211$ -$ -$ -$ -$ 1,102,038$ TOTAL USE OF FUNDS 969,790$ -$ 199,211$ -$ 199,211$ -$ -$ -$ -$ 1,169,000$ HIGHWAY 9 / UNIVERSITY AVENUE INTERSECTION IMPROVEMENTS Project 813-0202 PROPOSED STREETS PROGRAM Street Improvements C-36 LOS GATOS BLVDBLOSSOM HILL R D SHANN O N R D Project Name Los Gatos Boulevard/Shannon Road Improvements Project Number 813-0213 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will create a new pedestrian signalized crossing and restripe Shannon Road to provide longer turn lanes and improve the overall safety for pedestrians and bicyclists. The project will be coordinated with any potential development of adjacent parcels. Location This project is located at the intersection of Los Gatos Boulevard and Shannon Road. Project Background The intersection of Los Gatos Boulevard and Shannon Road is a heavily used area, especially during the morning and afternoon school and commute hours. To improve the safe operation of this intersection, a new pedestrian push button signal will be installed and also new striping on Shannon Road will provide a longer turn lane onto Los Gatos Boulevard. Should a development project occur at this location, that project will take on this work and the Town funding will revert to the GFAR in future budget cycles Operating Budget Impacts This project will use staff time for design and construction. Engineering staff time associated with these projects will be charged to the project as they are identified and delivered. PROPOSED STREETS PROGRAM Street Improvements C-37 Project Components & Estimated Timeline Fall 2018 Preliminary Design Project design & development Spring 2019 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATION -$ -$ 20,000$ -$ 20,000$ -$ -$ -$ -$ 20,000$ TOTAL SOURCE OF FUNDS -$ -$ 20,000$ -$ 20,000$ -$ -$ -$ -$ 20,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATION Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 20,000 - 20,000 - - - - 20,000 TOTAL TRAFFIC MITIGATION -$ -$ 20,000$ -$ 20,000$ -$ -$ -$ -$ 20,000$ TOTAL USE OF FUNDS -$ -$ 20,000$ -$ 20,000$ -$ -$ -$ -$ 20,000$ LOS GATOS BOULEVARD / SHANNON IMPROVEMENTS Project 813-0213 PROPOSED STREETS PROGRAM Street Improvements C-38 Project Name Monument Control Network Update Project Number 813-0214 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will provide ongoing update of the existing Town-wide survey monument control network in phases. Location This project is located Town-wide. Project Background In 2002, the Town undertook a project to establish a survey monument network for Los Gatos, which has been used by surveyors and engineers for the last 10 years. Due to new development projects, and changes to the Town’s infrastructure, such as new streets, the survey monument network is outdated. The survey monuments are a planning resource when considering new development projects or when designing or providing engineering specifications for projects. This project will provide a verification of the location of the Town monuments per the original survey. This survey document will enable staff to detect any variations of location of any monuments that have been affected by earth movements. Operating Budget Impacts This project will use staff time for design and management. This project is tentatively scheduled to begin in FY 2018/19. Engineering staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-39 Project Components & Estimated Timeline Fall 2018 Design Phase I project development Winter 2018 Bid process Phase I project bidding & contract award Summer 2019 Completion Phase I project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 20,000$ -$ 20,000$ -$ -$ -$ -$ 20,000$ TRAFFIC MITIGATION - - 10,000 - 10,000 - - - - 10,000 TOTAL SOURCE OF FUNDS -$ -$ 30,000$ -$ 30,000$ -$ -$ -$ -$ 30,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 20,000 - 20,000 - - - - - TOTAL GFAR -$ -$ 20,000$ -$ 20,000$ -$ -$ -$ -$ 20,000$ TRAFFIC MITIGATION Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 10,000 - 10,000 - - - - - TOTAL TRAFFIC MITIGATION -$ -$ 10,000$ -$ 10,000$ -$ -$ -$ -$ 10,000$ TOTAL USE OF FUNDS -$ -$ 30,000$ -$ 30,000$ -$ -$ -$ -$ 30,000$ MONUMENT CONTROL NETWORK UPDATE Project 813-0214 PROPOSED STREETS PROGRAM Street Improvements C-40 HWY 9 E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV Project Name Downtown Parking Lots Seal Coat & Restriping Project Number 817-0705 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will resurface downtown parking lots by applying a seal coat and then restriping. Location This project is located at various Town-owned parking lots in downtown Los Gatos. Project Background The public parking lots in downtown Los Gatos are heavily used on a daily basis. In order to keep their surfaces in good condition and prevent long term wear and damage, the parking lots need to be resurfaced and restriped. This project is necessary to prevent possible drainage or broken pavement problems in the future. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED STREETS PROGRAM Street Improvements C-41 Project Components & Estimated Timeline Winter 2017 Preliminary Design Project design & development Spring 2018 Final Design Project bidding & contract award Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ 24,915$ 75,085$ -$ 75,085 -$ -$ -$ -$ 100,000$ TOTAL SOURCE OF FUNDS -$ 24,915$ 75,085$ -$ 75,085$ -$ -$ -$ -$ 100,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - 24,915 75,085 - 75,085 - - - - 100,000 TOTAL GFAR -$ 24,915$ 75,085$ -$ 75,085$ -$ -$ -$ -$ 100,000$ TOTAL USE OF FUNDS -$ 24,915$ 75,085$ -$ 75,085$ -$ -$ -$ -$ 100,000$ DOWNTOWN PARKING LOTS SEAL COAT & RESTRIPING Project 817-0705 PROPOSED STREETS PROGRAM Street Improvements C-42 Project Name Hernandez Avenue Storm Drain Improvements Project Number 816-0409 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will improve the Hernandez Avenue storm drain system with the installation of an underground storm drain pipe and sidewalk above. Location The storm drain project is located on the south side of Hernandez Avenue, between Walnut Avenue and Wissahickon Avenue. Project Background Hernandez Avenue is a hillside collector street with an incomplete sidewalk network and storm drain systems alongside the roadway. This street averages over 1,000 vehicles per day, a normal amount for a collector street. At previous neighborhood meetings, residents indicated an interest in having continuous sidewalks, particularly in the area where an open storm drain exists. This project proposes to install an underground storm drain pipe into the existing ditch and put a concrete sidewalk, curb, and gutter system along the roadway to feed runoff water into the storm drain pipe. This street improvement addresses several neighborhood needs, including an improved drainage system, a safer pedestrian area, and an improved appearance of the neighborhood. This project will be funded by the Storm Basin Fund. This project is scheduled for FY 2021/22. Operating Budget Impacts Ongoing operating costs would be significantly reduced as this project would eliminate the need to clean or repair the existing open ditch. Engineering staff time associated with these projects will be charged to the project as it is delivered in FY 2021/22. L O S G A T O S - S A R A T O G A R D HWY 17N SANTA CRUZ AVUNIVERSITY AV PROPOSED STREETS PROGRAM Street Improvements C-43 Project Components & Estimated Timeline Fall 2020 Design Design project, include alternative methods and estimated costs, and determine best outcome Winter 2021 Bid Process Obtain bids from licensed contractors and submit to Council for approval Summer 2021 Construction Construction of storm drains and related street improvements Fall 2021 Completion Project completed Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) STORM BASIN #3 17,180$ -$ -$ -$ -$ -$ -$ -$ 65,000$ 82,180$ TOTAL SOURCE OF FUNDS 17,180$ -$ -$ -$ -$ -$ -$ -$ 65,000$ 82,180$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) STORM BASIN #3 Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 17,180 - - - - - - - 65,000 82,180 TOTAL STORM BASIN 17,180$ -$ -$ -$ -$ -$ -$ -$ 65,000$ 82,180$ TOTAL USE OF FUNDS 17,180$ -$ -$ -$ -$ -$ -$ -$ 65,000$ 82,180$ HERNANDEZ AVENUE STORM DRAIN IMPROVEMENTS Project 816-0409 PROPOSED STREETS PROGRAM Street Improvements C-44 LOS GATOS BLVDBLOSSOM HILL RD SHANNO N R D Project Name Blossom Hill Road/Cherry Blossom Lane Intersection Improvements Project Number 813-0212 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will install a new traffic signal and reconfigure this intersection to improve flow of vehicle, bicycle, and pedestrian traffic. Location This project is located at the intersection of Blossom Hill Road and Cherry Blossom Lane. Project Background In 2011, the Town conducted safety improvements on Blossom Hill Road from Cherry Blossom Lane to Camino del Cerro. This project was funded by Town Traffic Mitigation funds along with funding received from the State of California’s Safe Routes to School grant. The improvements from the first phase of the project included: reconfiguration of the crosswalks at Blossom Hill Road and Cherry Blossom Lane, widening of Blossom Hill Road from Cherry Blossom Lane to Camino del Cerro, construction of bicycle lanes on a section of Blossom Hill Road, construction of sidewalks on a section of Blossom Hill Road, and construction of a lighted crosswalk across Blossom Hill Road. The final phase of this project will replace the existing traffic signal system at the intersection of Blossom Hill Road and Cherry Blossom Lane. Additionally, this project will reconfigure this intersection to improve its operations for vehicles, pedestrians, and bicyclists. Operating Budget Impacts This project was recommended within the study of traffic around schools and is consistent with the Town’s Bicycle and Pedestrian Master Plan. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED STREETS PROGRAM Street Improvements C-45 Project Components & Estimated Timeline Fall 2018 Design Project design & development Winter 2018 Bid Process Project bidding & contract award Spring 2019 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATION -$ -$ 500,000$ -$ 500,000$ -$ -$ -$ -$ 500,000$ TOTAL SOURCE OF FUNDS -$ -$ 500,000$ -$ 500,000$ -$ -$ -$ -$ 500,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATION Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 500,000 - 500,000 - - - - 500,000 TOTAL TRAFFIC MITIGATION -$ -$ 500,000$ -$ 500,000$ -$ -$ -$ -$ 500,000$ TOTAL USE OF FUNDS -$ -$ 500,000$ -$ 500,000$ -$ -$ -$ -$ 500,000$ BLOSSOM HILL ROAD / CHERRY BLOSSOM LANE INTERSECTION IMPROVEMENTS Project 813-0212 PROPOSED STREETS PROGRAM Street Improvements C-46 HWY 9 E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV Project Name 224 West Main Property Acquisition (Parking Lot 6) Project Number 817-0704 Department Parks & Public Works Project Manager PPW Director: Matt Morley Description This project, carried forward from previous years, allocates funding from the GFAR Parking Reserve for the purchase of property (formerly 224 West Main Street) for Parking Lot 6. Location This project is located at Parking Lot 6, which is at 224 West Main Street. Project Background In 2009, the Town purchased a property next to Parking Lot 6 to expand the existing parking lot. This property was purchased by Town Housing/Redevelopment Agency (RDA) funds. Because the State dissolved redevelopment agencies, it is necessary that the Town use an alternative funding source for this purchase if affordable housing is not constructed at this site. Reserve funds for GFAR are identified for this use. Staff is recommending proceeding with the transfer of funds in the FY 2018/19 budget to complete this action. Operating Budget Impacts This project would use staff time for processing of the new property purchase. The staff time for this project is included in the FY 2018/19 Operating Budget. PROPOSED STREETS PROGRAM Street Improvements C-47 Project Components & Estimated Timeline Summer 2018 Estimated Completion Property purchase and funding completed. Prior Yrs Actuals 2017/18 Adjusted 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 5,375$ 1,194,625$ 18,625$ 1,176,000$ 38,913$ 1,214,913$ -$ -$ -$ -$ 1,238,913$ TOTAL SOURCE OF FUNDS 5,375$ 1,194,625$ 18,625$ 1,176,000$ -$ -$ -$ -$ -$ -$ 1,238,913$ Prior Yrs Actuals 2017/18 Adjusted 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - - Consultant Services - - - - - - - - - - - Project Construction Expenses 5,375 1,194,625 18,625 1,176,000 38,913 1,214,913 - - - - 1,238,913 TOTAL GFAR 5,375$ 1,194,625$ 18,625$ 1,176,000$ 38,913$ 1,214,913$ -$ -$ -$ -$ 1,238,913$ TOTAL USE OF FUNDS 5,375$ 1,194,625$ 18,625$ 1,176,000$ 38,913$ 1,214,913$ -$ -$ -$ -$ 1,238,913$ 224 WEST MAIN PROPERTY ACQUISITION (PARKING LOT 6)Project 817-0704 PROPOSED STREETS PROGRAM Street Improvements C-48 LOS GATOS BLVDBLOSSOM HILL RD SHANNON R D Project Name Sidewalk Improvements/Shannon/Los Gatos Blvd/Cherry Blossom Lane Project Number 813-0218 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will construct sidewalk, curb and gutter along the north side of Shannon Road between Los Gatos Boulevard and Cherry Blossom Lane, completing the pedestrian link between the two roads. Location The project is located on Shannon Road between Los Gatos Boulevard and Cherry Blossom Lane. Project Background Shannon Road is a heavily traveled two-lane roadway, especially when the schools are in session. Shannon Road is used by residents dropping off students at various schools, such as Blossom Hill Elementary, Van Meter Elementary, and Fisher Middle Schools. In addition, many parents walk their children to school along this segment of roadway. Shannon Road currently has intermittent sections of sidewalk on the south side of the roadway between Los Gatos Boulevard and Cherry Blossom Lane. Most pedestrians cross Shannon Road to walk along the south side, while some walk along the unimproved shoulder on the north side. This project will complete the sidewalk segment on the north side of the roadway and reduce congestion at Shannon Road and Cherry Blossom Lane, where a 3-way stop is inundated by crossing students, crossing guards, and vehicle traffic during peak school hours. With the proposed sidewalk, pedestrians will be encouraged to walk along the north side of Shannon Road, thus reducing the number of pedestrians crossing Shannon Road. Operating Budget Impacts Engineering staff time for design and construction of this project will be addressed in the FY 2018/19 Operating Budget. PROPOSED STREETS PROGRAM Street Improvements C-49 Project Components & Estimated Timeline Fall 2018 Design Project design & development Winter 2018 Bid process Project bidding & contract award Spring 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 104$ -$ 129,896$ -$ 129,896$ -$ -$ -$ -$ 130,000$ TOTAL SOURCE OF FUNDS 104$ -$ 129,896$ -$ 129,896$ -$ -$ -$ -$ 130,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed $ - USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 104 - 129,896 - 129,896 - - - - 130,000 TOTAL GFAR 104$ -$ 129,896$ -$ 129,896$ -$ -$ -$ -$ 130,000$ TOTAL USE OF FUNDS 104$ -$ 129,896$ -$ 129,896$ -$ -$ -$ -$ 130,000$ SIDEWALK IMPROVEMENTS/SHANNON/LOS GATOS BLVD/CHERRY BLOSSOM LANE Project 813-0218 PROPOSED STREETS PROGRAM Street Improvements C-50 LOS GATOS BLVDKENNE D Y R D SHANNO N R D Project Name Stonybrook & Kennedy Road Sidewalk Improvements Project Number 813-0219 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will remove a failing wooden sidewalk along Kennedy Road between Stonybrook Road and Longmeadow Drive and replace with new concrete sidewalk, retaining wall, curb, gutter, drainage improvements, and ADA ramps. Location This project is located on Kennedy Road between Stonybrook Road and Longmeadow Drive. Project Background The existing elevated wooden sidewalk was constructed a number of years ago. Over time, the wooden deck has deteriorated with age and has been damaged by termites. The improvements will be made to remove the existing walkway and replace with a concrete sidewalk. The walkway is adjacent to a drainage course and will require a retaining wall element in order for the sidewalk to match the elevation of Kennedy Road. The design of the project began in Winter 2015, and construction is anticipated to follow in FY 2018/19. