2009-023-Town Manager To Direct Geier & Geier Consulting To Conduct Environmental Review For The Library ProjectRESOLUTION 2009 -023
RESOLUTION OF THE TOWN COUNCIL OF THE TOWN OF LOS GATOS
AUTHORIZING THE TOWN MANAGER TO DIRECT
GEIER & GEIER CONSULTING TO CONDUCT
ENVIRONMENTAL REVIEW FOR THE LIBRARY PROJECT
RESOLVED, that the Town of Los Gatos Town Council has reviewed conceptual plans for the new Town
Library; and
RESOLVED, that the Council has authorized the Town Manager to execute and agreement with Noll & Tam
Architects for schematic design through construction administration services for the project and
RESOLVED, that the next step in the process is to commence with environmental review of the project; and
RESOLVED, that the Town has a contract with Geier & Geier Consulting (GGC) for environmental assessment
services; and
RESOLVED, that project managers Valerie and Frederick Geier of GGC have submitted a proposal and cost
estimate for preparation of a Focused Environmental Impact Report (EIR) and
RESOLVED, by the Town Council that the TOWN OF LOS GATOS enter into an agreement for services by
the environmental consultant.
FURTHER RESOLVED, by the Town Council that the Town Manager is authorized to direct then consultant to
conduct the environmental review, consistent with the scope of work attached hereto as Exhibit 1, on behalf of the
TOWN OF LOS GATOS.
PASSED AND ADOPTED at a regular meeting of the Town Council held on the 16th day of March, 2009, by
the following vote:
COUNCIL:
AYES: Diane McNutt, Joe Pirzynski, Steve Rice, Barbara Spector, and Mayor Mike Wasserman
NAYS:
ABSENT:
ABSTAIN:
SIGNED:
MAYOR OF THE TOWN OF LOS GATOS
LOS GATOS, CALIFORNIA
AT T:
CLERK O THE TOWN OF LOS GATOS
LOS GATOS, CALIFORNIA
0
GEIEIt er GEIE,R CONSULTING, INC.
Memorandum
To: Ms. Suzanne Davis Date: March 12, 2009
From: Valerie Geier and Frederick Geier
Subject: Proposal to Prepare an EIR; Los Gatos Library
Geier and Geier Consulting, Inc. (GGC) is pleased to submit this proposal to prepare the
Environmental Impact Report (EIR) for the proposed Los Gatos Library, which is to be adjacent
to Civic Center on Villa Avenue.,As indicated on the site plan dated 12/8/08, project
development would include the removal of five existing residences, followed by construction of a
two -story library building and two surface parking lots. Based on the parking report, the library
would be approximately 40,000 square feet. No subsurface facilities are proposed. The existing
Fiesta Way and the west end of Villa Avenue would be eliminated and incorporated into surface
parking lots. Project access would be from East Main Street via aisleways in these surface
parking lots, which would extend from East Main Street to the south side of Villa Avenue. Since
the existing library space will be vacated when the proposed library is completed, use of the
vacated space will need to be defined by the Town and considered in the CEQA impact
analysis.
For this project, Frederick Geier will serve as Project Manager, while Valerie Geier will be
Technical Director for this project. Our in -house capabilities will be complemented by the
expertise of the following subconsultants: William Kanemoto & Associates (WKA) will complete
the aesthetics /visual analysis, Carey & Company will evaluate the historical significance of
existing homes on the project site, Holman & Associates will be responsible for the
archaeological resources evaluation, and PIERS Environmental Services, Inc. will complete the
Phase I ESA for the hazards evaluation. WKA completed the visual simulations for the Old
Town EIR, while Holman & Associates has completed archaeological studies for numerous
projects (including the Highlands of Los Gatos EIR), PIERS was retained by the Town in 2002
to complete the Phase I studies for the two residential properties on Fiesta Way.
Scope of Work
Upon authorization by the Town, GGC will proceed with field studies to supplement technical
studies already completed by the Town for the project. The following tasks will be performed to
complete the environmental documentation process for the project.
