Staff Report PREPARED BY: MATT MORLEY Director of Parks and Public Works Reviewed by: Town Manager, Town Attorney, and Finance Director 110 E. Main Street Los Gatos, CA 95030 ● 408-354-6832 www.losgatosca.gov TOWN OF LOS GATOS COUNCIL AGENDA REPORT MEETING DATE: 01/17/2017 ITEM NO: 11 DATE: NOVEMBER 22, 2016 TO: MAYOR AND TOWN COUNCIL FROM: LAUREL PREVETTI, TOWN MANAGER SUBJECT: CUT THROUGH TRAFFIC PROJECT 813-0229 A. PROVIDE DIRECTION ON NEXT STEPS TO ADDRESS SUMMER CUT THROUGH TRAFFIC, INCLUDING DIRECTION FOR THE SUMMER OF 2017 AND POTENTIAL FUTURE CAPITAL PROJECTS. B. APPROVE A BUDGET ADJUSTMENT AND THE APPROPRIATION OF $9,908 FROM THE TRAFFIC IMPACT MITIGATION FUND TO THE CUT THROUGH TRAFFIC PROJECT 813-0229. C. AUTHORIZE THE TOWN MANAGER TO EXECUTE AN AGREEMENT WITH W-TRANS FOR ENGINEERING CONSULTING SERVICES IN AN AMOUNT NOT TO EXCEED $66,000. RECOMMENDATION: 1. Provide direction on next steps to address summer cut through traffic , including direction for the summer of 2017 and potential future capital projects. 2. Approve a budget adjustment and the appropriation of $9,908 from the Traffic Impact Mitigation Fund to the Cut Through Traffic Project 813 -0229. 3. Authorize the Town Manager to execute an Agreement with W-Trans for engineering consulting services in an amount not to exceed $66,000. BACKGROUND: On June 7, 2016, the Council approved the temporary closure of South Santa Cruz Avenue a t Wood Road from June 25 through July 10, 2016. On August 2, 2016 the Town Council directed staff to continue the closure through the Labor Day holiday and to continue traffic -related data collection. In addition, staff was directed to begin looking at long term options for mitigating summer cut through traffic. PAGE 2 OF 6 SUBJECT: SUMMER CUT THROUGH TRAFFIC NOVEMBER 22, 2016 S:\COUNCIL REPORTS\2017\01-17-17\Pilot Closure Results\11 Staff Report FINAL.docx 1/12/2017 1:10 PM MM DISCUSSION: Traffic for the duration of the summer proved similar to the early weekends of the closure, with significant relief to the residential neighborhoods south of Highway 9 and a significant decrease in traffic in the downtown business area. Traffic on other local streets demonstrated varied impacts. Streets such as Los Gatos Boulevard, Highway 9, and University and Santa Cruz Avenues continue d to experience very impactful cut through traffic. On the worst of days, traffic impacts spilled over onto smaller residential streets, such as Magneson Loop off of Los Gatos Boulevard or Rose and Andrews Avenues off of Highway 9. These impacts result ed largely from mapping applications, which directed traffic to smaller residential streets to achieve incremental reductions in travel times. This is a phenomenon that many jurisdictions throughout the Bay Area experience in conjunction with commute traffic. Staff anticipates these traffic patterns to continue. Resolving these challenges completely may not be feasible. Some minor relief may be possible through capital improvement projects, such as traffic signal upgrades that move the traffic more efficiently. The pilot closures allowed staff to study and collect data on impacts in relation to the closure. A report from the Town’s consultant, Traffic Patterns, and summarized data are included as Attachments 1 and 2. Staff has ensured that Caltrans has been well informed through this pilot program as they must provide approval for any ongoing closure and Caltrans’ continued support of the Town’s interim activities is necessary1. Some of the observations and hypotheses from the data collected through the summer include the following:  Overall, there was a significant increase in traffic entering Los Gatos on Winchester and Los Gatos Boulevard at Lark Avenue in comparison with 2015 base data.  On southbound Winchester Boulevard at Lark Avenue, a greater number of vehicles followed the signage towards Highway 17, demonstrating that information may be working.  On southbound Los Gatos Boulevard at Lark Avenue, traffic continued the trend of going straight through and not heeding signage directing vehicles back to Highway 17. This materialized in measured and observed queues along Los Gatos Boulevard, especially south of Blossom Hill Road.  Left turn movements on southbound Santa Cruz and University Avenues onto Highway 9 have experienced continued heavy traffic as vehicles use those routes to Highway 17. 