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with this project will be charged to the project as it is delivered. PROPOSED STREETS PROGRAM Street Improvements C-51 Project Components & Estimated Timeline Fall 2015 Design Project design & development Spring 2018 Bid process Project bidding & contract award Spring 2018 Construction Project construction Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 35,511$ 28,357$ 516,132$ -$ 516,132$ -$ -$ -$ -$ 580,000$ TOTAL SOURCE OF FUNDS 35,511$ 28,357$ 516,132$ -$ 516,132$ -$ -$ -$ -$ 580,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 35,511 28,357 516,132 - 516,132 - - - - 580,000 TOTAL GFAR 35,511$ 28,357$ 516,132$ -$ 516,132$ -$ -$ -$ -$ 580,000$ TOTAL USE OF FUNDS 35,511$ 28,357$ 516,132$ -$ 516,132$ -$ -$ -$ -$ 580,000$ STONYBROOK & KENNEDY SIDEWALK IMPROVEMETNS Project 813-0219 PROPOSED STREETS PROGRAM Street Improvements C-52 TOWN-WIDE Project Name Sidewalk Improvements – Multiple Locations Project Number 813-0221 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will construct sidewalk, curb, and gutter on the north side of Kennedy Road from Ferris Avenue to Los Gatos Boulevard and on the south side of Mitchell Avenue from George Street to Fisher Avenue. Location This project is located in the following areas: Kennedy Road from Ferris Avenue to Los Gatos Boulevard; Mitchell Avenue from George Street to Fisher Avenue; and Los Gatos Boulevard/Shannon Road. Project Background Kennedy Road from Ferris Avenue to Los Gatos Boulevard currently has a shoulder that is heavily utilized by parents and students walking and biking to school in the morning and afternoons. The sidewalk improvements will complete the connection in this residential block. In 2009, the Town completed the sidewalk installation on the north side of Mitchell Avenue from George Street to Fisher Avenue. Then in 2012, sidewalk was constructed on north and south side of Mitchell Avenue between Los Gatos Boulevard and George Street as part of the redevelopment of the former Honda site. This project will complete the last component of the sidewalks in this heavily utilized pedestrian area between Van Meter Elementary and Fisher Middle Schools. Operating Budget Impacts Engineering staff time for design and construction of this project will be addressed in the FY 2018/19 Operating Budget. PROPOSED STREETS PROGRAM Street Improvements C-53 Project Components & Estimated Timeline Fall 2018 Design Project design & development Winter 2018 Bid process Project bidding & contract award Spring 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$ TOTAL SOURCE OF FUNDS -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 60,000 - 60,000 - - - - - TOTAL GFAR -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$ TOTAL USE OF FUNDS -$ -$ 60,000$ -$ 60,000$ -$ -$ -$ -$ 60,000$ SIDEWALK IMPROVEMENTS - MULTIPLE LOCATIONS Project 813-0221 PROPOSED STREETS PROGRAM Street Improvements C-54 Project Name LED Streetlights Project Number 813-0224 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project has replaced existing streetlights with new energy efficient LED streetlights. Location This project is located Town-wide for all Town-owned streetlights. Project Background The work to install LED streetlights has been completed. This project remains active to allow for project closeout, including paying for project costs and ensuring applicable rate changes are processed by PG&E. The Town has replaced its low pressure sodium lights because the bulbs are not energy efficient and are costly to repair and maintain. LED streetlights have become a proven technology with demonstrable savings in both operations and maintenance costs. LED streetlights are now the Town standard and are being used throughout the Town as new development occurs. This project has replaced old existing streetlight heads with new LED heads. LED streetlights have three main benefits over traditional low-pressure sodium lights. First, LED lights can appear brighter, creating an increased sense of security. Additionally, LED streetlights are far more energy efficient versus the traditional streetlight bulb. Lastly, LED lights last longer, decreasing the costs for replacement. LED streetlights are more expensive to purchase, however, these costs will be recouped in the form of energy savings within less than four years. Generally, any energy efficiency projects with savings under a seven-year timeframe are highly desirable projects to implement. Operating Budget Impacts This project will result in electricity savings, which is projected at $413,000 over the span of this five- year CIP. Project delivery costs for this project are included in the CIP project’s total cost. Project delivery costs are estimated at $43,050 or approximately 11% of the total project cost. Engineering staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-55 Project Components & Estimated Timeline Summer 2015 Design Project design & development Summer 2016 Bid process Project bidding & contract award Summer 2017 Construction Project construction Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 826$ 395,352$ 108,470$ -$ 108,470$ -$ -$ -$ -$ 504,648$ TOTAL SOURCE OF FUNDS 826$ 395,352$ 108,470$ -$ 108,470$ -$ -$ -$ -$ 504,648$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 826 395,352 108,470 - 108,470 - - - - 504,648 TOTAL GFAR 826$ 395,352$ 108,470$ -$ 108,470$ -$ -$ -$ -$ 504,648$ TOTAL USE OF FUNDS 826$ 395,352$ 108,470$ -$ 108,470$ -$ -$ -$ -$ 504,648$ LED STREET LIGHTS Project 813-0224 PROPOSED STREETS PROGRAM Street Improvements C-56 HWY 17LOS GATOS BLVDLOS GA T O S- ALMADEN R D Project Name Utility Undergrounding Improvements Project Number 813-0225 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will remove utilities from above ground poles and install them underground. Location This project is located on Los Gatos Boulevard between Lark Avenue and Chirco Drive. Project Background Through the State of California’s Public Utilities Commission, Pacific Gas & Electric (PG&E) collects funds from ratepayers to provide for the undergrounding of utilities. These funds grow in reserve called Rule 20A funds, until such time that local jurisdictions identify an area for this project and begin working with PG&E. The funds are limited to use on roadways where traffic is heavy, making Los Gatos Boulevard a viable location. The Town’s allocation of Rule 20A funds has grown to the point where there is now approximately $3.8M available for programming. These funds will never actually come to the Town, but rather PG&E will deliver the project with coordination from Town staff. In addition to the Rule 20A funds, the Town collects developer fees for utility undergrounding. These funds are held by the Town for future projects. Staff has asked PG&E to look at an expanded project scope utilizing some or all of the Town funds as well. This will take full advantage of economies of scale through design and construction. The timeframe for PG&E to deliver Rule 20A projects has been between seven and ten years; however, indications are that this project may begin sooner. Funds have been moved to demonstrate a start of construction in FY 2018/19, with the bulk of the work occurring in FY 2019/20. Operating Budget Impacts There will be no Operating Budget impact as a result of this project. Project delivery costs for this project are included in the CIP project’s total cost. Project delivery costs are estimated at $266,000 over the five year term of the project or 4% of the total project cost. Project costs are significantly lower on this project due to the efficiencies in the project size and a larger proportion of work that will be coordinated by PG&E. PROPOSED STREETS PROGRAM Street Improvements C-57 Project Components & Estimated Timeline Fall 2017 Design Project design & development Summer 2019 Construction Project construction begins Summer 2020 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) UTILITY UNDERGROUNDING -$ -$ 112,000$ 2,218,000$ 2,330,000$ 4,436,000$ -$ -$ -$ 6,766,000$ TOTAL SOURCE OF FUNDS -$ -$ 112,000$ 2,218,000$ 2,330,000$ 4,436,000$ -$ -$ -$ 6,766,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) UTILITY UNDERGORUNDING Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 112,000 2,218,000 2,330,000 4,436,000 - - - 6,766,000 TOTAL GFAR -$ -$ 112,000$ 2,218,000$ 2,330,000$ 4,436,000$ -$ -$ -$ 6,766,000$ TOTAL USE OF FUNDS -$ -$ 112,000$ 2,218,000$ 2,330,000$ 4,436,000$ -$ -$ -$ 6,766,000$ UTILITY UNDERGROUNDING IMPROVEMENTS Project 813-0225 PROPOSED STREETS PROGRAM Street Improvements C-58 Project Name Cut-Through Traffic Mitigation Project Number 813-0229 Department Parks & Public Works Project Manager PPW Director: Matt Morley Description This project will provide infrastructure changes to help mitigate cut-through traffic. Location This project is located Town-wide. Project Background This project aims to mitigate cut-through traffic through the use of various measures, some of which have been previously used. In the summer of 2015, staff implemented various measures such as the deployment of portable message signs, messages on Caltrans changeable message signs, signal modifications, and temporary street closures to reduce cut-through traffic. In the summer of 2016, this project included signal modifications and synchronization at various intersections, roadway markings and additional signage, as well as costs associated with the temporary closure of south Santa Cruz Avenue at Wood Road and associated data collection. In FY 2018/19, funding will be used to advance the design of a permanent traffic circle at Santa Cruz Avenue at Wood Road, potential street closures, and neighborhood turn restriction signage as needed. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-59 Project Components & Estimated Timeline Winter 2017 Design Coordinate and design projects Summer 2018 Construction Install infrastructure and implement projects Fall 2018 Completion Assess Results Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ 149,655$ 50,000$ 10,000$ 60,000$ -$ -$ -$ -$ 209,655$ TRAFFIC MITIGATION 13,695 59,478 46,721 - 46,721 - - - - 119,894$ TOTAL SOURCE OF FUNDS 13,695$ 209,133$ 96,721$ 10,000$ 106,721$ -$ -$ -$ -$ 329,549$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - 149,655 50,000 10,000 60,000 - - - - 209,655 TOTAL GFARS -$ 149,655$ 50,000$ 10,000$ 60,000$ -$ -$ -$ -$ 209,655$ TRAFFIC MITIGATIONS Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 13,695 59,478 46,721 - 46,721 - - - - 119,894 TOTAL TRAFFIC MITIGATIONS 13,695$ 59,478$ 46,721$ -$ 46,721$ -$ -$ -$ -$ 119,894$ TOTAL USE OF FUNDS 13,695$ 209,133$ 96,721$ 10,000$ 106,721$ -$ -$ -$ -$ 329,549$ CUT-THROUGH TRAFFIC MITIGATION Project 813-0229 PROPOSED STREETS PROGRAM Street Improvements C-60 Project Name Traffic Signal Modernization Project Number 813-0227 Department Parks & Public Works Project Manager PPW Director: Matt Morley Description This project will modernize the Town’s traffic signal controllers. Location This project is located Town-wide. Project Background This project will modernize the Town’s traffic signal controllers to allow for greater control by staff, ensure that the current system meets current safety standards, and increase the traffic flow. The Town was awarded several grants through the VTA and the MTC for $1,200,000 of the project budget to complement the Town’s investment of Traffic Impact Mitigation Funds. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-61 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Winter 2018 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATION -$ -$ 177,869$ 177,869$ 355,738$ 374,949$ 415,027$ -$ -$ 1,145,713$ GRANTS & AWARDS 3,375 16,875 1,183,125 - 1,183,125$ - - - - 1,203,375 TOTAL SOURCE OF FUNDS 3,375$ 16,875$ 1,360,994$ 177,869$ 1,538,863$ 374,949$ 415,027$ -$ -$ 2,349,088$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATIONS Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 177,869 177,869 355,738 374,949 415,027 - - 1,145,713 TOTAL TRAFFIC MITIGATIONS -$ -$ 177,869$ 177,869$ 355,738$ 374,949$ 415,027$ -$ -$ 1,145,713$ GRANTS & AWARDS Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 3,375.00 16,875 1,183,125 - 1,183,125 - - - - 1,203,375 TOTAL GRANTS & AWARDS 3,375$ 16,875$ 1,183,125$ -$ 1,183,125$ -$ -$ -$ -$ 1,203,375$ TOTAL USE OF FUNDS 3,375$ 16,875$ 1,360,994$ 177,869$ 1,538,863$ 374,949$ 415,027$ -$ -$ 2,349,088$ TRAFFIC SIGNAL MODERNIZATION Project 813-0227 PROPOSED STREETS PROGRAM Street Improvements C-62 Project Name Bicknell Road Storm Drain Improvements Project Number 816-0410 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will reroute a Town storm drain line. Location This project is located on Bicknell Road near Montclair. Project Background This project will provide design services for the rerouting of an existing Town storm drain line from private property, after it was determined that the Town does not have a storm drain easement. Operating Budget Impacts This project will use staff time for construction inspection and management. The staff time for this project is included in the Department’s FY 2018/19 Operating Budget. QUITO RDBICKNELL RD HWY 9 PROPOSED STREETS PROGRAM Street Improvements C-63 Project Components & Estimated Timeline Fall 2017 Design Project design & development Spring 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) STORM BASIN #3 12,750$ 95,642$ 63,108$ -$ 63,108$ -$ -$ -$ -$ 108,392$ TOTAL SOURCE OF FUNDS 12,750$ 95,642$ 63,108$ -$ 63,108$ -$ -$ -$ -$ 108,392$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) STORM BASIN #2 Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 12,750 95,642 63,108 - 63,108 - - - - 108,392 TOTAL STORM BASIN 12,750$ 95,642$ 63,108$ -$ 63,108$ -$ -$ -$ -$ 108,392$ TOTAL USE OF FUNDS 12,750$ 95,642$ 63,108$ -$ 63,108$ -$ -$ -$ -$ 108,392$ BICKNELL ROAD STORM DRAIN IMPROVEMENTS Project 816-0410 PROPOSED STREETS PROGRAM Street Improvements C-64 Project Name Bicycle & Pedestrian Improvements Project Number 813-0231 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will enhance bicycle and pedestrian safety and mobility throughout the Town. Location This project is located Town-wide. Project Background This project will enhance bicycle and pedestrian safety and mobility Town-wide in the form of multiple projects. In the first year of funding, the Town Council has prioritized projects that were recommended by Safe Routes to School from the original Traffic Around Schools Study. In future years of funding, staff will continue to work with Safe Routes to School, Town Commissions, the Town Council, and the general public on prioritizing projects that have been recommended in the Council adopted Bicycle and Pedestrian Master plan and priorities identified in FY 2017/18 budget cycle for bicycle and pedestrian projects. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-65 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Winter 2018 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ 63,700$ 236,300$ 300,000$ 536,300$ -$ -$ -$ -$ 600,000$ TRAFFIC MITIIGATION - - 75,000 - 75,000 - - - - 75,000 TOTAL SOURCE OF FUNDS -$ 63,700$ 311,300$ 300,000$ 611,300$ -$ -$ -$ -$ 675,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - 63,700 236,300 300,000 536,300 - - - - 600,000 TOTAL GFAR -$ 63,700$ 236,300$ 300,000$ 536,300$ -$ -$ -$ -$ 600,000$ TRAFFIC MITIGATION Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - Consultant Services - - - - - - - - - Project Construction Expenses - - 75,000 - 75,000 - - - - 75,000 TOTAL TRAFFIC MITIGATION -$ -$ 75,000$ -$ 75,000$ -$ -$ -$ -$ 75,000$ TOTAL USE OF FUNDS -$ 63,700$ 311,300$ 300,000$ 611,300$ -$ -$ -$ -$ 675,000$ BICYCLE & PEDESTRIAN IMPROVEMENTS Project 813-0231 PROPOSED STREETS PROGRAM Street Improvements C-66 Project Name Stormwater Master Plan Project Number 816-0413 Department Parks & Public Works Project Manager PPW Director: Matt Morley Description This project will develop a Stormwater Master Plan. Location This project is located Town-wide. Project Background The Town of Los Gatos does not currently have an adopted Stormwater Master Plan. This project will develop a Stormwater Collection System Master Plan and provides the Town of Los Gatos with the necessary planning tools and capital improvement projects to address flood management and water quality within the collector portion of the storm drainage system. The Plan will be developed to help the Town meet its overarching environmental and economic goals. The goal of the Stormwater Master Plan is to manage stormwater runoff proactively to protect water quality and to minimize impacts of localized and downstream flooding by identifying infrastructure improvements for the collection, conveyance, and treatment of stormwater runoff within the Town. The Stormwater Master Plan will prioritize storm drain and water quality improvements within the Town and provides an implementation plan for the construction of conveyance and water quality improvements. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-67 Project Components & Estimated Timeline Summer 2018 Design Develop request for proposals Fall 2018 Bid Process Award consultant agreement Winter 2018 Construction Conduct study Spring 2019 Completion Finalize report Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 200,000$ -$ 200,000$ -$ -$ -$ -$ -$ TOTAL SOURCE OF FUNDS -$ -$ 200,000$ -$ 200,000$ -$ -$ -$ -$ -$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 200,000 - 200,000 - - - - - TOTAL GFAR -$ -$ 200,000$ -$ 200,000$ -$ -$ -$ -$ 200,000$ TOTAL USE OF FUNDS -$ -$ 200,000$ -$ 200,000$ -$ -$ -$ -$ 200,000$ STORMWATER MASTER PLAN Project 816-0414 PROPOSED STREETS PROGRAM Street Improvements C-68 Project Name Stormwater System – Pollution Prevention Compliance Project Number 816-0414 Department Parks & Public Works Project Manager PPW Director: Matt Morley Description This project will install improvements, such as trash capture devices, to reduce pollution in the storm water solution. Location This project is located Town-wide. Project Background This project will install solutions, such as multiple trash capture devices in storm inlets, throughout the Town to meet the Municipal Regional Permit Provision C.10 trash reduction requirements. The Town has submitted a plan to meet the requirement to reduce trashload impacts to creeks which are: 70% by 2017 and 100% by 2022. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-69 Project Components & Estimated Timeline Summer 2018 Design Project design & development Winter 2018 Bid Process Project bidding & contract award Spring 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 300,000$ 300,000$ -$ -$ -$ -$ 300,000$ TOTAL SOURCE OF FUNDS -$ -$ -$ 300,000$ 300,000$ -$ -$ -$ -$ 300,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 300,000 300,000 - - - - 300,000 TOTAL GFAR -$ -$ -$ 300,000$ 300,000$ -$ -$ -$ -$ 300,000$ TOTAL USE OF FUNDS -$ -$ -$ 300,000$ 300,000$ -$ -$ -$ -$ 300,000$ STORMWATER SYSTEM - POLLUTION PREVENTION COMPLIANCE Project 816-0414 PROPOSED STREETS PROGRAM Street Improvements C-70 Project Name Public Arts Gateway Project Number 821-2009 Department Library Project Manager Library Director: Ryan Baker Description This project will install public art at gateway locations throughout the Town. Location This project is located Town-wide. Project Background The Arts and Culture Commission identified this project as a way to enhance the appearance of the entrances into Los Gatos. At the January 31, 2017 Priority Setting, Council identified $25,000 for public art and on April 18, 2017 the Arts and Culture Commission proposed the gateway project as the best use of the funds, which Council approved. This project will install the first phase of artwork at Town entrances based on the Town’s Public Art Selection Policy and Procedures. Operating Budget Impacts This project will use staff time for construction inspection and management. The staff time for this project is included in the Department’s FY 2018/19 Operating Budget. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-71 Project Components & Estimated Timeline Summer 2018 Call for artist Project design & award Winter 2018 Construction Project construction Spring 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ TOTAL SOURCE OF FUNDS -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 25,000 - 25,000 - - - - 25,000 TOTAL TRAFFIC MITIGATION -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ TOTAL USE OF FUNDS -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ PUBLIC ART GATEWAY Project 821-2009 PROPOSED STREETS PROGRAM Street Improvements C-72 E MAIN ST HWY 17 Project Name Jones Road Storm Drain Improvements Project Number 816-0415 Department Parks & Public Works Project Manager PPW Director: Matt Morley Description This project will install new storm piping and a drain inlet on Jones Road. Location This project is located on Jones Road. Project Background The existing storm drain improvements along Jones Road were part of a 1948 subdivision. This portion of the storm drain system accepts Town roadway runoff from Jones Road and empties the water into the Town’s storm system. Currently water from the Jones Road trailhead flows down the street and overwhelms the system, creating ponding and carrying debris to downstream residential residents. Resolution to this issue can be achieved through the installation of new storm piping and a drain inlet on Jones Road. The new infrastructure will capture the stormwater upstream and channel it into the stormy system, relieving the ponding issues that now occur. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED STREETS PROGRAM Street Improvements C-73 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Winter 2018 Construction Project construction Spring 2019 Completion Project Completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) STORM BASIN #2 -$ 18,700$ 2,300$ -$ 2,300$ -$ -$ -$ -$ 18,700$ TOTAL SOURCE OF FUNDS -$ 18,700$ 2,300$ -$ 2,300$ -$ -$ -$ -$ 18,700$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) STORM BASIN #2 Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - 18,700 2,300 - 2,300 - - - - 18,700 TOTAL STORM BASIN -$ 18,700$ 2,300$ -$ 2,300$ -$ -$ -$ -$ 18,700$ TOTAL USE OF FUNDS -$ 18,700$ 2,300$ -$ 2,300$ -$ -$ -$ -$ 18,700$ JONES ROAD STORM DRAIN IMPROVEMENTS Project 816-0415 PROPOSED STREETS PROGRAM Street Improvements C-74 Project Name Downtown Parking Study Project Number 813-0233 Department Parks & Public Works Project Manager PPW Director: Matt Morley Description This project will fund a consultant to examine parking holistically in the downtown and high school areas. Location This project is located downtown and near Los Gatos High School. Project Background The project scope will include the following: • Analyze existing parking capacity. • Provide a recommendation for residential (permit area parking, especially as it is impacted around Los Gatos High School. • Provide recommendations for parking management for time limited parking. • Analyze paid parking. • Provide best practices recommendations for managing employee parking. • Identify the need for additional parking capacity vis-a-vis a parking structure. • Review the impacts of one-way streets on parking capacity. Operating Budget Impacts This project will use staff time for project management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED STREETS PROGRAM Street Improvements C-75 Project Components & Estimated Timeline Summer 2018 Design Project design & development Summer 2018 Bid Process Project bidding & contract award Summer 2019 Completion Project Completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ TOTAL SOURCE OF FUNDS -$ -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 200,000 200,000 - - - - 200,000 TOTAL GFAR -$ -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ TOTAL USE OF FUNDS -$ -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ DOWNTOWN PARKING STUDY Project 813-0233 PROPOSED STREETS PROGRAM Street Improvements C-76 HWY 9 E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV Project Name One-Way Downtown Street Pilot Project Number 813-0234 Department Parks & Public Works Project Manager PPW Director: Matt Morley Description This project will fund the implementation of a one-way streets pilot. Location This project is located downtown on North Santa Cruz Avenue and University Avenue. Project Background This project will fund a trial of one-way streets for North Santa Cruz and University Avenues between Highway 9 and Main Street. Operating Budget Impacts This project will use staff time for management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED STREETS PROGRAM Street Improvements C-77 Project Components & Estimated Timeline Summer 2018 Design Project design & development Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR - - - 130,000 130,000 - - - - 130,000 TOTAL SOURCE OF FUNDS - - - 130,000 130,000 - - - - 130,000 Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits - - - - - - - - - - Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 130,000 130,000 - - - - 130,000 GFAR - - - 130,000 130,000 - - - - 130,000 TOTAL USE OF FUNDS - - - 130,000 130,000 - - - - 130,000 ONE-WAY DOWNTOWN STREET PILOT Project 813-0234 PROPOSED STREETS PROGRAM Street Improvements C-78 Project Name Annual Storm Drain Improvement Project Project Number 816-0414 Department Parks & Public Works Project Manager Assistant Director/Town Engineer: Lisa Petersen Description This project will install infill storm drain systems that are required to enhance safety and improve infrastructure to accept water runoff. Location This project is located Town-wide. Project Background The Town is responsible for keeping Town roads clear of excessive water and managing storm water running down Town streets. Storm drain improvements in the Town right of ways and parking lots are necessary to manage water drainage issues within these Town locations. The intent of this project is to keep pace with the needs of the Town’s storm drain system to prevent flooding in the Town right of ways. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-79 Project Components & Estimated Timeline Summer 2018 Design Project design & development Winter 2018 Bid Process Project bidding & contract award Spring 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) STORM BASIN #1 -$ -$ -$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 250,000$ STORM BASIN #2 - - - 50,000 50,000 50,000 50,000 50,000 50,000 250,000 STORM BASIN #3 - - - 50,000 50,000 50,000 50,000 50,000 50,000 250,000 TOTAL SOURCE OF FUNDS -$ -$ -$ 150,000$ 150,000$ 150,000$ 150,000$ 150,000$ 150,000$ 750,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) STORM BASIN #1 Project Construction Expenses - - - 50,000 50,000 50,000 50,000 50,000 50,000 250,000 TOTAL STORM BASIN #1 -$ -$ -$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 250,000$ STORM BASIN #2 Project Construction Expenses -$ -$ -$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 250,000$ TOTAL STORM BASIN #2 -$ -$ -$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 250,000$ STORM BASIN #3 Project Construction Expenses -$ -$ -$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 250,000$ TOTAL STORM BASIN #3 -$ -$ -$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 50,000$ 250,000$ TOTAL USE OF FUNDS -$ -$ -$ 150,000$ 150,000$ 150,000$ 150,000$ 150,000$ 150,000$ 750,000$ ANNUAL STORM DRAIN IMPROVEMENT PROJECT Project 816-0412 PROPOSED STREETS PROGRAM Street Improvements C-80 Project Name Pilot School Busing Program Project Number 812-0128 Department Parks & Public Works Project Manager Transportation & Mobility Manager: Ying Smith Description This project will explore congestion relief through piloting school bus service. The pilot school bus service will provide morning and afternoon routes to and from school, with neighborhood-based stops. Vehicles and drivers would meet Federal, State and industry-best-practice safety standards. The Town will contract the service to a qualified school bus transportation provider through a RFP process. The service schedule and designated pick up and drop off locations will be published. Interested families may purchase an annual pass to reserve a seat. The pilot program will provide two routes for a total of 24 months. Location This project is located Town-wide. Project Background The Town of Los Gatos and the school community have been exploring new transit services customized to meet the needs of students traveling to and from schools. The primary areas of interest are corridors with the highest level of traffic congestion. Town staff and a consulting team are working on a Congestion Relief School Bus Feasibility Study, which will be completed in the fall of 2019. Based on surveys with the school families and community input, staff is recommending a Pilot Service starting in January 2019. Operating Budget Impacts Funding would come from Transportation Fund for Clean Air grant (pending), Town sources as well as fees from parents / guardians whose students utilize the service. This project will use staff time for service design. PPW staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED STREETS PROGRAM Street Improvements C-81 Project Components & Estimated Timeline Summer 2018 Design Service plan design, marketing, customer sign up Fall 2018 Bid Process RFP & service contract award, finalize service plan Spring 2019 Construction Service Launch Winter 2020 Completion Completion of total 2 years (24 mo.) of service Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 80,600$ 80,600$ 161,200$ 311,880$ -$ -$ 553,680$ GRANTS & AWARDS - - - 30,000 30,000$ 60,000 30,000 - - 120,000 TOTAL SOURCE OF FUNDS -$ -$ -$ 110,600$ 110,600$ 221,200$ 341,880$ -$ -$ 673,680$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 80,600 80,600 161,200 311,880 - - 553,680 TOTAL GFAR -$ -$ -$ 80,600$ 80,600$ 161,200$ 311,880$ -$ -$ 553,680$ GRANTS & AWARDS Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 30,000 30,000 60,000 30,000 - - 120,000 TOTAL GRANTS & AWARDS -$ -$ -$ 30,000$ 30,000$ 60,000$ 30,000$ -$ -$ 120,000$ TOTAL USE OF FUNDS -$ -$ -$ 110,600$ 110,600$ 221,200$ 341,880$ -$ -$ 673,680$ PILOT SCHOOL BUSING PROGRAM Project 812-0128 PROPOSED STREETS PROGRAM Street Improvements C-82 LOS GATOS BLVDHWY 17N SANTA CRUZ AVBLOSSOM H I L L R D SHANN O N R D UNIVERSITY AV Project Name Highway 17 Bicycle & Pedestrian Bridge Preliminary Design Project Number 818-0803 Department Parks & Public Works Project Manager Transportation & Mobility Manager: Ying Smith Description This project will fund the conceptual engineering for a potential bicycle and pedestrian bridge. Location This project is located at Blossom Hill Road or Nino Way over Highway 17. Project Background Crossing Highway 17 in the project vicinity is a barrier for bicyclists and pedestrians. This is a suggested path included in the Safe Routes to School Phase 1 Study. Improvements for Highway 17 crossing have been included in several policy documents. The Bicycle and Pedestrian Master Plan (BPMP) identified the Nino Avenue Bridge over Highway 17 as one of the new bike/pedestrian bridge connections. The Town’s General Plan identified widening the Blossom Hill Road Bridge over Highway 17 for bicyclists and pedestrians. The project is also included in the Traffic Impact Mitigation Fee program and the Town’s submittals to the VTA’s Valley Transportation Plan 2040. Implementing long-term and complex capital projects requires a strategic financing plan. Obtaining the first round of funding at the critical time is the key to initiate the process. Most funding programs either require or prioritize projects that are “shovel ready.” This funding allocation will advance the project to enable greater competition for funding of later phases. In future years, additional funds will be needed for environmental clearance, right-of-way, and final design. It is estimated that additional $800,000 will be required to complete all engineering and design work, over approximately three to five years. The construction cost will be in the $5 to $10 million range. Completing the first step would enhance the Town’s access to a combination of funds available through competitive opportunities. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED STREETS PROGRAM Street Improvements C-83 Project Components & Estimated Timeline Summer 2018 Design Project design & development Spring 2023 Bid Process Project bidding & contract award Summer 2023 Construction Project construction Summer 2024 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATION -$ -$ -$ 147,005$ 147,005$ -$ -$ -$ -$ 147,005$ GRANTS & AWARDS - - - 52,995 52,995$ - - - - 52,995 TOTAL SOURCE OF FUNDS -$ -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) TRAFFIC MITIGATION Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 147,005 147,005 - - - - 147,005 TOTAL TRAFFIC MITIGATION -$ -$ -$ 147,005$ 147,005$ -$ -$ -$ -$ 147,005$ GRANTS & AWARDS Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 52,995 52,995 - - - - 52,995 TOTAL GRANTS & AWARDS -$ -$ -$ 52,995$ 52,995$ -$ -$ -$ -$ 52,995$ TOTAL USE OF FUNDS -$ -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ HIGHWAY 17 BICYCLE AND PEDESTRIAN BRIDGE Project 818-0803 PROPOSED STREETS PROGRAM Street Improvements C-84 PROPOSED STREETS PROGRAM Bridge Projects C-85 LO S G A T O S - S A R A T O G A R D LOS GATOS BLVDE MAIN STHWY 17HWY 17N SANTA CRUZ AVWINCHESTER BLVDBLOSSOM HILL RDLOS GATOS BLVDHW Y 8 5 KENNE D Y R D SHA N N O N R D A POLLARD R D QUITO RD PROJECT LOCATIONS A Quito Road - Bridge Replacement PROPOSED STREETS PROGRAM Bridge Projects C-86 PROGRAM SECTION DIRECTORY PAGE 0801 Quito Road - Bridge Replacement C – 88 PROPOSED STREETS PROGRAM Bridge Projects C-87 The Streets Program’s Bridge Projects section contains Capital Improvement Program projects that repair, replace, or rehabilitate a deficient bridge structure as the primary scope of work. Bridge structure safety falls under the guidance of state and federal regulations, and bridge projects are often driven by available funding from these jurisdictions, such as Caltrans grant programs or the federal Highway Bridge Replacement and Rehabilitation (HBRR) program. Los Gatos does not have a designated funding source for repairing, maintaining, and improving the Town’s bridges, and relies upon grant programs for major bridge improvement projects. BRIDGE PROJECTS SUMMARY Carryforward Projects 0801 Quito Road - Bridge Replacement 64,594$ 235,087$ -$ -$ -$ -$ 299,681$ Total Bridge Projects 64,594$ 235,087$ -$ -$ -$ -$ 299,681$ Expended Through 2017/18 Total Budgeted FY 2018/19- 2022/23 CAPITAL IMPROVEMENT PROGRAM 2019/20 Budget 2018/19 Budget & Carryfwd* 2022/23 Budget BRIDGE PROJECTS 2021/22 Budget 2020/21 Budget * Total FY 2017/18 Carryforward $235,087 PROPOSED STREETS PROGRAM Bridge Projects C-88 Project Name Quito Road - Bridge Replacement Project Number 818-0801 Department Parks & Public Works Project Manager Town Engineer: Lisa Petersen Description This project funds the Town’s portion of the replacement cost for two bridges on Quito Road to improve roadway safety and provide adequate storm water flow capacity in the creek under the bridge. Location The two Quito Road bridges span a tributary of San Tomas Aquino Creek. The bridges are located on Quito Road in the vicinity of Old Adobe Road, approximately 1½ miles north of Highway 9, on the common boundary line between the City of Saratoga and the Town of Los Gatos. Project Background San Tomas Aquino Creek is under the jurisdiction of the Santa Clara Valley Water District (SCVWD), while the replacement of the bridges is the shared responsibility of the City of Saratoga and the Town of Los Gatos. Both bridges are approximately ninety years old and have been classified “structurally deficient” under Caltrans guidelines. In addition, both bridges are not adequate to receive 100-year flood flows. In 2001, the City of Saratoga, the project sponsor, secured partial funding (80%) through the federal Highway Bridge Replacement and Rehabilitation (HBRR) program to replace both bridges with wider span structures that will allow the 100-year design flood flow to pass underneath. Saratoga is the lead agency to oversee the design, environmental, right-of-way acquisition, and construction services for the project. The City of Saratoga, the Town of Los Gatos, and SCVWD agreed to share the duties and responsibilities for the project and the remaining 20% local match funding requirement. After further evaluation of the bridges, it was determined that Quito Road would require reconstruction at each end of the bridge, which in turn requires additional right-of-way acquisitions and environmental reviews under both the State of California (Caltrans) and federal regulations. These changes have made it necessary to redesign this project, significantly increasing the estimated costs. The City of Saratoga has applied for additional funding from Caltrans due to the redesign. As a result of the additional project costs, the local funding match from the City of Saratoga, the Town of Los Gatos, and the SCVWD has increased from $155,000 to $238,000 for each agency. Based on the April 2012 schedule from the City of Saratoga, the construction of these bridges is anticipated to be completed by 2018. Operating Budget Impacts Engineering staff time for coordination of this project with the City of Saratoga is incorporated into the FY 2017/18 Operating Budget. Completion of this project will mitigate the potential costs of lawsuits from bridge failure and pre-empt the cost of replacing the bridge in an emergency situation. HW Y 8 5 POLLARD R D QUITO RD PROPOSED STREETS PROGRAM Bridge Projects C-89 Project Components & Estimated Timeline Jan 2001 Grant Funding The City of Saratoga obtained grant funding from the federal HBRR program Oct 2001 Cooperative Agreement Council approved a cooperative agreement with the City of Saratoga and SCVWD for the replacement of the two bridges May 2002 Preliminary Design City of Saratoga started preliminary design 2013 Right of way Right of way acquisition process is ongoing and environmental permitting is underway 2015 Final Design Design completed and project bidding by the City of Saratoga 2018 Completion Construction is anticipated to begin in 2016 and be completed by 2018 Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 64,594$ -$ 235,087$ -$ 235,087$ -$ -$ -$ -$ 299,681$ TOTAL SOURCE OF FUNDS 64,594$ -$ 235,087$ -$ 235,087$ -$ -$ -$ -$ 299,681$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 64,594 - 235,087 - 235,087 - - - - 299,681 TOTAL GFAR 64,594$ -$ 235,087$ -$ 235,087$ -$ -$ -$ -$ 299,681$ TOTAL USE OF FUNDS 64,594$ -$ 235,087$ -$ 235,087$ -$ -$ -$ -$ 299,681$ QUITO ROAD - BRIDGE REPLACEMENT Project 818-0801 PROPOSED STREETS PROGRAM Bridge Projects C-90 Parks Program PROPOSED PARKS AND TRAILS PROGRAM D-1 PARK PROJECT DIRECTORY 4605 Parks Playground Fibar Project D – 6 3104 Park Rehabilitation – Bachman Park D – 8 3303 Belgatos Park Restroom Improvements D – 10 4609 Creek Trail & Parks Pathway & Parking Lot Seal Coat and Striping D – 12 4202 Town Plaza Turf Repairs D – 14 4006 Outdoor Fitness Equipment D – 16 TRAIL PROJECT DIRECTORY 4504 Open Space Trail Upgrades D – 22 4507 Forbes Mill Footbridge Improvements D – 24 4503 Charter Oaks Trail Repair D – 26 4505 Trailhead Connector Project D – 28 PROPOSED PARKS AND TRAILS PROGRAM Park Improvement Projects D-2 PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-3 PROJECT LOCATIONS A Parks Playground Fibar Project B Park Rehabilitation – Bachman Park C Belgatos Park Restroom Improvements D Creek Trail & Parks Pathway & Parking Lot Seal Coat and Striping E Town Plaza Turf Repairs F Outdoor Fitness Equipment LO S G A T O S - S A R A T O G A R D LOS GATOS BLVDE MAIN STHWY 17HWY 17N SANTA CRUZ AVWINCHESTER BLVDBLOSSOM HILL RDLOS GATOS BLVDHW Y 8 5 KENNE D Y R D SHA N N O N R D LA R K A V LOS GATOS-ALMADEN RD UNIVERSITY AVWEDGEWOOD KNOWLE S A, D AND F ARE TOWN-WIDE PROJECTS B RDBELGATOSE C PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-4 PROGRAM SECTION DIRECTORY PAGE 4605 Parks Playground Fibar Project D – 6 3104 Park Rehabilitation – Bachman Park D – 8 3303 Belgatos Park Restroom Improvements D – 10 4609 Creek Trail & Parks Pathway & Parking Lot Seal Coat and Striping D – 12 4202 Town Plaza Turf Repairs D – 14 4006 Outdoor Fitness Equipment D – 16 PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-5 The Parks Program’s Park Improvement Projects section contains Capital Improvement Program projects that repair or improve a Town park as the primary scope of work. Typical park improvement projects include parking lot, walkway, and basketball or tennis court resurfacing; and park equipment or facility upgrades. The Park Improvement Projects section does not have ongoing programs; all projects are considered one-time projects. The exception to this is the Parks Fibar replacement project. Because Fibar requires regular replacement and infill, this project is scheduled as a bi-annual project. One-time park improvement projects are prioritized based on health and safety issues, available funding sources, infrastructure impacts, project costs, and community impacts. Los Gatos does have Park Construction Tax Revenue as a designated funding source for the Parks operating program budget; however, tax receipts are limited to approximately $11,000 per year, and are not sufficient for a capital program. In addition to GFAR funding, grants, in-lieu fees, and CDBG funds are pursued and utilized for park improvements when available. PARK IMPROVEMENT PROJECTS SUMMARY * Total FY 2017/18 Carryforward $565,659 Unfunded Projects • Oak Meadow Park Upgrades • Worcester Park • Civic Center Irrigation System Replacement & Upgrade • Turf Renovations - Various Parks • Oak Meadow Park Fencing Upgrades • Oak Meadow Park Turf Upgrades • Oak Meadow Park Restroom Expansion • Park Rehabilitation – La Rinconada Park • Park Rehabilitation –Live Oak Manor Park • Park Rehabilitation – Blossom Hill Park PARKS Carryforward Projects 4605 Parks Playground Fibar Project 63,460$ 36,540$ -$ 25,000$ -$ 25,000$ 150,000$ 3104 Park Rehabilitation - Bachman Park 10,418 529,119 - - - - 539,537 3303 Belgatos Park Restroom Improvements - 25,000 - - - - 25,000 New Projects 4202 Town Plaza Turf Repairs - 28,000 - - - - 28,000 4006 Oak Meadow Park Exercise Equipment - 60,000 - - - - 4609 Creek Trail & Parks Path & Parking Lot Seal & Striping - 225,000 - - - - Total Park Improvement Projects 73,878$ 903,659$ -$ 25,000$ -$ 25,000$ 742,537$ 2018/19 Budget & Carryfwd* 2019/20 Budget 2020/21 Budget 2021/22 Budget FY 2018/19- 2022/23 CAPITAL IMPROVEMENT PROGRAM PARK AND TRAIL IMPROVEMENT PROJECTS Expended Through 2017/18 2022/23 Budget Total Budgeted PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-6 Project Name Parks Playground Fibar Project Project Number 831-4605 Department Parks & Public Works Project Manager Superintendent: Steve Regan Description This project will replace fibar material at all Town playgrounds. Location This project will be completed at various parks in Los Gatos. Project Background Several Town parks have playground structures that are heavily used by children and their families. Playground safety codes require that the fibar material be spread under and around playground structures to prevent injury to children. Fibar replacement is required when the material is below a specific depth near the playground structure. Fibar is a wood product that degrades over time based on foot traffic and weather conditions. This material should be replaced on a regular, as needed basis. This is an annual CIP project to improve the safety of the Town’s playgrounds. Operating Budget Impacts This project will use staff time for construction inspection and management. The staff time for this project is included in the department’s FY 2018/19 Operating Budget. TOWN-WIDE PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-7 Project Components & Estimated Timeline Summer 2018 Design Project development Summer 2018 Bid Process Project bidding & contract award Summer 2018 Construction Project construction Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 42,500$ 20,960$ 11,540$ 25,000$ 36,540$ -$ 25,000$ -$ 25,000$ 150,000$ TOTAL SOURCE OF FUNDS 42,500$ 20,960$ 11,540$ 25,000$ 36,540$ -$ 25,000$ -$ 25,000$ 150,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 42,500 20,960 11,540 25,000 36,540 - 25,000 - 25,000 150,000 TOTAL GFAR 42,500$ 20,960$ 11,540$ 25,000$ 36,540$ -$ 25,000$ -$ 25,000$ 150,000$ TOTAL USE OF FUNDS 42,500$ 20,960$ 11,540$ 25,000$ 36,540$ -$ 25,000$ -$ 25,000$ 150,000$ PARKS PLAYGROUND FIBAR PROJECT Project 831-4605 PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-8 H W Y 9 W M A I N S T HWY 17N SANTA CRUZ AVUNIVERSITY AV Project Name Park Rehabilitation - Bachman Park Project Number 831-3104 Department Parks & Public Works Project Manager Superintendent: Steve Regan Description This project will make improvements to the park pathway and lighting system. Location The project is located at Bachman Park, bordered by Bachman, Belmont, and Nicholson Avenues. Project Background Bachman Park is a small 3.6-acre neighborhood park close to downtown Los Gatos. The park features a basketball court on the southwest side of the park, playground equipment, as well as a large lawn area for recreational use. Over the last several years, the basketball court was resurfaced, the playground equipment was retrofitted to be in compliance with consumer quality guidelines, and the turf irrigation system was replaced. Other major park infrastructure improvements have not been made to this park in many years due to limited funding. This project will make improvements to the asphalt pathway, retaining walls, as well as the park’s pathway lighting. The lighting in this particular park is outdated and will be replaced with more energy efficient lighting fixtures. Additional improvements include: a new concrete sidewalk, landscape improvements, ivy removal, and reseeding and grading. The improvements will be scheduled in phases to minimize the impact on park users. This project shows the use of CDBG funds for pathway improvements. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-9 Project Components & Estimated Timeline Fall 2017 Design Project design through community outreach process Spring 2018 Bid Process Project bidding & contract award Spring 2018 Construction Project construction Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ 10,418$ 314,582$ -$ 314,582$ -$ -$ -$ -$ 325,000$ GRANTS & AWARDS - - 214,537 - 214,537 - - - - 214,537 TOTAL SOURCE OF FUNDS -$ 10,418$ 529,119$ -$ 529,119$ -$ -$ -$ -$ 539,537$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - 10,418 314,582 - 314,582 - - - - 325,000$ TOTAL GFAR -$ 10,418$ 314,582$ -$ 314,582$ -$ -$ -$ -$ 325,000$ GRANTS &AWARDS Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - Consultant Services - - - - - - - - - Project Construction Expenses - - 214,537 - 214,537 - - - - 214,537$ TOTAL GRANTS & AWARDS -$ -$ 214,537$ -$ -$ -$ -$ -$ 214,537$ TOTAL USE OF FUNDS -$ 10,418$ 529,119$ -$ 529,119$ -$ -$ -$ -$ 539,537$ PARK REHABILITATION - BACHMAN PARK Project 831-3104 PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-10 Project Name Belgatos Park Restroom Improvements Project Number 831-3303 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description The project will restore minor structural elements, repaint the exterior, and relocate and replace the existing drinking fountain with a hydration station. Location The project is located at Belgatos Park, which is at 330 Belgatos Road. Project Background Belgatos Park is a popular destination for local residents and hikers due to its proximity to Heintz Open Space Reserve. In FY 2013/14, the Town completed restroom partition upgrades and accessibility modifications at Blossom Hill Park, Belgatos Park, Oak Meadow Park, and Balzar Field. During these improvements, some deficiencies have come to life. The restroom improvements project at Belgatos Park will repair some dry rot structural members on the building, replace a drinking fountain, and repaint the exterior surfaces of the building. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. BLOSSOM HILL RD BELGATOS RD PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-11 Project Components & Estimated Timeline Fall 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Winter 2018 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ TOTAL SOURCE OF FUNDS -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 25,000 - 25,000 - - - - 25,000$ TOTAL GFAR - - 25,000 - 25,000 - - - - 25,000$ TOTAL USE OF FUNDS -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ BELGATOS PARK RESTROOM IMPROVEMENTS Project 831-3303 PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-12 TOWN-WIDE Project Name Creek Trail & Park Pathway & Parking Lot Seal Coat & Striping Project Number 831-4609 Department Parks & Public Works Project Manager Superintendent: Steve Regan Description The project will resurface and restripe park parking lots, pathways, and sections of the Los Gatos Creek Trail. Location The project is located at Belgatos Park, Blossom Hill Park, Live Oak Manor Park, Oak Meadow Park, and the Los Gatos Creek Trail. Project Background The parking lots located in parks and the Los Gatos Creek Trail are heavily used on a daily basis. In order to keep their surfaces in good condition and prevent long term wear and damage, the parking lots and trails need to be resurfaced and striped. This project is necessary to prevent future damages to existing pavement surfaces in the future. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-13 Project Components & Estimated Timeline Fall 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Winter 2018 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 225,000$ 225,000$ -$ -$ -$ -$ 225,000$ TOTAL SOURCE OF FUNDS -$ -$ -$ 225,000$ 225,000$ -$ -$ -$ -$ 225,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 225,000 225,000 - - - - 225,000 TOTAL GFAR -$ -$ -$ 225,000$ 225,000$ -$ -$ -$ -$ 225,000$ TOTAL USE OF FUNDS -$ -$ -$ 225,000$ 225,000$ -$ -$ -$ -$ 225,000$ CREEK TRAIL, PARKS PATHS & PARKING LOTS SEAL AND STRIPING Project 831-4609 PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-14 E MAIN STHWY 17N SANTA CRUZUNIVERSITY AVAV Project Name Town Plaza Turf Repairs Project Number 831-4202 Department Parks & Public Works Project Manager Superintendent: Steve Regan Description This project will renovate the turf at Plaza Park. Location The project is located at Town Plaza Park, at the corner of West Main Street and Santa Cruz Avenue. Project Background Plaza Park, located in the heart of downtown Los Gatos, is a popular park and hosts a variety of community events, such as Jazz on the Plazz and the Farmer’s Market. Because of the amount of high foot traffic at this location, the turf is heavily impacted. This project will remove the existing sod and soil. New soil will be added to the area to enhance root growth and to re-grade the ground to mitigate standing water issues. Additionally, along with the installation of new turf grass, minor changes to the irrigation system will be completed to maximize water coverage. The turf was last replaced around 2010. The project will be completed during a period when there is the least impact on scheduled downtown events. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-15 Project Components & Estimated Timeline Summer 2018 Design Project design & development Summer 2018 Bid Process Project bidding & contract award Summer 2018 Construction Project construction Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 28,000$ 28,000$ -$ -$ -$ -$ 28,000$ TOTAL SOURCE OF FUNDS -$ -$ -$ 28,000$ 28,000$ -$ -$ -$ -$ 28,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 28,000 28,000 - - - - 28,000 TOTAL GFAR -$ -$ -$ 28,000$ 28,000$ -$ -$ -$ -$ 28,000$ TOTAL USE OF FUNDS -$ -$ -$ 28,000$ 28,000$ -$ -$ -$ -$ 28,000$ TOWN PLAZA TURF REPAIRS Project 831-4202 PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-16 Project Name Outdoor Fitness Equipment Project Number 831-4006 Department Parks & Public Works Project Manager Superintendent: Steve Regan Description This project will install outdoor fitness equipment. Location The project location is still being determined. Project Background The Town was awarded an outdoor fitness rig after attending a California Parks & Recreation Society conference and competing in a competition. The Town will receive equipment that is valued at $30,000 and Town staff will install the equipment at a location to be determined. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. TOWN-WIDE PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-17 Project Components & Estimated Timeline Summer 2018 Design Project design & development Summer 2018 Bid Process Project bidding & contract award Summer 2018 Construction Project construction Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 60,000$ 60,000$ -$ -$ -$ -$ 60,000$ TOTAL SOURCE OF FUNDS -$ -$ -$ 60,000$ 60,000$ -$ -$ -$ -$ 60,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 60,000 60,000 - - - - 60,000 TOTAL GFAR -$ -$ -$ 60,000$ 60,000$ -$ -$ -$ -$ 60,000$ TOTAL USE OF FUNDS -$ -$ -$ 60,000$ 60,000$ -$ -$ -$ -$ 60,000$ OUTDOOR FITTNESS EQUIPMENT Project 831-4006 PROPOSED PARKS & TRAILS PROGRAM Park Improvement Projects D-18 PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-19 PROJECT LOCATIONS A Open Space Trail Upgrades B Forbes Mill Footbridge Improvements C Charter Oaks Trail Repair D Trailhead Connector Project LO S G A T O S - S A R A T O G A R D LOS GATOS BLVDE MAIN STHWY 17HWY 17N SANTA CRUZ AVWINCHESTER BLVDBLOSSOM HILL RDLOS GATOS BLVDHW Y 8 5 KENNE D Y R D SHA N N O N R D LA R K A V LOS GATOS-ALMADEN RD UNIVERSITY AVWEDGEWOOD KNOWLES "A" IS A TOWN-WIDE PROJECT B C D PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-20 PROGRAM SECTION DIRECTORY PAGE 4504 Open Space Trail Upgrades D – 22 4507 Forbes Mill Footbridge Improvements D – 24 4503 Charter Oaks Trail Repair D – 26 4505 Trailhead Connector Project D – 28 PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-21 The Parks Program’s Trail Improvement Projects section contains Capital Improvement Program projects that construct, repair, or improve a Town trail as the primary scope of work. Typical trail improvement projects include pathway construction or resurfacing. TRAIL IMPROVEMENT PROJECTS SUMMARY * Total FY 2017/18 Carryforward $226,510 ` Carryforward Projects 4504 Open Space Trail Upgrades -$ 152,000$ -$ -$ -$ -$ 152,000$ 4202 Forbes Mill Footbridge Improvements 16,338 74,510 - - - - 90,848 New Projects 4503 Charter Oaks Trail Repair Project - 163,051 350,000 - - - 513,051 4505 Trailhead Connector - 387,440 - - - - 387,440 Total Trail Improvement Projects 16,338$ 777,001$ 350,000$ -$ -$ -$ 1,143,339$ 2022/23 Budget 2019/20 Budget 2018/19 Budget & Carryfwd* Total Budgeted FY 2018/19- 2022/23 CAPITAL IMPROVEMENT PROGRAM 2020/21 Budget Expended Through 2017/18 2021/22 Budget TRAIL IMPROVEMENT PROJECTS PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-22 Project Name Open Space Trail Upgrades Project Number 832-4504 Department Parks & Public Works Project Manager Superintendent: Steve Regan Description This project will repair and replace old damaged retaining walls, fences, and embankments along the trails in the Town’s open spaces. Location This project is located at Santa Rosa Open Space, Heintz Open Space, and Belgatos Park. Project Background The Town has a number of open space preserves that are under its jurisdiction. There are several public trail networks that traverse the open space preserves in the hillsides. The aging process has deteriorated a number of retaining walls and embankments along some trail sections. Without proper repair and replacement, the possibility of failure of the trails will increase greatly. This project will repair and replace several retaining walls that are supporting the trails and their embankments. In addition, this project will improve the drainage system around the retaining walls to prevent further erosion of the trails. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. . TOWN-WIDE PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-23 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Winter 2018 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR Open Space Reserve Fund -$ -$ 152,000$ -$ 152,000$ -$ -$ -$ -$ 152,000$ TOTAL SOURCE OF FUNDS -$ -$ 152,000$ -$ 152,000$ -$ -$ -$ -$ 152,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 152,000 - 152,000 - - - - 152,000 TOTAL GFAR -$ -$ 152,000$ -$ 152,000$ -$ -$ -$ -$ 152,000$ TOTAL USE OF FUNDS -$ -$ 152,000$ -$ 152,000$ -$ -$ -$ -$ 152,000$ OPEN SPACE TRAIL UPGRADES Project 832-4504 PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-24 Project Name Forbes Mill Footbridge Improvements Project Number 832-4507 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description The project will provide pathway lighting across the 400-foot span of the pedestrian bridge and install additional art panels. Location The project is located on the pedestrian bridge between Forbes Mill and Old Town across Highway 17. Project Background Forbes Mill footbridge is a heavily used pathway crossing Highway 17 between the Main Street businesses, Civic Center, and high school on the east side of the freeway, and the downtown on the west. The interior walls of the walkway are decorated with murals painted by students over the past decades. The pathway structure once had a lighting system, but fell into disrepair several years ago and was removed. This leaves the pathway dark in the evening, which has prompted concerns from residents. The footbridge improvements will include LED lighting for the pathway. This project will also install additional art panels to occupy the remaining space. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. HWY 9 E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-25 Project Components & Estimated Timeline Fall 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Winter 2018 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 7,815$ 8,522$ 74,510$ -$ 74,510$ -$ -$ -$ -$ 90,848$ TOTAL SOURCE OF FUNDS 7,815$ 8,522$ 74,510$ -$ 74,510$ -$ -$ -$ -$ 90,848$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 7,815 8,522 74,510 - 74,510 - - - - 90,848 TOTAL GFAR 7,815$ 8,522$ 74,510$ -$ 74,510$ -$ -$ -$ -$ 90,848$ TOTAL USE OF FUNDS 7,815$ 8,522$ 74,510$ -$ 74,510$ -$ -$ -$ -$ 90,848$ FORBES MILL FOOTBRIDGE IMPROVEMENTS Project 832-4507 PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-26 HWY 17WINCHESTER BLVDLOS GATOS BLVDHW Y 8 5 LA R K A V KNOWLE S Project Name Charter Oaks Trail Repair Project Project Number 832-4503 Department Parks & Public Works Project Manager Superintendent: Steve Regan Description This project will repair the storm damage on the Los Gatos Creek Trail near Charter Oaks, which includes damage to the fencing and asphalt pathway. Location This project is located on the Los Gatos Creek Trail near Charter Oaks. Project Background The existing trail is adjacent to Los Gatos Creek and was damaged by flooding during the winter storms of 2017. The impacts of the storm included damage to the fencing and to the asphalt concrete pathway. The trail is well used by the public and the damage has negatively impacted trail users by making the trail more difficult to use. Funds for this project will be provided by FEMA. The FEMA funding must be spent by the fall of 2018. Subsequent to the trail repair work, this project will further evaluate improvements along the trail from Lark Avenue towards Highway 85 utilizing Community Benefit funds in the amount of $350,000 from the Albright project. This project scope will be determined through community outreach efforts for construction in FY 2019/20. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-27 Project Components & Estimated Timeline Summer 2018 Design Project design & development Summer 2018 Bid Process Project bidding & contract award Fall 2018 Construction Project construction Fall 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 15,000$ 15,000$ 350,000$ -$ -$ -$ 365,000$ GRANTS - - - 148,051 148,051 - - - - 148,051 TOTAL SOURCE OF FUNDS -$ -$ -$ 163,051$ 163,051$ 350,000$ -$ -$ -$ 513,051$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 15,000 15,000 350,000 - - - 365,000 TOTAL GFAR -$ -$ -$ 15,000$ 15,000$ 350,000$ -$ -$ -$ 365,000$ GRANTS &AWARDS Salaries and Benefits - - - - - - - - - - Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 148,051 148,051 - - - - 148,051 TOTAL GRANTS &AWARDS -$ -$ -$ 148,051$ 148,051$ -$ -$ -$ -$ 148,051$ TOTAL USE OF FUNDS -$ -$ -$ 163,051$ 163,051$ 350,000$ -$ -$ -$ 513,051$ CHARTER OAKS TRAIL REPAIR PROJECT Project 832-4503 PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-28 H W Y 9 HWY 17N SANTA CRUZ AVUNIVERSITY AV Project Name Trailhead Connector Project Project Number 832-4505 Department Parks & Public Works Project Manager Asst. Director Lisa Petersen Description This project will fund the design of a trailhead connection for Los Gatos Creek Trail to Highway 9. Location This project is located on the Los Gatos Creek Trail near Highway 9. Project Background This project will fund the design of a trailhead connection for Los Gatos Creek Trail to Highway 9. The project will become a “shovel ready” project which will allow the Town to be in a better position to obtain grant funding to fund project construction. The project is an identified priority within Measure B and the Bicycle and Pedestrian Plan. The Council approved the staff recommendation for the next steps on this project in June 2017. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-29 Project Components & Estimated Timeline Summer 2018 Design Project design & development Pending Bid Process Project bidding & contract award Pending Construction Project construction Pending Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 44,440$ 44,440$ -$ -$ -$ -$ 44,440$ GRANTS & AWARDS - - - 343,000 343,000 - - - - 343,000 TOTAL SOURCE OF FUNDS -$ -$ -$ 387,440$ 387,440$ -$ -$ -$ -$ 387,440$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 44,440 44,440 - - - - 44,440 TOTAL GFAR - - - 44,440 44,440 - - - - 44,440 GRANTS &AWARDS Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 343,000 343,000 - - - - 343,000 TOTAL GRANTS &AWARDS -$ -$ -$ 343,000$ 343,000$ -$ -$ -$ -$ 343,000$ TOTAL USE OF FUNDS -$ -$ -$ 387,440$ 387,440$ -$ -$ -$ -$ 387,440$ TRAILHEAD CONNECTOR Project 831-4505 PROPOSED PARKS & TRAILS PROGRAM Trail Improvement Projects D-30 Public Facilities Program PUBLIC FACILITIES DIRECTORY PROPOSED E -1 TOWN INFRASTRUCTURE PROJECT DIRECTORY 2302 Building Replacement at Corporation Yard E – 6 2110 Civic Center Building Energy Efficiency Measures E – 8 2304 Fuel System Enhancements E – 10 2008 Energy Efficiency Upgrades – Town-wide E – 12 2112 Exterior Lighting Replacement – Civic Center E – 14 2113 Civic Center – Fountain Modification E – 16 2115 HVAC – Chiller Repair E – 18 2001 Facilities Assessment E – 20 2307 Mechanic Bay Heater E – 22 2502 Library Teen Door Installation E – 24 2503 Library Carpet Replacement E – 26 2002 Town Beautification E – 28 2205 Youth Recreation Center HVAC Replacement E – 30 EQUIPMENT PROJECT DIRECTORY 6101 Information System Upgrade E – 36 6001 Audio/Video System Upgrade E – 38 6003 Town-Wide Document Imaging Project E – 40 2305 Engineering Document Archiving E – 42 2402 Police & PPW Interoperability Radio Project E – 44 6305 Silicon Valley Regional Interoperability Project (SVRIP) Service E – 46 6306 Neighborhood Emergency Preparedness E – 48 6103 EOC Communication Upgrade E – 50 6104 IT Disaster Recovery Improvements E – 52 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 2 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 3 LO S G A T O S - S A R A T O G A R D LOS GATOS BLVDE MAIN STHWY 17HWY 17N SANTA CRUZ AVWINCHESTER BLVDBLOSSOM HILL RDLOS GATOS BLVDHW Y 8 5 KENNE D Y R D SHA N N O N R D LA R K A V LOS GATOS-ALMADEN RD UNIVERSITY AVWEDGEWOOD KNOWLE S D, H AND L ARE TOWN-WIDE PROJECTS B, E, F, G, J, K A, C, I M PROJECT LOCATIONS A Building Replacement at Corporation Yard H Facilities Assessment B Civic Center Building Energy Efficiency Measures I Mechanic Bay Heater C Fuel System Enhancements J Library Teen Door Installation D Energy Efficiency Upgrades – Town-wide K Library Carpet Replacement E Exterior Lighting Replacement – Civic Center L Town Beautification F Civic Center – Fountain Modification M Youth Recreation Center HVAC Replacement G HVAC – Chiller Repair PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 4 PROGRAM SECTION DIRECTORY PAGE 2302 Building Replacement