P.O. Box 5054 - Berkeley, CA 94M -5054 • 510.644.2535 • 510.644.2534 rnx • www,geierconsulring.corn
Exbibit I
Memo to Suzanne Davis
March 12, 2009
Page 2 of 9
Task 1: Initial Study (IS), Notice of Preparation (NOP), and Administrative Draft
Environmental Impact Report (ADEIR)
GGC will prepare the IS and NOS' in accordance with CEQA Guidelines. The IS will include a
project description and evaluation of all environmental topics. For any impacts determined to be
potentially significant, the IS will include explanatory discussions identifying the environmental
issues that will need to be addressed in the EIR (providing justification for a focused EIR). The
decision to include an environmental topic In the focused EIR will be based on whether the
impact would be less than significant and/or whether there is sufficient information to make a
determination. For example, if a detailed technical study is required to make an impact
determination (such as traffic and parking), this topic will be deferred to the EIR so as not to
delay completion of the Initial Study and NOP and to keep the environmental review process
moving forward. This scope of work assumes that the Town will distribute the NOP as required
by CEQA.
Under each environmental topic of the focused El R, the EIR will describe the existing
environmental setting, outline significance thresholds, describe methodologies employed to
assess impacts, identify significant impacts based on these thresholds, identify mitigation
measures proposed as part of the project or recommended by the EIR, and then define whether
or not the measures have mitigated significant impacts to a less than significant level. The EIR
will conform to all of the requirements identified by CEQA.
Based on preliminary discussions with Town staff, the Town will provide a number of technical
studies that will be required for the EIR, as indicated below, While the IS and focused EIR will
address all environmental topics required by CEQA, it is expected that detailed analysis will be
required under the following topics:
Aesthetics: A detailed visual analysis will be required in the EIR due to the visual sensitivity
of this area. The visual impacts are typically defined by visual impacts on public viewing
areas such as parks, schools, roads, etc. Given the project's location adjacent to the Civic
Center and East Main Street, both public viewing areas, it will be important to evaluate the
project's visual impact from these two key viewpoints. Nighttime illumination could also be
an issue depending on the design option ultimately selected by the Town.
William Kanemoto & Associates (WKA) will be responsible for completing the visual
analysis. WKA will consult with Town staff to determine two key viewpoint locations. Visual
simulations of the proposed library and parking lots will be prepared by WKA from these two
viewpoints. WKA will prepare an accurate and realistic 3D computer model of the proposed
library and associated facilities based on plans and elevations to be provided by the City.
The model would then be used to produce realistic computer - generated simulations from
viewpoints to be selected in consultation with the City. The level of detail and realism of the
simulation would reflect the level of design detail and other information available, and will
include proposed streetscape, people and vehicles. For purposes of cost estimation, we
assume that two simulations would be required.
Memo to Suzanne Davis
March 12, 2009
Page 3 of
The visual analysis will focus on CEQA significance criteria; (1) changes in visual character
due to proposed removal of existing homes and landscape trees, as well as development of
the library building and surface parking lot (including consistency of building mass and
design with surrounding /adjacent development); (2) light and glare impacts; and (3)
consistency with pertinent Town General Plan policies, The analysis will not address
architectural issues since the Town will address these during the project review process.
• Air Quality and Climate Change: GGC will estimate the project's air pollutant emissions
and compare them to BAAQMD significance thresholds for criteria air pollutants. GGC will
also complete an evaluation of the project's impact on climate change. This analysis will
entail an estimate of greenhouse gas emissions associated with the project (construction
and operation) as well as a discussion of project's consistency with AB32 (Global Warming
Solutions Act) goals. The significance determination for this impact will largely depend on
the extent of green building measures that are incorporated into the project design (e.g.,
LEED standards).
• Biological Resources: The Town's consulting arborist, Arbor Resources, will provide a tree
evaluation that evaluates the direct and indirect impacts of project construction on the long-
term health and vigor of existing trees on the site. Preliminary review of the site indicates no
other sensitive biological resources on the project site. Therefore, this analysis will focus on
proposed tree removal impacts and tree replacement.
• Cultural Resources: Carey & Co. Inc. will evaluate the historical significance of the five
existing homes on the project site, and determine the impacts of proposed
demolition /removal of these homes. Carey & Co, will provide all necessary documentation
(e.g. DPR Forms) in the event any of these homes are determined to be historically
significant.
Holman & Associates will evaluate the project's potential effect on archaeological resources
(including historical archaeology). Holman will complete a records search at the
Archaeological Clearinghouse at Sonoma State University and conduct a field
reconnaissance to determine the potential to encounter archaeological resources.
Recommendations will be provided to ensure than any known and unknown resources are
adequately protected.
