2000-107-Work Of J.J.R. Construction, Inc. Project 00-01-Annual Sidewalk, Curb And Gutter Reconstruction And Authorizing The Town Manager-Executive Director To ExeRESOLUTION 2000 -107
RESOLUTION OF THE TOWN COUNCIL AND REDEVLOPMENT AGENCY
OF THE TOWN OF LOS GATOS
ACCEPTING WORD OF J.J.R. CONSTUCTION, INC.
PROJECT 00-01-ANNUAL SIDEWALK, CURB AND GUTTER RECONSTRUCTION
AND AUTHORIZING THE TOWN MANAGER/EXECUTIVB DIRECTOR TO EXECUTE
CERTIFICATE OF ACCEPTANCE AND NOTICE OF COMPLETION
FOR RECORDING BX TOWN CLERK
WHEREAS:
1. On December 6, 1999, the Town Council/Agency awarded the contract for the
proposed work to J.J.R. Construction, Inc.
2. J.J.R. Construction, Inc., substantially completed the project in conformance with the
plans and specifications pursuant to Town Council/Agency approval.
RESOLVED:
A. The work on Project 00-01-Annual Sidewalk, Curb and Gutter Reconstruction,
completed by J.J.R. Construction, Inc., is hereby :accepted as complete pursuant to the plans and
specifications for the project.
B. The Town Manager/Executive Director is authorized .and directed to execute the
Certificate of Acceptance and Notice of Completion attached as Exhibit A hereto.
C. The Town Clerlc is directed to transmit this Certificate of Acceptance and Notice of
Completion to the Recorder of Santa Clara County for recording.
PASSED AND ADOPTED at a regular meeting of the Town Council/Redevelopment
Agency of the flown of Los Gatos, California, held on the 5th day of September, 2000 by the
following vote.
COUNICL/AGENCY MEMBERS:
AYES: Randy Attaway, Jan Hutchins, Linda Lubeck, Joe Pirzynski,
Mayor .Steven Blanton.
NAYS : None
ABSENT: None
ABSTAIN: None
SIGNED.: MA CHAIR F HE O OF LOS
GA OS /REDEVELOPMENT AGENCY
LOS GATOS, CALIFORNIA
ATTEST:
~~ ~ ~
CL'F,~.I~/SECRETARY OF THE TOWN OF LOS GATOS
REDEVELOPMENT AGENCY
LOS GATO~, CALIFORNIA
.PLEASE RECORD AND RETURN TO:
Town Clerlc
P.O. Box '949
Los Gatos, CA 95031
CERTIFICATE OF .ACCEPTANCE .AND NOTICE OF COMPLETION
PROJECT 00-01-ANNUAL SIDEWALK, CURB AND GUTTER RECONSTRUCTION
TO WHOM IT MAY CONCERN:
We do hereby certify that J.J.R. Construction, Inc., substantially completed the work on .June 9,
2000 called for in the agreement with the Town Council/Redevelopment Agency dated December
6, 1999. The work is listed in the specifications prepared by the Town of Los Gatos and generally
consisted of furnishing all labor, materials, tools, edupment, and services reduired for completion
of Project #00-01 -Annual Sidewalk, Curb and Gutter Reconstruction, located in the TOWN OF
LOS GATOS, County of Santa Clara, State of California and was completed, approved and accepted
September 5, 2000.
The Surety on the bond accompanying the contract/agreement is the Employers Insurance of
Wausau a Mutual Company.
TOWN OF LOS GATOS
By:
Director of Parlcs and Public Worlcs
By:
Town Manager/Executive Director
I, LESLIE R. WHITE, the Interim Town Manager/Executive Director of Town of Los Gatos,llave
read the foregoing CERTIFICATE OF ACCEPTANCE .AND NOTICE OF COMPLETION and
l~now the contents thereof. The same is true of my own knowledge, except. as to the matters which
are therein alleged on information or belief, and as to those matters I believe it to be true.
I declare under penalty ofpeijury that the foregoing is true and correct and that this declaration was
executed on , 2000 at Los Gatos, California.
LESLIE R. WHITE,
.Interim Town Manager/Executive Director