1997-075-Execution Of An Agreement With Pacific Westhershield, Inc.RESOLUTION 1997 - 75
RESOLUTION OF THE TOWN COUNCIL
OF THE TOWN OF LOS GATOS
AUTHORIZING THE EXECUTION OF AN AGREEMENT WITH
PACIFIC WEATHERSHIELD, INC.
FOR THE CONSTRUCTION OF PROJECT 9705
CIVIC CENTER PLAZA DECK ROOF REPLACEMENT
WHEREAS, bids were sought in conformance with State and Town law, and Pacific
Weathershield, Inc. is the lowest bidder for Project 9705 - Civic Center Plaza Deck Roof
Replacement.
THEREFORE, BE IT RESOLVED: by the Town Council of the Town of Los Gatos,
County of Santa Clara, State of California, that the Town Manager is authorized to enter into an
agreement with Pacific Weathershield, Inc. for the construction of Project 9705 - Civic Center
Plaza Deck Roof Replacement, (attached) as Exhibit A.
PASSED AND ADOPTED at a regular meeting of the Town Council of the
Town of Los Gatos, California, held on the 7th day of July, 1997, by the following vote.
COUNCIL MEMBERS:
AYES: Randy Attaway, Steven Blanton, Jan Hutchins, Linda Lubeck,
Mayor Joanne Benjamin.
NAYS: None
ABSENT: None
ABSTAIN: None
SIGNED MAYOR OF THE TOF LOS GATOS
LOS GATOS, CALIFORNIA
ATTEST:
I iL 1--Cn
CLERK OF THE TOWN OF LO GATOS
LOS GATOS, CALIFORNIA
Section 7
AGREEMENT
Town CLERK
AGR:. q�Z
RE
}00: —.
THIS IS AN AGREEMENT between the Town of Los Gatos (hereinafter referred to as "Owner ") and Pacific
Wesathershield, Inc. (hereinafter referred to as "Contractor ").
Owner and Contractor, for the consideration hereinafter named, agree as follows:
1 - SCOPE OF WORK
Contractor shall furnish all materials and perform all of the work for the construction of PROJECT #9705 -
CIVIC CENTER PLAZA DECK ROOF REPLACEMENT in accordance with the Contract Documents.
2 - CONTRACT PRICE
As full compensation for fiunishing all materials and for doing all the work contemplated and embraced in this
agreement, also for all loss or damage arising out of the nature of the work aforesaid, or from the actions of
the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the
prosecution of the work until its acceptance by Owner, and for all risks of every description connected with the
work, also for all expenses incurred by or in consequence of the suspension or discontinuance of work, and for
well and faithfully completing the work, and the whole thereof, in the manner and according to the Contract
Documents, Owner shall pay the amount specified by Contractor in Contractor's Bid Form.
3 - CONTRACT DOCUMENTS
All rights and obligations of Owner and Contractor are fully set forth and described in the Contract Documents.
All parts of the Contract Documents are intended to be correlated so that any work called for in one part and
not mentioned in the other, or vice versa, is to be executed the same as if mentioned in all said documents. The
Contract Documents are defined in section 8 -01(A) of these Specifications and are incorporated herein by
reference the same as though set out in full.
4 - BEGINNING OF WORK
Following the execution of this agreement and the approval of bonds and insurance policies and certificates,
Owner shall issue a notice to proceed with the work. Commencing work or the entrance of equipment or
materials on the site of the work by Contractor before receipt of the notice to proceed is at the sole risk and
expense of Contractor, and the Contractor shall be fully liable for any damage or injury sustained by Owner or
third persons resulting therefrom.
5 - TIME OF COMPLETION
The work called for herein shall be fully completed within the time limit set forth in the Special Conditions.
Revised JANUARY 17, 1995 (ATY)
SECTION 7 - AGREENfENT
6 - CORRECTION OF WORK AFTER ACCEPTANCE AND FINAL PAYMENT BY TOWN
0
Contractor shall remedy any defects due to faulty materials and/or workmanship and pay for any damages to
other work and/or existing facilities resulting therefrom which shall appear within a period of two years from
the date of recording of the Notice of Completion.
7 - LIQUIDATED DAMAGES
The undersigned has reviewed and is thoroughly familiar with the appropriate sections of the Contract and
Section 8 -06(C) of these Specifications pertaining to liquidated damages.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement as of the _ day of
,19
TOWN OF LOS GATOS
im
Town Manager
CONTRACTOR
M
President
616452
Contractor's License Number
Pacific Weathershield, Inc.
2305 Paragon
San Francisco CA 94124
Business Address
APPROVED AS TO FORM:
ORRY P. KORB
Town Attorney
ATTEST:
MARIAN COSGROVE
Town Clerk
Revised JANUARY 17, 1995 (ATY)