at Corporation Yard E – 6 2110 Civic Center Building Energy Efficiency Measures E – 8 2304 Fuel System Enhancements E – 10 2008 Energy Efficiency Upgrades – Town-wide E – 12 2112 Exterior Lighting Replacement – Civic Center E – 14 2113 Civic Center – Fountain Modification E – 16 2115 HVAC – Chiller Repair E – 18 2001 Facilities Assessment E – 20 2307 Mechanic Bay Heater E – 22 2502 Library Teen Door Installation E – 24 2503 Library Carpet Replacement E – 26 2002 Town Beautification E – 28 2205 Youth Recreation Center HVAC Replacement E – 30 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 5 The Town Infrastructure & Facilities Projects section contains Capital Improvement Program projects that maintain or improve the Town’s public buildings and structures to keep them in a clean, safe, and functional condition. Town-owned buildings include the Civic Center, Library, Police Operations Center, Parks & Public Works Building, Corporation Yard and associated structures, and the following buildings leased to other agencies: the Los Gatos-Saratoga Community Education and Recreation headquarters building and the Adult Recreation Center (formerly the Neighborhood Center). Other Town facilities include the Venue, Tait Avenue, and Forbes Mill. Town Infrastructure and Facilities Projects are prioritized in consideration of the user needs, federal and state mandates, federal and state grant restrictions, and local community standards. The Community Development Department assumes responsibility for evaluating the overall conformance to the General Plan and the status of environmental assessment. The Parks & Public Works Department assumes responsibility for project design, planning, and construction. This section contains annual ongoing improvement projects as well as identified one-time projects. One-time infrastructure and facilities projects are prioritized based on health and safety issues, infrastructure impacts, available funding sources, project costs, and community needs. Los Gatos does not have a designated funding source for repairing, maintaining, and improving the Town’s public facilities; however, grants, CDBG funds, and donations are pursued and utilized when available. TOWN INFRASTRUCTURE & FACILITIES PROJECTS SUMMARY *Total FY 2017/18 Carryforward $536,374 Unfunded Projects • Civic Center Improvements • Deferred maintenance at Town-owned, leased properties • Lighting system improvements throughout Town • Deferred improvements to Town-owned properties Carryforward Projects 2302 Building Replacement at Corporation Yard 16,717$ 149,083$ 25,000$ 25,000$ 25,000$ 50,000$ 290,800$ 2110 Civic Center Building Energy Efficiency Measures - 25,000 - - - - 25,000 2304 Fuel System Enhancements 37,580 37,420 - - - - 75,000 2008 Energy Efficiency Upgrade - Town-wide - 75,000 - - - - 75,000 2112 Exterior Lighting Replacement - Civic Center 7,784 17,216 - - - - 25,000 2113 Civic Center Fountain Modification - 33,135 - - - - 33,135 2115 HVAC - Chiller Repair 31,480 93,520 - - - - 125,000 2307 Mechanic Bay Heater - 25,000 - - - - 25,000 2001 Facilities Assessment - 80,000 - - - - 80,000 2002 Town Beautification 87,593 15,000 15,000 15,000 15,000 15,000 162,593 2502 Library Teen Door Installation - 51,000 - - - - 51,000 New Projects 2205 Youth Recreation Center HVAC Replacement - 22,600 - - - - 22,600 2503 Library Carpet Replacement - 56,500 - - - - 56,500 Total Infrastructure / Facility Projects 181,154$ 680,474$ 40,000$ 40,000$ 40,000$ 65,000$ 1,046,628$ Total Budgeted 2021/22 Budget FY 2018/19- 2022/23 CAPITAL IMPROVEMENT PROGRAM 2022/23 Budget 2020/21 Budget TOWN INFRASTRUCTURE & FACILITIES PROJECTS 2019/20 Budget Expended Through 2017/18 2018/19 Budget & Carryfwd* PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 6 Project Name Building Replacement at Corporation Yard* Project Number 821-2302 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin *This project was presented to Council as part of the Capital Improvement Program in FY 2015/16. A portion of these funds ($200,000) for this project was transferred to provide funding for the Almond Grove Street Reconstruction project. Description This project will replace an old building at the Parks and Public Works Department (PPW) Corporation Yard that is used for office space and evidence storage. Location This project is located at the PPW Corporation Yard, which is located at 41 Miles Avenue. Project Background The maintenance lead staff has been using a small portable building located at the north side of the PPW Corporation Yard for their office facility. This building has deteriorated over the years and is becoming more difficult to maintain because of its aging infrastructure. The existing building has several problems including a leaky roof and windows, a poor heating and cooling (HVAC) system, and lacks a restroom facility in the building. This building is also used partially by the Police Department as their evidence storage facility. Evidence must be stored and kept at a certain room temperature, which requires an updated HVAC system. This project will replace the existing building and configure an effective layout in the new building for both office and storage space uses. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 7 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Summer 2019 Construction Project construction Fall 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 15,800$ 917$ 124,083$ 25,000$ 149,083$ 25,000$ 25,000$ 25,000$ 50,000$ 290,800$ TOTAL SOURCE OF FUNDS 15,800$ 917$ 124,083$ 25,000$ 149,083$ 25,000$ 25,000$ 25,000$ 50,000$ 290,800$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 15,800 917 124,083 25,000 149,083 25,000 25,000 25,000 50,000 290,800 TOTAL GFAR 15,800$ 917$ 124,083$ 25,000$ 149,083$ 25,000$ 25,000$ 25,000$ 50,000$ 290,800$ TOTAL USE OF FUNDS 15,800$ 917$ 124,083$ 25,000$ 149,083$ 25,000$ 25,000$ 25,000$ 50,000$ 290,800$ BUILDING REPLACEMENT AT CORPORATION YARD Project 821-2302 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 8 Project Name Civic Center Building Energy Efficiency Measures Project Number 821-2110 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description This project will identify energy reduction measures to reduce overall utility costs. Location This project is located at the Civic Center, which is at 110 E. Main Street. Project Background The Civic Center was designed and built about 50 years ago and lacks the energy efficient design needed to keep energy costs down. With single pane windows, insulation deficiencies, and mechanical system limitations, the need for system modifications to reduce energy waste is crucial to save operating costs. For example, since the current mechanical system cannot manage multiple zones and only operates either on or off, the system must run 24/7 to accommodate police operations in the Civic Center building, which is causing high energy costs. This project consists of an energy efficiency study to evaluate the overall mechanical system at the Civic Center, identify a plan to allow operation of the system in separate zones, and control those zones separately as operating schedules dictate. This is expected to reduce energy usage by 20% given the mechanical equipment operation is the largest portion of the electricity and gas usage. The project plan, recommended as a result of this study, will be evaluated in relation to the ongoing savings they create and the ability to recover costs within a short payback period. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 9 Project Components & Estimated Timeline Summer 2018 Design Project Development Summer 2018 Bid process Project bidding & contract award Winter 2018 Construction Project construction Fall 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ TOTAL SOURCE OF FUNDS -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 25,000 - 25,000 - - - - 25,000 TOTAL GFAR -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ TOTAL USE OF FUNDS -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ CIVIC CENTER BUILDING ENERGY EFFICIENCY MEASURES 821-2110 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 10 Project Name Fuel System Enhancements Project Number 821-2304 Department Parks & Public Works Project Manager Superintendent: Steve Regan Description This project will enhance and replace the existing fuel system to a new modern system. Location This project is located at the Corporation Yard, 41 Miles Avenue. Project Background The fuel system technology was outdated and not efficient Staff used chip key technology to track user’s identification and mileage for each vehicle used manually. This led to some issues with tracking and logging vehicle use data accurately. If the data were not manually inputted properly, the data usage information was incorrect. The data are used to track vehicle usage as well as fuel data use. The new technology system automatically tracks this data via a transmittal device that is inside each vehicle. The data are tracked and transmitted wirelessly. The data are sent to a database system that staff can manage and administer electronically. This new fuel replacement system minimizes the number of data errors, and allows staff to better manage vehicle and fleet operations more efficiently. This project has been completed and will be closed out in FY 2018/19. Operating Budget Impacts This project will use staff time for construction inspection and management. Engineering staff time associated with these projects will be charged to the project as it is delivered. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 11 Project Components & Estimated Timeline Fall 2017 Design Project development Winter 2017 Bid process Project bidding & contract award Spring 2018 Construction Project construction Summer 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ 37,580$ 37,420$ -$ 37,420$ -$ -$ -$ -$ 75,000$ TOTAL SOURCE OF FUNDS -$ 37,580$ 37,420$ -$ 37,420$ -$ -$ -$ -$ 75,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - Project Construction Expenses - 37,580 37,420 - 37,420 - - - - 75,000 TOTAL GFAR -$ 37,580$ 37,420$ -$ 37,420$ -$ -$ -$ -$ 75,000$ TOTAL USE OF FUNDS -$ 37,580$ 37,420$ -$ 37,420$ -$ -$ -$ -$ 75,000$ FUEL SYSTEM ENHANCEMENTS 821-2304 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 12 Project Name Energy Efficiency Upgrades Town-wide Project Number 821-2008 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description This project will perform various energy efficiency upgrades throughout Town-owned facilities. Location This project location is Town-wide. Project Background This project will complete various improvements in Town-owned facilities, which will improve energy efficiency, resulting in cost savings over the long term. Once these improvements are completed, it can lead to an average seven-year payback on utility and operating expenses. Many of the existing fixtures and equipment throughout Town-owned facilities are outdated. Although these items are functional, they are not the most energy efficient option at the current time. These funds are a placeholder for future work. After an energy efficiency audit has occurred, these funds will be used to make improvements at Town owned buildings. Some locations may include the Adult Recreation Center, the Police Operations Building, and Civic Center. A sample of various improvements will include low flow water fixtures, light motion sensors, and energy efficient equipment. Operating Budget Impacts There will be no Operating Budget impact as a result of this project. Project delivery costs for this project are included in the CIP project’s total cost. Project delivery costs are estimated at $3,000 or 2% of the total project cost. TOWN-WIDE PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 13 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Winter 2018 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 50,000$ 25,000$ 75,000$ -$ -$ -$ -$ 75,000$ TOTAL SOURCE OF FUNDS -$ -$ 50,000$ 25,000$ 75,000$ -$ -$ -$ -$ 75,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 50,000 25,000 75,000 - - - - 75,000 TOTAL GFAR -$ -$ 50,000$ 25,000$ 75,000$ -$ -$ -$ -$ 75,000$ TOTAL USE OF FUNDS -$ -$ 50,000$ 25,000$ 75,000$ -$ -$ -$ -$ 75,000$ ENERGY EFFICIENCY - TOWN WIDE Project 821-2008 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 14 HWY 9 E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV Project Name Exterior Lighting Replacement – Civic Center Project Number 821-2112 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description This project will replace the original exterior lights at the Civic Center. Location This project location is outside the Civic Center. Project Background This project will replace the five remaining original incandescent pole lights behind the Civic Center with new LED lights to match the front lights that were recently replaced. The existing lights are dim, so the replacement of these lights will enhance the safety of the back lot by increasing the amount of visibility. Operating Budget Impacts There will be no Operating Budget impact as a result of this project. Project delivery costs for this project are included in the CIP project’s total cost. Project delivery costs are estimated at $2,500 or 10% of the total project cost. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 15 Project Components & Estimated Timeline Fall 2017 Bid Process Project bidding & contract award Winter 2017 Construction Project construction Spring 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ 7,784$ 17,216$ -$ 17,216$ -$ -$ -$ -$ 25,000$ TOTAL SOURCE OF FUNDS -$ 7,784$ 17,216$ -$ 17,216$ -$ -$ -$ -$ 25,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - 7,784 17,216 - 17,216 - - - - 25,000 TOTAL GFAR -$ 7,784$ 17,216$ -$ 17,216$ -$ -$ -$ -$ 25,000$ TOTAL USE OF FUNDS -$ 7,784$ 17,216$ -$ 17,216$ -$ -$ -$ -$ 25,000$ CIVIC CENTER - EXTERIOR LIGTHING REPLACEMENT Project 821-2112 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 16 Project Name Civic Center – Fountain Modification Project Number 821-2113 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin *This project was presented to Council as part of the Capital Improvement Program in FY 2016/17. A portion of the funds ($1,865) for this project was transferred to the Green Bike Lane project. Description This project will make alterations to the fountain to make it functional. Location This project location is on the deck of Town Hall. Project Background This improvement will visually enhance the existing fountain while creating safeguards to prevent people and pets from entering the water. Operating Budget Impacts There will be additional operating costs associated with the ongoing maintenance of the fountain of approximately $3,000 per year. Project delivery costs for this project are included in the CIP project’s total cost. Project delivery costs are estimated at $3,500 or 10% of the total project cost. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 17 Project Components & Estimated Timeline Winter 2018 Design Project design & development Spring 2019 Bid Process Project bidding & contract award Summer 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 33,135$ -$ 33,135$ -$ -$ -$ -$ 33,135$ TOTAL SOURCE OF FUNDS -$ -$ 33,135$ -$ 33,135$ -$ -$ -$ -$ 33,135$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 33,135 - 33,135 - - - - 33,135 TOTAL GFAR -$ -$ 33,135$ -$ 33,135$ -$ -$ -$ -$ 33,135$ TOTAL USE OF FUNDS -$ -$ 33,135$ -$ 33,135$ -$ -$ -$ -$ 33,135$ CIVIC CENTER - FOUNTAIN MODIFICATION Project 821-2113 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 18 Project Name HVAC – Chiller Repair Project Number 821-2115 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description This project will rebuild the chiller at the Civic Center. Location This project is located at the Civic Center, which is at 110 East Main Street. Project Background The Civic Center chiller is at its half-life and recent tests on the chiller show several refrigerant leaks, which will require a rebuild of the chiller to remedy. Staff recommends rebuilding the chiller and will reassess for replacement in 10 years. Operating Budget Impacts The project will use staff time for construction management and inspection. The staff time for this project will be included in the department’s FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 19 Project Components & Estimated Timeline Spring 2018 Design Project design & development Spring 2018 Bid Process Project bidding & contract award Spring 2018 Construction Project construction Spring 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 6,248$ 25,232$ 93,520$ -$ 93,520$ -$ -$ -$ -$ 125,000$ TOTAL SOURCE OF FUNDS 6,248$ 25,232$ 93,520$ -$ 93,520$ -$ -$ -$ -$ 125,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 6,248 25,232 93,520 - 93,520 - - - - 125,000 TOTAL GFAR 6,248$ 25,232$ 93,520$ -$ 93,520$ -$ -$ -$ -$ 125,000$ TOTAL USE OF FUNDS 6,248$ 25,232$ 93,520$ -$ 93,520$ -$ -$ -$ -$ 125,000$ HVAC - CHILLER REPAIR Project 821-2115 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 20 TOWN-WIDE Project Name Facilities Assessment Project Number 821-2001 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description This project will fund a consultant to assess the condition of Town facilities. Location This project location is Town-wide. Project Background This project will assess the condition of Town facilities to determine current condition of equipment and building systems to assess priorities for repair versus replacements and to predict capital expenditures needed year by year for life-cycle scheduled work and replacement. Operating Budget Impacts The project will use staff time for construction management and inspection. The staff time for this project will be included in the department’s FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 21 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 80,000$ -$ 80,000$ -$ -$ -$ -$ 80,000$ TOTAL SOURCE OF FUNDS -$ -$ 80,000$ -$ 80,000$ -$ -$ -$ -$ 80,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 80,000 - 80,000 - - - - 80,000 TOTAL GFAR -$ -$ 80,000$ -$ 80,000$ -$ -$ -$ -$ 80,000$ TOTAL USE OF FUNDS -$ -$ 80,000$ -$ 80,000$ -$ -$ -$ -$ 80,000$ FACILITIES ASSESSMENT Project 821-2001 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 22 Project Name Mechanic Bay Heater Project Number 821-2307 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description This project will replace the heaters in the mechanic bay at the Parks and Public Works Corporation Yard. Location This project location is at the Parks and Public Works Corporation Yard. Project Background This project will replace the two Reznor gas-fired heaters in the mechanic’s bay as they have reached the end of their useful lives. Operating Budget Impacts The project will use staff time for construction management and inspection. The staff time for this project will be included in the department’s FY 2017/18 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 23 Project Components & Estimated Timeline Summer 2018 Design Project design & development Summer 2018 Construction Project construction Fall 2018 Completion Project Completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ TOTAL SOURCE OF FUNDS -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - Consultant Services - - - - - - - - - Project Construction Expenses - - 25,000 - 25,000 - - - - 25,000 TOTAL GFAR -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ TOTAL USE OF FUNDS -$ -$ 25,000$ -$ 25,000$ -$ -$ -$ -$ 25,000$ MECHANIC BAY HEATER Project 821-2307 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 24 HWY 9 E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV Project Name Library Teen Door Installation Project Number 821-2502 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description This project will install sound mitigating glass doors at the entrance to the teen area of the Library. Location This project location is inside the library at 100 Villa Avenue. Project Background Noise mitigation inside the Library was identified as a project by Library Staff and by public request as early as 2013. Staff contracted the original architects, Noll and Tam, to research the problem and develop a comprehensive plan for sound-mitigation. In June of 2014 Noll and Tam submitted the report and architectural drawings. The report identified three phases of work to be completed. This project will install the first phase which will install glass sound barrier doors between the teen area and the main library. Operating Budget Impacts The project will use staff time for construction management and inspection. The staff time for this project will be included in the department’s FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 25 Project Components & Estimated Timeline Summer 2018 Design Project design & development Fall 2018 Bid Process Project bidding & contract award Spring 2019 Construction Project construction Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ 51,000$ -$ 51,000$ -$ -$ -$ -$ 51,000$ TOTAL SOURCE OF FUNDS -$ -$ 51,000$ -$ 51,000$ -$ -$ -$ -$ 51,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - 51,000 - 51,000 - - - - 51,000 TOTAL GFAR -$ -$ 51,000$ -$ 51,000$ -$ -$ -$ -$ 51,000$ TOTAL USE OF FUNDS -$ -$ 51,000$ -$ 51,000$ -$ -$ -$ -$ 51,000$ LIBRARY TEEN DOOR INSTALLATION Project 821-2502 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 26 Project Name Library Carpet Replacement Project Number 821-2503 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description This project will replace large sections of the carpet squares in the children’s area that have started to fail. Location This project location is inside the library at 100 Villa Avenue. Project Background The carpet in the children’s area of the library is starting to mat, lift, and stain from extensive foot traffic, spilled food, and other accidents. This area of the library is where the young kids play, listen to stories, and congregate for different activities on the carpet. Recent replacements of the furniture upholstery have been completed due to stains and failure, and this project will help complete the restoration of the space back to a high service level. Operating Budget Impacts The project will use staff time for construction management and inspection. The staff time for this project will be included in the department’s FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 27 Project Components & Estimated Timeline Winter 2018 Design Project design & development Spring 2019 Bid Process Project bidding & contract award Summer 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 56,500$ 56,500$ -$ -$ -$ -$ 56,500$ TOTAL SOURCE OF FUNDS -$ -$ -$ 56,500$ 56,500$ -$ -$ -$ -$ 56,500$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - 56,500 56,500 - - - - 56,500 Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - - - - - - - - TOTAL GFAR -$ -$ -$ 56,500$ 56,500$ -$ -$ -$ -$ 56,500$ TOTAL USE OF FUNDS -$ -$ -$ 56,500$ 56,500$ -$ -$ -$ -$ 56,500$ LIBRARY CARPET REPLACEMENT 821-2503 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 28 TOWN-WIDE Project Name Town Beautification Project Number 821-2002 Department Parks & Public Works Project Manager Environmental Specialist: Marina Chislett Description This project funds Town-wide beautification projects on an annual, as-needed basis. Location This project location is Town-wide. Project Background The Town Beautification Program was established to provide improvements to enhance the Town’s beauty, particularly along public streets, sidewalks, and other Town property. One example is the Town’s Outside the Box Program which enhances the character of the community by adding artwork to utility boxes that are often targeted by graffiti vandals. Selected artwork contains environmental sustainability messages that include: alternative transportation, clean energy, clean creeks, community sustainability, and healthy lifestyles. In FY 2017/18 four utility boxes were added to bring the total to 17, and another four are planned in FY 2018/19. Operating Budget Impacts The project will use staff time for program management and inspection. The staff time for this project will be included in the department’s FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 29 Project Components & Estimated Timeline Winter 2018 Design Project design & development Summer 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 87,593$ -$ -$ 15,000$ 15,000$ 15,000$ 15,000$ 15,000$ 15,000$ 162,593$ TOTAL SOURCE OF FUNDS 87,593$ -$ -$ 15,000$ 15,000$ 15,000$ 15,000$ 15,000$ 15,000$ 162,593$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 87,593 - - 15,000 15,000 15,000 15,000 15,000 15,000 162,593 TOTAL GFAR 87,593$ -$ -$ 15,000$ 15,000$ 15,000$ 15,000$ 15,000$ 15,000$ 162,593$ TOTAL USE OF FUNDS 87,593$ -$ -$ 15,000$ 15,000$ 15,000$ 15,000$ 15,000$ 15,000$ 162,593$ TOWN BEAUTIFICATION PROJECTS Project 821-2002 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 30 HWY 9 E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV Project Name Youth Recreation Center HVAC Replacement Project Number 821-2113 Department Parks & Public Works Project Manager Facilities Manager: Jim Harbin Description This project will replace the existing HVAC unit at the Youth Recreation Center. Location This project location is at the Youth Recreation Center at 123 E. Main Street. Project Background The HVAC package unit located on the roof of the Youth Recreation Center has reached the end of its useful life. This project will remove the existing unit with a crane, and then install a new HVAC unit in its place. All mechanical connections will be made completing a turn-key project. Operating Budget Impacts The project will use staff time for construction management and inspection. The staff time for this project will be included in the department’s FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 31 Project Components & Estimated Timeline Winter 2018 Design Project design & development Spring 2019 Bid Process Project bidding & contract award Summer 2019 Construction Project construction Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 22,600$ 22,600$ -$ -$ -$ -$ 22,600$ TOTAL SOURCE OF FUNDS -$ -$ -$ 22,600$ 22,600$ -$ -$ -$ -$ 22,600$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 22,600 22,600 - - - - 22,600 TOTAL GFAR -$ -$ -$ 22,600$ 22,600$ -$ -$ -$ -$ 22,600$ TOTAL USE OF FUNDS -$ -$ -$ 22,600$ 22,600$ -$ -$ -$ -$ 22,600$ YOUTH RECREATION CENTER HVAC UNIT REPLACEMENT 821-2205 PROPOSED PUBLIC FACILITIES PROGRAM Town Infrastructure & Facilities Projects E- 32 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 33 LO S G A T O S - S A R A T O G A R D LOS GATOS BLVDE MAIN STHWY 17HWY 17N SANTA CRUZ AVWINCHESTER BLVDBLOSSOM HILL RDLOS GATOS BLVDHW Y 8 5 KENNE D Y R D SHA N N O N R D LA R K A V LOS GATOS-ALMADEN RD UNIVERSITY AVWEDGEWOOD KNOWLES A, B, C, F D, E G, H AND I ARE TOWN-WIDE PROJECTS PROJECT LOCATIONS A Information System Upgrade B Audio/Video System Upgrade C Town-Wide Document Imaging Project D Engineering Document Archiving E Police & PPW Interoperability Radio Project F Silicon Valley Regional Interoperability Project (SVRIP) Service G Neighborhood Emergency Preparedness H EOC Communication Upgrade I IT Disaster Recovery Improvements PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 34 PROGRAM SECTION DIRECTORY PAGE 6101 Information System Upgrade E – 36 6001 Audio/Video System Upgrade E – 38 6003 Town-Wide Document Imaging Project E – 40 2305 Engineering Document Archiving E – 42 2402 Police & PPW Interoperability Radio Project E – 44 6305 Silicon Valley Regional Interoperability Project (SVRIP) Service E – 46 6306 Neighborhood Emergency Preparedness E – 48 6103 EOC Communication Upgrade E – 50 6104 IT Disaster Recovery Improvements E – 52 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 35 The Equipment Projects section contains Capital Improvement Program projects that provide new equipment; or replace, improve, or upgrade existing Town equipment. This section does not have ongoing equipment programs; all projects are considered one-time projects. One-time equipment capital improvement projects are prioritized based on service level considerations, available funding sources, project costs, and community impacts. Los Gatos does not have a designated funding source for new equipment or the replacement or upgrading of existing equipment; however, grants are pursued and utilized when available. EQUIPMENT PROJECTS SUMMARY Carryforward Projects 6101 Information System Upgrade 402,215$ 172,785$ -$ -$ -$ -$ 575,000$ 6001 Audio/Video System Upgrade 68,048 42,552 - - - - 110,600 6003 Town-wide Document Imaging Project 198,011 16,990 - - - - 215,000 2305 Engineering Document Archiving 8,284 51,716 - - - - 60,000 2402 Police & PPW Interoperability Radio Project 508,459 87,221 - - - - 595,680 6305 Silicon Valley Regional Interoperability Project (SVRIP) Service 395,027 63,601 - - - - 458,628 New Projects 6103 EOC Communications Upgrade - 50,000 - - - - 50,000 6104 IT Disaster Recovery Improvements - 200,000 - - - - 200,000 6306 Neighborhood Emergency Preparedness - 50,000 - - - - 50,000 Total Equipment Projects 1,580,043$ 734,865$ -$ -$ -$ -$ 2,314,909$ Total Budgeted 2019/20 Budget 2020/21 Budget 2021/22 Budget 2022/23 Budget EQUIPMENT PROJECT SUMMARY BY PROGRAM Expended Through 2017/18 2018/19 Budget & Carryfwd* FY 2018/19- 2022/23 CAPITAL IMPROVEMENT PROGRAM Total FY 2017/18 Carryforward $334,865 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 36 Project Name Information System Upgrade Project Number 841-6101 Department Finance Project Manager Finance Director: Stephen Conway Description This project upgrades the Town’s existing financial/human resources information database, enhancing its reporting system and providing future web-based online services. This project will be coordinated with the upgrade of the Town’s existing permit tracking system. Location The project will enhance the information systems used by the Finance, Human Resources, and Building Departments. Purchased computer hardware will be located in the IT Department, 110 E. Main Street. Project Background In FY 2008/09, staff completed a significant portion of a multi-year financial information system upgrade. This project involved the conversion of General Ledgers, Payroll, Budget, and Human Resources modules, followed by the implementation of the Cashiering and Business License modules. Planned for FY 2018/19 required system upgrade, online-timesheet management, completion of the fixed asset module, and continuation of electronic commerce, including online permitting and business license applications. Operating Budget Impacts The remaining project balance is estimated to be $72,785. It is anticipated that the maintenance costs for the Finance/Human Resources information system would be approximately $40,000 annually, which has been incorporated into the FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 37 Project Components & Estimated Timeline Fall 2018 System Implementation Upgrade and test data migration and functionality of financial/human resources information database Spring 2019 System Implementation Develop and test fixed assets, electronic commerce, and electronic timesheet functions. Summer 2019 Implement data migration Spring 2020 System Implementation Implementation of electronic commerce, and electronic timesheet functions. Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR Transfer from MIS 394,421$ 7,794$ 72,785$ 100,000$ 172,785$ -$ -$ -$ -$ 575,000$ TOTAL SOURCE OF FUNDS 394,421$ 7,794$ 72,785$ 100,000$ 172,785$ -$ -$ -$ -$ 575,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services 394,421 7,794 72,785 100,000 172,785 - - - - 575,000 Project Construction Expenses - - - - - - - - - - TOTAL GFAR 394,421$ 7,794$ 72,785$ 100,000$ 172,785$ -$ -$ -$ -$ 575,000$ TOTAL USE OF FUNDS 394,421$ 7,794$ 72,785$ 100,000$ 172,785$ -$ -$ -$ -$ 575,000$ INFORMATION SYSTEM UPGRADE Project 841-6101 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 38 Project Name Audio/Video System Upgrade Project Number 841-6001 Department Town Manager Project Manager IT Manager: Chris Gjerde Description This project provides for the replacement and/or upgrade of Council Chamber video, audio/visual, and other applicable equipment used for televised and non-televised public meetings. Location The video production system is located in the audio/video equipment room at the Civic Center, 110 E. Main Street, and involves various electronic equipment required to cablecast public meetings and make presentations. Project Background In FY 2008/09, the audio/visual equipment located in the Town Council Chambers was upgraded to meet the needs at that time. The maintenance of the video production equipment is now the responsibility of KCAT, who receives Public, Educational, and Governmental (PEG) fees, provided by local cable operators for this purpose. The remaining funds in this project will be used to replace and/or upgrade the Town’s A/V equipment in the Council Chambers, as needed. Staff will also explore the availability of additional audio/visual meeting management enhancements. Operating Budget Impacts This Audio/Video System Upgrade project is funded in the GFAR Fund. It is unknown at this time which replacements or upgrades will be required during FY 2018/19. Staff oversight of this project will be included in the FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 39 Project Components & Estimated Timeline Fiscal Year 18/19 Monitoring As needed. Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 52,440$ 15,608$ 42,552$ -$ 42,552$ -$ -$ -$ -$ 110,600$ TOTAL SOURCE OF FUNDS 52,440$ 15,608$ 42,552$ -$ 42,552$ -$ -$ -$ -$ 110,600$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment 52,440 15,608 42,552 - 42,552 - - - - 110,600 Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - - - - - - - - TOTAL GFAR 52,440$ 15,608$ 42,552$ -$ 42,552$ -$ -$ -$ -$ 110,600$ TOTAL USE OF FUNDS 52,440$ 15,608$ 42,552$ -$ 42,552$ -$ -$ -$ -$ 110,600$ AUDIO / VIDEO SYSTEM UPGRADE Project 841-6001 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 40 Project Name Town-Wide Document Imaging Project Project Number 841-6003 Department Community Development/Police Project Manager Community Development Director: Joel Paulson Description This is the continuation of the first phase of a Town-wide project to convert existing microfiche and paper files to electronic storage and provide desktop access. Location Town of Los Gatos Civic Center complex, 110 E. Main Street. Project Background The Community Development Department has an immediate need to provide electronic storage and retrieval of many archived documents. The electronic retrieval system will allow immediate access to all building and planning files for members of the Community Development Department via desktop access. Following implementation, priorities will be identified to expand document imaging to other departments, subject to available funding. Operating Budget Impacts The Community Development Department collects permit fees, a portion of which will be used to offset some costs for document storage. PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 41 Project Components & Estimated Timeline FY 2018/19 Production Continue document conversion of Building and Planning Division files. Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR Transfer from MIS 198,011$ -$ 16,990$ -$ -$ -$ -$ -$ -$ 215,000$ TOTAL SOURCE OF FUNDS 198,011$ -$ 16,990$ -$ -$ -$ -$ -$ -$ 215,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 198,011 - 16,990 - 16,990 - - - - 215,000 TOTAL GFAR 198,011$ -$ 16,990$ -$ 16,990$ -$ -$ -$ -$ 215,000$ TOTAL USE OF FUNDS 198,011$ -$ 16,990$ -$ 16,990$ -$ -$ -$ -$ 215,000$ TOWN-WIDE DOCUMENT IMAGING PROJECT Project 841-6003 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 42 HW Y 9 E MAIN STHWY 17N SANTA CRUZ AVUNIVERSITY AV Project Name Engineering Document Archiving Project Number 821-2305 Department Parks & Public Works Project Manager Assistant PPW Director: Lisa Petersen Description This project will scan and archive all engineering record documents such as as-builts, federal and state funded capital improvement projects, and recorded documents, all of which are currently stored in paper format. Location This project is located at the Engineering Services office, which is at 41 Miles Avenue. Project Background Currently, most files are kept in a hard copy format in the Engineering Services office. These hard copies have become damaged due to age and need to be preserved through archiving to maintain pertinent records. By digitally archiving these documents, searching through records becomes much more efficient. It is anticipated that this project will be implemented over four fiscal years, starting in FY 2014/15 and completion estimated in FY 2019/20. Operating Budget Impacts This project will use staff time for management. The staff time for this project is included in the Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 43 Project Components & Estimated Timeline Summer 2015 Design Project development Fall 2015 Bid process Project bidding & contract award Summer 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 8,284$ -$ 51,716$ -$ 51,716$ -$ -$ -$ -$ 60,000$ TOTAL SOURCE OF FUNDS 8,284$ -$ 51,716$ -$ 51,716$ -$ -$ -$ -$ 60,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 8,284 - 51,716 - 51,716 - - - - 60,000 TOTAL GFAR 8,284$ -$ 51,716$ -$ 51,716$ -$ -$ -$ -$ 60,000$ TOTAL USE OF FUNDS 8,284$ -$ 51,716$ -$ 51,716$ -$ -$ -$ -$ 60,000$ ENGINEERING DOCUMENT ARCHIVING Project 821-2305 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 44 Project Name Police & PPW Interoperability Radio Project Project Number 821-2402 Department Police Project Manager Captain D’Antonio & Superintendent Steve Regan Description This project will update the existing police radio system to be compatible with the regional interoperability requirements. The project will replace current mobile and portable radios with new digital P25 compliant equipment using a 700 Mhz. spectrum. Location This project is located at Police Administration Building. Project Background The Town is a member of a County-wide joint powers authority which is moving forward with an aggressive program for regional interoperability of public safety communications for police and fire services across all jurisdictions. The Town’s Police Department has taken steps to update their radio system to be compatible with this regional interoperability requirement. In advance of the upgrade of the existing police radio system, the Police Department moved forward with Communications Center upgrades that will be compatible with the new police radio system. New digital radio consoles were installed in November 2014 and were purchased through an agreement with the County of Santa Clara to obtain the best pricing. The Police Department is working with other County law enforcement agencies to obtain best possible pricing for the mobile and portable radios. The Parks and Public Works Department staff also uses a similar radio system in order to communicate with public safety officials and requires it as part of day-day operations. In order to be compatible with these radio system changes, Park and Public Works Department’s radio system is being updated and the Building Inspectors are being added to the system. Operating Budget Impacts Staff oversight of this project will be included in the FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 45 Project Components & Estimated Timeline Spring 2017 Bid process Project bidding & contract award Winter 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2017/18 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 268,423$ 126,604$ 63,601$ -$ 63,601$ -$ -$ -$ -$ 458,628$ TOTAL SOURCE OF FUNDS 268,423$ 126,604$ 63,601$ -$ 63,601$ -$ -$ -$ -$ 458,628$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2017/18 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 268,423 126,604 63,601 - 63,601 - - - - 458,628 TOTAL GFAR 268,423$ 126,604$ 63,601$ -$ 63,601$ -$ -$ -$ -$ 458,628$ TOTAL USE OF FUNDS 268,423$ 126,604$ 63,601$ -$ 63,601$ -$ -$ -$ -$ 458,628$ SILICON VALLEY REGIONAL INTEROPERABILITY PROJECT (SVRIP) SERVICE Project 841-6305 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 46 Project Name Silicon Valley Regional Interoperability Project (SVRIP) Service Project Number 841-6305 Department Police Project Manager Captain D’Antonio Description This project will update the existing police radio system infrastructure to be compatible with the regional interoperability requirements. Location Town of Los Gatos Civic Center Complex, 110 E Main Street and the Town of Los Gatos Police Operations Building, 15900 Los Gatos Boulevard. Project Background The Silicon Valley Radio Interoperability Authority (SVRIA) in conjunction with the City Managers Association and the County Chiefs Association is moving towards a program for regional interoperability of public safety communications for police, fire services, and public works across all jurisdictions. The Police Department, in conjunction with other public safety agencies within Santa Clara County, will be contributing to radio system infrastructure for a period of three years to allow for interoperability of public safety communications regionally. Operating Budget Impacts Staff oversight of this SVRIP project will be included in the FY 2018/19 Operating Budget. PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 47 Project Components & Estimated Timeline Summer 2015 Design Project development Winter 2016 Bid process Project bidding & contract award Winter 2018 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR 268,423$ 126,604$ 63,601$ -$ 63,601$ -$ -$ -$ -$ 458,628$ TOTAL SOURCE OF FUNDS 268,423$ 126,604$ 63,601$ -$ 63,601$ -$ -$ -$ -$ 458,628$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses 268,423 126,604 63,601 - 63,601 - - - - 458,628 TOTAL GFAR 268,423$ 126,604$ 63,601$ -$ 63,601$ -$ -$ -$ -$ 458,628$ TOTAL USE OF FUNDS 268,423$ 126,604$ 63,601$ -$ 63,601$ -$ -$ -$ -$ 458,628$ SILICON VALLEY REGIONAL INTEROPERABILITY PROJECT (SVRIP) SERVICE Project 841-6305 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 48 TOWN-WIDE Project Name Neighborhood Emergency Preparedness Project Number 841-6306 Department Town Manager Office/PD Project Manager Assistant Town Manager, Arn Andrews Description This project upgrades and adds Neighborhood Incident Command Posts (NICPs) for deployment in the Town’s Community Emergency Response Team (CERT) neighborhood sectors. Location The project will enhance and deploy additional NICPs throughout the Town’s thirteen geographic CERT neighborhoods. Project Background The Town has identified thirteen distinct CERT geographic neighborhoods. CERT is a critical element of the Towns ability to adequately address any large scale disaster. CERT members go through extensive training in order to facilitate and provide emergency response capabilities in their immediate neighborhoods. For CERT teams to function effectively they require prepositioned NICPs within their CERT geographic area. The NICPs store critical medical, safety, communication and other necessary equipment to adequately address the immediate needs of a neighborhood in an emergency. The Town currently has seven NICPs in various states of preparedness. Operating Budget Impacts This project will use staff time for management. The staff time for this project is included in the FY 2018/19 Operating Budget. . PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 49 Project Components & Estimated Timeline Summer 2018 Design Project development Fall 2018 Procurement Procurement of Equipment and Installation Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 50,000$ 50,000$ -$ -$ -$ -$ 50,000$ TOTAL SOURCE OF FUNDS -$ -$ -$ 50,000$ 50,000$ -$ -$ -$ -$ 50,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 50,000 50,000 - - - - 50,000 TOTAL GFAR - - - 50,000 50,000 - - - - 50,000 TOTAL USE OF FUNDS -$ -$ -$ 50,000$ 50,000$ -$ -$ -$ -$ 50,000$ NEIGHBORHOOD EMERGENCY PREPAREDNESS Project 841-6306 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 50 TOWN-WIDE Project Name EOC Communications Upgrade Project Number 841-6103 Department Town Manager Office/IT/PD Project Manager Assistant Town Manager, Arn Andrews Description This project upgrades identified deficiencies in the Town’s Emergency Operations Center (EOC) communication capabilities. Location The project will enhance the communication systems within the EOC to create better interoperability between Town staff, Public Safety and citizen volunteers in the event of an emergency. Project Background The recent wildfire disasters in California and lessons learned from prior Town emergency preparedness exercises continue to identify a lack of adequate communications as a major flaw in emergency responses. Without robust EOC communication capabilities the situational awareness necessary to adequately assess, and respond to, an operational area in the event of an emergency is severely compromised. Staff is seeking to create multiple seamless communication channels between the Town EOC, County EOC, Town Public Safety staff, Town PPW staff, Town CDD staff and CERT volunteers. Operating Budget Impacts This project will use staff time for management. The staff time for this project is included in the FY 2018/19 Operating Budget. . PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 51 Project Components & Estimated Timeline Summer 2018 Design Project development Fall 2018 Procurement Procurement of equipment and installation Spring 2019 Completion Project completion Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR -$ -$ -$ 50,000$ 50,000$ -$ -$ -$ -$ 50,000$ TOTAL SOURCE OF FUNDS -$ -$ -$ 50,000$ 50,000$ -$ -$ -$ -$ 50,000$ Prior Yrs Actuals 2017/18 Estimated Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - - Consultant Services - - - - - - - - - - Project Construction Expenses - - - 50,000 50,000 - - - - 50,000 TOTAL GFAR -$ -$ -$ 50,000$ 50,000$ -$ -$ -$ -$ 50,000$ TOTAL USE OF FUNDS -$ -$ -$ 50,000$ 50,000$ -$ -$ -$ -$ 50,000$ EOC COMMUNICATION UPGRADE Project 841-6103 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 52 TOWN-WIDE Project Name IT Disaster Recovery Improvements Project Number 841-6104 Department IT Project Manager IT Manager: Chris Gjerde Description This project upgrades the Town’s existing Information Technology infrastructure including windows servers, storage, and network switches. Location The project will enhance the IT systems used by all Town departments at all locations. Purchased computer hardware will be located at 110 E. Main Street and 15900 Los Gatos Boulevard Project Background Annually staff evaluates and replaces older servers and network infrastructure to ensure reliable operation. In FY 2017/18, staff began an IT disaster recovery inventory, identifying many areas to improve our disaster preparedness posture and increasing efficiencies with more modern infrastructure design. These improvements to IT infrastructure require more than a simple staggered replacement of a small percentage of servers. Improvements include Hypervisor Server Clusters and Replication, redundant Storage Area Networks, and Public Cloud DR Data Center Operating Budget Impacts This project will use staff time for management. The staff time for this project is included in the FY 2018/19 Operating Budget. . PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 53 Project Components & Estimated Timeline Summer 2018 Design Project development Fall 2018 Procurement Procurement of equipment and installation Spring 2019 Completion Project completion Prior Yrs Actuals Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project SOURCE OF FUNDS to 2018/19 (with Carryfwd) GFAR Transfer from MIS -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ TOTAL SOURCE OF FUNDS -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ Prior Yrs Actuals Estimated Carryfwd 2018/19 New Funding 2018/19 Budget 2019/20 Proposed 2020/21 Proposed 2021/22 Proposed 2022/23 Proposed Total Project USE OF FUNDS to 2018/19 (with Carryfwd) GFAR Salaries and Benefits -$ -$ -$ -$ -$ -$ -$ -$ -$ Services/Supplies/Equipment - - - - - - - - - Site Acquisition & Preparation - - - - - - - - - Consultant Services - - - - - - - - - Project Construction Expenses - - 200,000 200,000 - - - - 200,000 TOTAL GFAR -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ TOTAL USE OF FUNDS -$ -$ 200,000$ 200,000$ -$ -$ -$ -$ 200,000$ IT DISASTER RECOVERY IMPROVEMENTS Project 841-6104 PROPOSED PUBLIC FACILITIES PROGRAM Equipment Projects E- 54