■ Geology, Seismicity, and Soils: In 1990, the Town retained Terratech, Inc, to complete a
preliminary geologic and geotechnical survey of the library site. This survey included
subsurface trenching to determine the potential for surface fault rupture and only included
the portion of the project site located south of Villa Avenue, The portion of the site located
north of Villa Avenue is traversed by a trace of the Eerrocal Fault, but the fault location was
not confirmed by this study. In addition, the Terratech study only confirmed the absence of
the fault in the area south of the existing sidewalks that extends along the south side of Villa
Avenue. The preliminary site plan indicates that the proposed library would extend over Villa
Memo to Suzanne Davis
March 12, 2009
Page 4of9
Avenue, and the area under Villa Avenue was not explored by Terratech. Terratech also
identified two possible landslides on the hill located south of the site as well as a mine tunnel
entrance. Exploratory trenching will need to be completed in the vicinity of Villa Avenue to
confirm that the proposed library footprint would not be located on a fault trace. Additional
detailed geotechnical investigations will be required to determine the potential for other
hazards such as landslides, expansive soils, slope instability hazards associated with the
mine tunnel, and groundshaking. GGC will summarize findings of these investigations.
Hazards: The project site Is comprised of six residential lots, and there are currently five
residential structures that would be removed as part of project development. Past land uses
on the project site need to be confirmed in order to determine the potential to encounter
hazardous materials. Records indicated that Phase 9 Environmental Site Assessments
(ESA) have been completed on some or all of these six lots. However, some or all were
completed more than six months ago and will need to be updated. PIERS Environmental
Services will update and complete a Phase I ESA for the entire project site. GGC files
indicate that a Building Conditions Assessment (including inspection for asbestos) may have
been done on some or all of these homes. While surveys for asbestos and lead -based
paints will need to be done prior to construction, these surveys are not required for the
CEQA analysis. CEQA documentation will include recommendations to ensure these
hazards are properly surveyed and abated prior to building demolition /removal.
The General Plan's Fire Hazard Area Map indicates the project site is located within the Fire
Hazard Area. GGC will address wildfire hazards and review the project design for
consistency with applicable General Plan policies.
Hydrology and Water Quality: Since the project possibly involves disturbance of more than
one acre, GGC will identify jurisdictional agencies and possible requirements, such as a
storm water pollution prevention plan (SWPPP) and non -point source measures to minimize
or eliminate pollutant discharges from construction activities and from developed areas after
construction (pursuant to C.3 requirements). GGC will complete this analysis, but will rely on
Town Engineering to evaluate the adequacy of existing storm drain capacity to
accommodate increased runoff associated with the proposed project.
Land Use: The project site is currently designated by the General Plan as Medium - Density
Residential, while the site is zoned Multi - Family Residential (RM:5 -12). It appears that the
project site will require a General Plan amendment and rezoning, although such
amendments are not considered to a significant environmental impacts. 'Nevertheless, the
EIR will examine the project's consistency with existing General Plan policies and zoning
requirements that pertain to the proposed project. In addition, this analysis will examine
existing surrounding public, residential, and commercial land uses, and evaluate
compatibility of the proposed project with these uses. Land use compatibility criteria will
include consideration of the combined or cumulative effect of project - related noise,
aesthetics /visual, and traffic impacts, GGC will rely on Town staff's evaluation of the
Memo to Suzanne Davis
March 12, 2009
Page 5 of 9
project's consistency with General Plan, Zoning Ordinance and applicable design guidelines
to complete this analysis,
Noise: The proposed library use is considered a noise- sensitive use. Therefore, a 24 -hour
noise measurement will be conducted at the project site to ensure that the proposed use is
compatible with existing and future noise levels at the site. In addition to noise compatibility,
the noise analysis will identify project - related operational noise impacts due to increased
traffic and parking activities as well as operation of mechanical equipment associated with
the proposed new library building. Specifically, the noise analysis will evaluate potential
changes in the local noise environment from the proposed expansion of surface parking on
the project site as well as traffic circulation changes on local streets that could result from
the proposed project. Project - related mechanical equipment will be reviewed for
conformance with the Town's Noise Ordinance. The noise analysis will also evaluate short -
term noise impacts resulting from project- related construction activities including operation
of construction equipment on -site and increased truck traffic on local streets. Potential
impacts on any identified sensitive receptors will be assessed, and measures to reduce the
impacts of construction and operational noise will be recommended as necessary.
