Loading...
Item 9 Staff Report Request for Amicus Participation in Amelco Electric v. City of Thousand Oaks, Supreme Court Case No. S091069, 2nd Civil No. B129406 at no Cost to the TownMEETING DATE: 6!4/01 ITEM NO. ca COUNCIL AGENDA REPORT DATE: May 25, 2001 TO: MAYOR AND TOWN COUNCIL FROM: ORRY P. KORB, TOWN ATTORNEYOfr SUBJECT: REQUEST FOR AMICUS PARTICIPATION INAMELCO ELECTRIC v. CITY OF THOUSAND OAKS, SUPREME COURT CASE NO. S091069, 2ND CIVIL NO. B129406, AT NO COST TO THE TOWN RECOMMENDATION: Authorize the Town Attorney to include the Town of Los Gatos as an amicus curiae in the case of Amelco Electric v. City of Thousand Oaks, Supreme Court, case number S091069, 2nd civil case number B129406, at no cost to the Town. BACKGROUND: In February 2000 the Town joined in the amicus brief in this case filed in the appellate court. The case affected cities' liability for contractors' claims beyond the contract price. The City of Thousand Oaks contracted with the lowest bidder to perform electrical work on its Civic Center project. During the work on the project, change orders were required and agreed upon, adding additional amounts to the original contract amount. To the City's surprise, after completion of the job the contractor made an additional claim for yet extra compensation. The jury awarded the contractor an additional $2.1 million under the "total cost recovery" from a breach of contact and contact "abandonment" doctrines, legal theories allowing compensation in the absence of contracts which are not ordinarily applied to public entities. The same basic issues require review by the Supreme Court as raised before the Court of Appeal. If the appellate court's decision is allowed to stand contractors would not be bound by the contract PREPARED BY: ORRY P. KORB, TOWN ATTORNEY OPK:LMB/wp [N:'ATV\AmeIco.TCR.wpol Reviewed by: (' -KIanager Clerk Finance Community Development Rev: 5/25/01 1 Reformatt7/ 19i99 File# 301-05 & 704-15.86 PAGE 2 MAYOR AND TOWN COUNCIL SUBJECT: REQUEST FOR AMICUS PARTICIPATION IN AMELCO ELECTRIC v. CITY OF THOUSAND OAKS, SUPREME COURT CASE NO. S091069, 2ND CIVIL NO. B129406, AT NO COST TO THE TOWN May 25, 2001 price nor even by the agreed -upon amendments to the contract. Cities would be faced with uncertainty in contracts. They would be unable to effectively plan or budget, nor would they be able to maintain any control in providing public works projects at the lowest cost to the public as required by law. Attachments: Memo dated April 30, 2001 from Brown, Infield & Canzoneri Distribution: Nowland C. Hong, Brown, Winfield & Canzoneri, 300 South Hope Street, #1500, Los Angeles, CA 90071 BROWN , WI N FI ELD & CANZONERI INCORPORATED kv 300 SOUTH GRAND AVENUE. SUITE 1500 LOS ANGELES. CALIFORNIA 90071-3125 TELEPHONE (213) 687-2100 / TELECOPIER 687-2149 MEMORANDUM TO: ALL CALIFORNIA CITY ATTORNEYS FROM: NOWLAND C. HONG DATE: April 30, 2001 RE: RECEIED MAY 4 - 2001 TOWN A TTNv. JOINING IN THE AMICUS BRIEF IN SUPPORT OF THE CITY OF THOUSAND OAKS IN THE PETITION OF REVIEW GRANTED BY THE SUPREME COURT ON THE DECISION OF THE COURT OF APPEAL IN THE Amelco Electric v. City of Thousand Oaks, Supreme Court Case No. S091069; 2d Civil No. B129406: ISSUE: APPLICABILITY OF THE DOCTRINES OF: (1) "ABANDONMENT" TO A PUBLIC WORKS CONSTRUCTION CONTRACT; AND (2) "TOTAL COST RECOVERY" BY A CONSTRUCTION CONTRACTOR, ALLOWING THE RECOVERY OF ALL COSTS, PROFITS AND OVERHEAD INCURRED ON A JOB BEYOND THE AMOUNT SET IN THE CONTRACT We request your city's Amicus assistance by joining that brief (on a no -cost basis) regarding the Supreme Court's review of the Court of Appeal's opinion affirming a judgment against the City of Thousand Oaks for $2.1 million in additional compensation to a public works construction contractor. That judgment was based on "total cost recovery" from breach of contract and contract "abandonment" doctrines. These doctrines allow for the creation of an implied contract or quantum meruit recovery contrary to the holdings of Miller v. McKinnon (1942) 20 Ca1.2d 83 and South Bay Senior Housing Corp. v. City of Hawthorne (App. 2 Dist. 1997) 56 Cal.App.4th 1231. The League of California Cities' Legal Advocacy Committee has approved the preparation of an Amicus brief in this matter. Our firm will be preparing that Amicus brief. BRIEF DESCRIPTION OF CASE The plaintiff, Amelco Electric, was the low bidder for electrical work of the Thousand Oaks $64 million Civic Center project. Amelco's bid and contract were for $6.1 million. Perhaps, due to the limited