1 The Town has an agreement with the Santa Clara County Traffic Authority (the predecessor to the V alley Transportation Authority), that requires the Traffic Authority to provide an agreement with Caltrans to allow for the management of the South Santa Cruz onramp due to traffic conditions. There is no evidence that such an agreement with Caltrans was ever executed. PAGE 3 OF 6 SUBJECT: SUMMER CUT THROUGH TRAFFIC NOVEMBER 22, 2016 S:\COUNCIL REPORTS\2017\01-17-17\Pilot Closure Results\11 Staff Report FINAL.docx 1/12/2017 1:10 PM MM DISCUSSION (cont’d):  Compared with July data, there were some increases in traffic entering the downtown from Highway 9, which may demonstrate increased access to the downtown in August through Labor Day.  Traffic at Main Street and Santa Cruz Avenue showed vehicles headed towards parking areas. Combined with decreased numbers leaving the downtown at Highway 9, these data may point to visitors staying downtown. The closure at Wood Road directly impacted the Caltrans onramp to Highway 17 and as a result, any permanent infrastructure or ongoing closure will require permits from Caltrans. Town staff has met with Caltrans to begin discussions on how to advance a future project. These steps outline that process: 1. The Town needs to develop a concept project to include conceptual plans and a feasibility study for the proposed work, including options for control of the Wood Road intersection. These would be submitted to Caltrans as preliminary documents for a permit. 2. Caltrans provides their reaction or input to the permit submittals. This is the first opportunity for the Town to get documented feedback on whether a project would be permitted by Caltrans. 3. Assuming a positive review, the Town would develop full plans and specifications for the project. Caltrans would continue to review the project and refine its input to the permit request. 4. Once the project scope is fully identified, staff can revise the project cost estimate and identify funding. 5. The project requires environmental review, including a traffic analysis prior to construction. 6. After the completion of environmental review and project approval, construction can begin. The entire timeline for this process is two to three years. In order to assess the first task, staff engaged one of the Town’s on call engineering consultants, W-Trans. On call engineering consultants are selected through a Request for Proposal (RFP) process to provide specialized services on an as needed basis. W-Trans specializes in roundabouts and has extensive local experience working with Caltrans, making them well qualified for this work. W-Trans estimates that the cost of steps one and two above is $66,000. If the Council wishes to pursue this project through steps one and two, funding could be allocated from the remaining Cut Through Traffic Mitigation Capital Improvement Project (Project Number 813-0229) and through a supplement of $9,908 from the Traffic Impact Mitigation Fund. PAGE 4 OF 6 SUBJECT: SUMMER CUT THROUGH TRAFFIC NOVEMBER 22, 2016 S:\COUNCIL REPORTS\2017\01-17-17\Pilot Closure Results\11 Staff Report FINAL.docx 1/12/2017 1:10 PM MM DISCUSSION (cont’d): Previous Town efforts identified a roundabout in proximity to the current location as a gateway project for the Town. That plan, completed in 2003, estimated a project construction cost of $500,000. With Consumer Price Index adjustments, that anticipated cost today would increase to $650,000. Additional costs for project design and project delivery could add $250,000 to the project cost. The overall project scope will significantly influence these costs. The Town will need to identify funding for this project if the Council decides to move forward with it. Funding sources may include Traffic Impact Mitigation funds, Town Capital Improvement Program (CIP) funds, and potential Transportation Initiative funding resulting from the November 2016 Measure B. Given the projected timeline for this project, the Town may wish to consider other measures for implementation during upcoming summers: Street Closure Events. An event similar to the Spring into Green event held last year, may provide one option. This event required expenditures of approximately $10,000. Partnerships with downtown businesses may provide an opportunity to lower these costs. A relocation to a section of Santa Cruz Avenue would help this type of event serve dual purposes. Similar events that provide “open streets” or convert parts of the street to pedestrian zones