Traffic, Circulation, and Parking: The Town's consulting traffic engineer, TJKM, will be
responsible for preparing the detailed traffic and parking, analysis. TJKM's findings and
recommendations will be presented in the EIR. GGC assumes that TJKM will adequately
address project - related and cumulative traffic impacts on local roadways and intersection
operations (including CMP intersections) as well as traffic safety impacts associated with
project - related increases on local roadways. While the Town has provided a calculation of
the existing parking supply and the number of spaces that will be required, an evaluation of
the adequacy of the proposed parking supply will need to be completed by TJKM.
Topical Issues Required by CEQA: The EIR will include topics required by CEQA
including Effects Not Found to be Significant, Growth - inducing impacts, Cumulative Impacts,
and Significant Unavoidable Adverse impacts. It is anticipated that the following topics will
be determined to have less - than- significant impacts and will not require detailed impact
analysis: Agriculture Resources, Air Quality, Climate Change, Mineral Resources,
Population and Housing, Public Services /Utilities, and Recreation.
Early in the process, GGC will work with Town staff to develop up to four alternatives for the
project. The following possible alternatives could be evaluated in the EIR: No Project
Alternative, Reduced Project Alternative, Off -site Project Alternative (only if there are other
suitable sites on Town -owned properties), and Modified Design Alternative. The latter
alternative would represent an alternative design that incorporates all the design - related
mitigation measures recommended in the EIR. Alternatives will be evaluated at a more
general level of detail than the project, and the degree of impact will be compared to project
impacts.
Memo to Suzanne Davis
March 12, 2009
Page 6 of 9
Deliverables; 5 Copies of the Draft IS and NOP
25 Copies of the Final IS and NOP
5 Copies of the Administrative Draft EIR
Task 2: Prepare Draft EIR
After Town comments are received, GGC will incorporate requested changes and prepare the
Draft EIR, It is assumed the Town will be responsible for distributing the Draft EIR to all
agencies and Individuals included on the distribution list, as well as preparation and distribution
of the Notice of Completion for the EIR.
Deliverables: 60 Copies of the Draft EIR
Task 3: Final EIR (Responses to Comments Document) and Mitigation Monitoring and
Reporting Program
After all written and oral comments are received, GGC will respond to all relevant comments
and prepare the Responses to Comments document (RTC), or Final EIR, consistent with CEQA
Section 15132. This document will include a summary of comments received at the Planning
Commission public hearing, copies of all written comments, and responses to all CEQA- relevant
comments. GGC assumes that the Town will provide transcripts of the public hearings.
In accordance with AB 3180, a Mitigation Monitoring and Reporting Program (MMRP) will be
prepared. The MMRP will specify the timing and issues that need to be adequately addressed
in this program. The MMRP will be provided as an attachment to the Responses to Comments
document.
Deliverables: 5 Copies of Draft Response to Comments document
40 Copies of the Response to Comments document
Task 4: Attend Public Hearings
Under the terms of this proposal, GGC (Frederick and Valerie Geier) will attend up to three
public hearings: two meetings before the Planning Commission and one before the Town
Council. Attendance at any additional meetings or hearings, or attendance by other specialist
subcontractors will be on an extra - service basis.
Memo to Suzanne Davis
March 12, 2009
Page 7 of 9
Schedule
GGC will be able to commence work upon authorization by the Town. We estimate the following
schedule for completion of the work program:
Task Duration
Receive Authorization to Proceed
Task 1: IS, NOP, ADEIR
Staff Review
Complete Final IS
ISINOP Comment Period
Prepare Administrative Draft EIR
Staff Review
Task 2: Prepare Draft EIR
Public Review Period
Task 3: Prepare Response to Comments Document
and Mitigation Monitoring and Reporting Program
Public Review
Task 4: Attend Public bearings
March 16, 2009
April 13 (4 Weeks)
April 20 (1 Week)
April 27 (1 Week)
April 28 to May 28 (30 Days)
May 28 to July 23 (8 Weeks)
July 23 to August 6 (2 Weeks)
August 6 to August 20 (2 Weeks)
August 21 to October 2 (45 Days)
October 2 to October 30 (4 Weeks)
October 30 to November 13 (15 Days)
According to Town bearing Schedules
The amount of time required by Town staff for document review is assumed and subject to
variation at the discretion of the Town. The schedule for the ADEIR assumes responses to the
NOP do not raise any substantial new issues and that technical studies are provided by May
28 111 , when the ADEIR is scheduled to begin, This schedule also assumes that comments are
typical in volume and do not require any new technical studies in addition to those already
anticipated.