construction activity at that time, the contractor aggressively bid the project on a low 81432.3 999100-0001 04/30/2001 - 3:13 pm Memorandum to ALL CALIFORNIA CITY ATTORNEYS April 30, 2001 Page 2 profit and no overhead basis. Pursuant to the written contract, progress payments were made and releases were obtained. However, after finishing the job, the contractor made, to the City's surprise, a "total cost recovery" claim for extra compensation in the amount of $1.7 million. The claim included monies to recover all of the contractor's costs, plus an amount for overhead and profit on the entire job. The claim was based on an alleged breach of the written construction contract, and also on the equitable theory of implied "abandonment" of that written contract. The City had 32 change orders on this large project. All change orders followed the formal and written process set forth in the Contract. These change orders added $1.1 million to the original contract amount, which represented only an 18% increase to the initial total contract. The contractor tracked other costs and impacts of City actions or changes to the project, but it did not do so concerning the alleged impacts due the City's breaches. Although a large sophisticated electrical contractor, it simply testified that due to the numerous sketches, record keeping of the actual impacts was too difficult. Thus, Amelco never established at trial a fixed cost impact or a direct causal relationship between any City action (be it the sketches or whatever) and its damages. Rather, they asked for a "total cost recovery", summarizing "they died of a thousand cuts" from handling these informational sketches. A $2.1 million dollar "total cost recovery" verdict was rendered by the jury against the City for both a breach of the written contract and for abandonment. The City then appealed the judgment entered against it. The Court of Appeal, Second Appellate District, Division Six affirmed the judgment. Thereafter, the City petitioned the Supreme Court for review which was granted. WHY THIS CASE MERITS CITY ATTENTION The same basic issues require review by the Supreme Court as were raised before the Court of Appeal. Therefore, the following reasons and issues are similar to that which was urged in our memorandum for the joining of your city in the League's amicus curie brief before the Court of Appeal. Cities have numerous limitations on their authority to contract, particularly public works contracts which must be awarded to the lowest responsive bidder. Under the abandonment theory, if tied to a cost recovery claim, the contractor is not bound by the contract price or the negotiated change orders, and the city becomes liable for any and all contractor inefficiencies (costs plus profit/overhead, or practically a blank check). That type of lawsuit is really a quantum meruit action, which the courts have traditionally denied against public entities. With limited public funds, a city should be able to reasonably budget for its public projects, relying on negotiated change orders and releases. A contractor should not be able to unilaterally determine the contract has been abandoned, 81432.3 999100-0001 04/30/2001 - 3:13 pm Memorandum to ALL CALIFORNIA CITY ATTORNEYS April 30, 2001 Page 3 thereby creating fiscal budgeting havoc. It is common place that in constructing a public project there will be some change in the work. If the public entities have an exposure to an abandonment claim where written change orders are agreed to, every contractor will be encouraged to make such indefinite claims. Keeping separate and accurate records of the actual costs to the contractor of any additional work or changes is the most reliable method of qualifying costs or damages. The "total cost" method negates the bargain both parties made. That doctrine should not be used to convert public contracts from a fixed price low bid arrangement to a cost plus contract. ISSUES OF AMICUS BRIEF 1. Abandonment. Abandonment of a written construction contract may be implied by the acts of the parties. Opdyke & Butler v. Benjamin Silver (1952) 111 Cal.App.2d 912. Abandonment has been justified because the scope of the work, when the contractor finally undertakes the actual work, greatly exceeded that called for under the original written contract. Daugherty v. Kimberly-Clark Corp. (1971) 14 Ca1.App.3d 151,156. However, no California abandonment case has been found where a public entity was the owner. Public works projects must be awarded to the lowest bidder and