2004-005- Work Of Cupertino Electric, Inc. For Project 02-33B - Santa Cruz Avenue Electrical Improvements And Authorizing The Town Manager/Executive Director To ExecuteRESOLUTION 2004 - 5
RESOLUTION OF THE TOWN COUNCIL,/REDEVELOPIVIENT AGENCY
OF THE TOWN OF LOS GATOS
ACCEPTING WORK OF CUPERTINO ELECTRIC. INC. FOR
PROJECT 02-33B --SANTA CRUZ AVENUE ELECTRICAL IMPROVEMENTS AND
AUTHORIZING THE TOWN MANAGER/EXECUTIVE DIRECTOR TO EXECUTE
CERTIFICATE OF ACCEPTANCE AND NOTICE OF COMPLETION
FOR RECORDING BY THE TOWN CLERK/SECRETARY
WHEREAS, on Apri121, 2003, the Town Council/Redevelopment Agency approved
plans and specifications for Project 02-33B - Santa Cruz Avenue Electrical Improvements; and
WHEREAS, on August 18, '2003, the Town Council/Redevelopment Agency awarded
the contract for the proposed work to Cupertino Electric, Inc.; and
WHEREAS., Cupertino Electric, Inc. substantially completed the project in conformance
with the plans and specifications pursuant to Council/Agency approval; and
WHEREAS, ten percent of the performance bond provided by Cupertino Electric, Inc.
shall remain in place for two years until January 5, 2005 to guarantee the work; and
WHEREAS, the work on Project 02-33B -Santa Cruz Avenue Electrical Improvements
is hereby accepted as complete pursuant to the plans and specifications for the project.
NOW THEREFORE BE IT RESOLVED, that the Town Manager/Executive Director
is authorized and directed to execute the Certificate of Acceptance and Notice of Completion
attached as (Exhibit A) hereto.
BE IT FURTHER RESOLVED, that the Town Clerk/Secretary is directed to transmit
this Certificate of Acceptance and Notice of Completion to the Recorder of Santa Clara County
for recording.
PASSED AND ADOPTED at a regular meeting of the Town Council/Redevelopment.
Agency of the Town of Los Gatos, California, held on the 5`'' day of January, 2004 by the
following vote.
COUNCIL/AGENCY MEMBERS:
AYES: Sandy Decker, Diane McNutt, .Joe Pirzynski, Mike Wasserman,
Mayor Steve Glickman.
NAYS: None
ABSENT: None
ABSTAIN: None ~ ~
SIGNED: ~,~~--~-'rte-a~..---~
MAYOR/CHAIlZ OF THE REDEVELOPMENT
AGENCY OF THE TOWN OF LOS GATOS
LOS GATOS, CALIFORNIA
ATTEST::
~,
CLERK/SECRBTARY OF'THE REDEVELOPMENT
AGENCY (~F THE TOWN OF LOS GATOS
LOS GATOS, CALIFORNIA
Mi2EC; c~~F. ~i
PLEASE .RECORD .AND RETURN TO:
Town Clerk/Secretary
P.O. Box 949
Los Gatos, CA 95031.
CERTIFICATE OF ACCEPTANCE AND NOTICE OF COMPLETION
PROJECT 02-33B - SANTA CRUZ AVENUE ELECTRICAL IMPROVEMENTS
TO WHOM IT MAY CONCERN:
We do hereby certifythat Cupertino Electric, Inc. substantially completed the worlc on November
21, 2003 called for in the agreement with the Town of Los Gatos dated September 16, 2003. The
work is listed in the specifications prepared by the Town of Los Gatos and generally consisted of
furnishing all labor, materials, tools, equipment, and services required for completion ofthe Santa
Cruz .Avenue Electrical Improvements .located in the TOWN OF LOS GATOS, County of Santa
Clara, State of California and was completed, approved .and accepted .January 5, 2004..
The Surety on the bond accompanying the contract/agreement is Safeco Insurance Company of
America.
Bond #: 6210954
Dated: 9/3/03
TOWN OF LOS GATOS
By:
Director of Parks and Public Works.
By:
Town Manager/Executive Director
I, DEBRA J. FIGONE, the Town Manager/Executive Director of the Redevelopment Agency of
the Town of Los Gatos, have read the foregoing CERTIFICATE OF ACCEPTANCE .AND
NOTICE OF COMPLETION and know the contents thereof. The same is true of my own
knowledge, except as to the matters which are therein alleged on information or belief, and as to
those matters I believe it to be true.
I declare under penalty of perjury that the .foregoing. is true and correct and that this declaration
was executed on 2004 at Los Gatos, California.
DEBRA J. FIGONE, 'TOWN MANAGER/EXECUTTVE DIRECTOR of
the Redevelopment Agency of the Town of Los Gatoa
RECOMMENDED BY:
.Director of Parrs and Public Works
APPROVED AS TO FORM:
Date:
Date:
Town Attorney/General Counsel
TOWN OF LOS GATOS, CALIFORNIA, ACKNOWLEDGMENT
.State of California
County of Santa Clara
On before me, MARIAN V. COSGROVE, Town Clerk/Secretary of the
Redevelopment. Agency, personally appeared DEBRA J. FIGONE Town Manager/Executive
Director of the .Redevelopment Agency, personally known to me to be the person whose name
is subscribed to the within instrument and acknowledged to me that he executed the same in his
authorized capacity, and that by his signature on the within instrument the entity upon behalf of
which the person acted, The Town of Los Gatos, executed the instrument.
WITNESS myhand and official seal.
Town Clerk/Secretary ofthe Redevelopment Agency
of the Town of Los Gatos
Los Gatos, California
CAPACITY CLAIMED BY SIGNER:
Municipal Officer of the Town of Los Gatos
DESCRIPTION OF ATTACHED DOCUMENT:
Title of Document: Certificate of Acceptance .and Notice of Completion
Project 02-33B -Santa Cruz Avenue Electrical Improvements
Number of Pages: 2
Date of Document:
Signer(s) Other than Named Above: None