may also be effective. Staff suggests that closing North Santa Cruz Avenue from Main Street to Elm Street may be a worthwhile trial, pending coordination with local businesses. A trial closure of Santa Cruz Avenue to support an event would identif y any unanticipated impacts, including how traffic reroutes in reaction. Advanced planning would need to occur to avoid increased cut through in residential neighborhoods. If interest lies in this type of solution, staff would appreciate Council input on advancing this type of event alone or in conjunction with a closure at Wood Road. Ongoing Closure at Wood Road The Town may wish to consider ongoing summer closures similar to that from last summer, which will allow for continued data collection and analysis that may be necessary for the project. The temporary closure, data collection, and study costs over last summer totaled approximately $160,000. This option is viable in support of a continued effort to install a permanent roundabout at Wood Road to facilitate ongoing closures, but not as a solution by itself. If the Council would like to continue this option, staff will need advance funding for the period from the Memorial Day weekend through June 30 (11 closure days) and additional funding allocations PAGE 5 OF 6 SUBJECT: SUMMER CUT THROUGH TRAFFIC NOVEMBER 22, 2016 S:\COUNCIL REPORTS\2017\01-17-17\Pilot Closure Results\11 Staff Report FINAL.docx 1/12/2017 1:10 PM MM DISCUSSION (cont’d): for next fiscal year beginning July 1 through Labor Day (21 closure days). Using expenditures from last year, the average daily cost is approximately $9,000, which leads to a total estimated 2017 cost of $288,000 ($99,000 in FY 2016/17). Based on Council input, staff could present the request for these funds as a FY 2016/17 midyear budget adjustment and through the FY 2017/18 Capital Budget program. Capital Projects Town staff previously identified capital projects, including signal modifications, lane changes, and signage to help alleviate traffic beyond the downtown. Staff will provide recommendations for these projects for Council consideration through scheduled Council Priority Setting Study Session in January and through the FY 2017-18 Capital Budget Program. Attachment 1 provides near term and long term options for capital improvements. Council input on the projects could guide staff in preparation for further review. CONCLUSION: The closure of South Santa Cruz Avenue has had a significant impact on traffic in the downtown. On the positive side, traffic flows have been normalized and congestion within the downtown is minimized. The solution continues to create a barrier to the downtown at and approaching Highway 9, making it difficult to enter the downtown area. Additionally, the solution does not provide relief to the areas of Town north of Highway 9. It is requested that the Town Council: 1. Provide direction on next steps to address summer cut through traffic, including direction for the summer of 2017 and potential future capital projects. 2. Approve a budget adjustment and the appropriation of $9,908 from the Traffic Impact Mitigation Fund to the Cut Through Traffic Project 813 -0229. 3. Authorize the Town Manager to execute an Agreement with W-Trans for engineering consulting services in an amount not to exceed $66,000. COORDINATION: This report has been coordinated with the Finance Department and the Town Attorney. PAGE 6 OF 6 SUBJECT: SUMMER CUT THROUGH TRAFFIC NOVEMBER 22, 2016 S:\COUNCIL REPORTS\2017\01-17-17\Pilot Closure Results\11 Staff Report FINAL.docx 1/12/2017 1:10 PM MM FISCAL IMPACT: In addition, through the priority setting in early 2017, the Town Council may identify projects or studies that require additional funding to continue efforts associated with this item. ENVIRONMENTAL ASSESSMENT: This is not a project defined under CEQA, and no further action is required. Attachments: 1. Highway 17 On-Ramp Extended Closure Observations 2. Traffic Volume Data Comparison Original Expended/Recommended Total Proposed Budget Encumbered Available Budget Recommended Project Fiscal Impact Funding To Date Balance Adjustment Budget Cost Cut-Through Traffic Mitigation Project 471-813-0229 215,000$ 158,908$ 56,092$ 9,908$ 66,000$ 66,000$ TOTALS 215,000$ 158,908$ 56,092$ 9,908$ 66,000$ 66,000$ TOTAL EXPENDITURES BY CATEGORY: Consultation Services 86,008$ Supplies & Equipment 72,900$ TOTALS 158,908$ CUT-THROUGH TRAFFIC MITIGATION Project 813-0229