Costs
GGC proposes to undertake the scope of work described above, including the preparation of
administrative and public review environmental documents and attendance at up to three public
hearings for a fee of labor and expenses not to exceed $100,758. Services beyond those
specified in this proposal will be billed on a time -plus- expenses basis or negotiated under a
separate contract. Fees will be billed on a monthly basis. A breakdown of costs by personnel,
time, and expenditures for each of the tasks identified in this proposal is provided as follows:
Memo to Suzanne Davis
March 12, 2009
Page 8 of 9
NOTES; Printing and distribution costs include 5 Draft ISs, 25 ISs, 5 ADEIRs, 60 DEIRs, 5 Draft RTCs, and 40 Final RTCs. Labor
estimate for Task 3 assumes about 75 comments are received and require responses. If an excessive number of comments are
received or additional analysis is required, there may be additional costs.
Client Responsibilities
GGC assumes that the Town will provide the following information:
1. Two hard copy.sets of project plans (including a grading and drainage plan) and electronic
files, and one CDIDVD with electronic files containing project plans in pdf format
2. Detailed studies as outlined in the above scope of work, which includes:
■ Arborist's Report (Arbor Resources)
■ Updated Detailed Geotechnical Investigation (addressing proposed building footprint and
surface fault rupture hazards)
Hours
Tasks
F. Geier
V. Geler
Staff
WKA
PIERS
Holman
Carey
Total Hours
1. Initial Stud Needed to focus out topics
Prepare Initial Study
24
10
34
2. Administrative Draft EIR
Project Manage ment/Edltln g
60
30
90
Word Processing
40
40
Graphics
30
30
Introduction
4
4
summary
6
6
Project Description
6
6
Environmental Setting/Impacts/ Miti atfon
Aesthetics_
4
$11,840
Air Quail t and Climate Change
16
_
_
16
Biological Resources
12
12
Cultural Resources
16
1 2
$1,500
$8,910
16
Geology and Seismicit
12
Hazards and Hazardous Materials
8
$ 2,500
8
20
H dr logy and Water Quality
20
Land Use and Planning
16
16
Population and Housing
16
Traffic, Circulation, and Parking
16
16
Noise
24
24
4
20
Public Services and Ut i l ities
Required Considerations
4
12
_ _
B
3. Draft EIR
Prepare Draft EIR
i
__
16
16
8
$944
40
4. Responses to Comments Document and MTtI ation
Prepare Res onses to Comments 40
Monitoring Program
40 16
96
5. Public Hearings
Attend Three Hearin s
20
20
40
I
I
I
Total Hours
280
196
94
570
Hourly Rate
$135
$135
$65
Labor Costs
$37,800
$26,460
$6,110
$12,784
$2,500
_
$1,500
$8,910
$96,064
Direct Expenses
$4,694
Inclusive
Inclusive
Inclusive
Indusive
$4,694
Total Cost
$75,064
112,784
$2,500
$1,500
$8,910
$100,758
NOTES; Printing and distribution costs include 5 Draft ISs, 25 ISs, 5 ADEIRs, 60 DEIRs, 5 Draft RTCs, and 40 Final RTCs. Labor
estimate for Task 3 assumes about 75 comments are received and require responses. If an excessive number of comments are
received or additional analysis is required, there may be additional costs.
Client Responsibilities
GGC assumes that the Town will provide the following information:
1. Two hard copy.sets of project plans (including a grading and drainage plan) and electronic
files, and one CDIDVD with electronic files containing project plans in pdf format
2. Detailed studies as outlined in the above scope of work, which includes:
■ Arborist's Report (Arbor Resources)
■ Updated Detailed Geotechnical Investigation (addressing proposed building footprint and
surface fault rupture hazards)
Memo to Suzanne Davis
March 12, 2009
Page 9 of 9
■ Traffic and Parking Study (TJKM)
■ Staff Evaluation of General Plan, Zoning Ordinance and applicable design guidelines
Items #1 and 42 should be provided at least six weeks prior to completion of the EIR.
Remaining items should be provided at least four weeks prior to completion of the
Administrative Draft EIR.