meet certain statutory requirements. Abandonment converts the written low bid contract to a quantum meruit recovery. In addition, both the City and the contractor must act in such a way as to abandon this contract, and there must be excessive changes. C. Norman Peterson Co. v. Container Corp. of America (1985) 172 Cal. App.3d 628. In Peterson the contractor had a "not to exceed" cost of $4,789,000 and for a project to be completed in 18 months. Shortly after the bid, both parties became aware that the initial drawings were inadequate. Thereafter, revised drawings were made but some were up to 14 months late, yet the project was completed on time. The contractor repeatedly complained about lack of revised drawings and their additional costs. The contract set forth a formal procedure for change orders. However, there were so many changes that the formal written change order process became an expedited oral process. The hundred plus change orders added $3,405,713 to the original contract of $4,789,000, a 71% increase. 2. No quantum meruit recovery against public entities. One who makes a contract with a public entity takes notice of those limitations on its power to contract. Morrison Homes Corp. v. City of Pleasanton (1976) 58 Cal.App.3d 724, 727. "And 81432.3 999100-0001 04/30/2001 - 3:13 pm Memorandum to ALL CALIFORNIA CITY ATTORNEYS April 30, 2001 Page 4 even though the person with whom the contract was made has supplied labor and materials in the performance of the contract and the public agency has received the benefits thereof, he has no right of action to recover in quantum meruit the reasonable value thereof." (Citations omitted) "The competitive bidding requirement is founded upon a salutary public policy declared by the legislature to protect the taxpayers from fraud, corruption, and carelessness on the part of public officials and the waste and dissipation of public funds." Miller v. 1 M. Mckinnon (1942) 20 Ca1.2d 83, 88. Generally, when a statute limits a city's power to make contracts to a certain prescribed method, impliedly prohibiting any other method, a contract that does not conform to that prescribed method is void and no implied liability can arise for benefits received by the city. A "total cost recovery" converts a fixed price low bid contract to a quantum meruit recovery, or the contract into a cost plus contract. 3. Total cost recovery disfavored. Because the total cost method does not require the contractor to break down and prove its costs or to link each extra cost item directly to the owner's actions, that method of damages should be a disfavored remedy. Total cost allows the low bid contractor to recover its entire costs incurred on the job, including added on profit and overhead. In Huber, Hunt & Nichols v. Moore (1977) 67 Ca1.App.3d 278, the court did not allow the inadequacies of the contractor's accounting system to alter the contractor's normal burden of proving causation between the owner's acts and the contractor's damages. 4. Unjustified betterment. A fundamental principle in contract damages is the court should place the nonbreaching party in the same position it would have been if the contract had been fully performed. Its goal is not to make a better contract or to create profit where none existed. When a contractor has aggressively bid the project on a low profit/no overhead basis, a verdict cannot include unexpected profit and overhead. STATUS AND JOINDER OR CONSENT Wendy Lascher of Lascher & Lascher (of Ventura, CA, Tel. No. 805-648-3228) is handling the City's appeal now filed with Supreme Court. Our Amicus brief is due on May 25, 2001. We therefore request those cities wishing to join the Amicus, to return the attached written consent form by May 18, 2001. Please specify how the name of the public entity or the City Attorney should be printed on the brief. 81432.3 999100-0001 04/30/2001 - 3:13 pm Memorandum to ALL CALIFORNIA CITY ATTORNEYS April 30, 2001 Page 5 Thank you for your support, DATED: April 30, 2001 cc: JoAnne Speers, League Staff Kara Ueda, Municipal Legal Fellow 81432.3 999100-0001 04/30/2001 - 3:13 pm BROWN, WINFIELD & CANZONERI, INC. By. Nowland C. Hong Town Council Minutes June 4, 2001 Redevelopment Agency Los Gatos, California PLANNING COMMISSION/PLANNING DEPARTMENT MONTHLY STATUS REPORT (07.38) Informational report regarding activity ofPlanning Commission and Department was received and filed. TREASURER'S REPORT (08.02) Informational report submitted by the Treasurer to the Council for the month ended April 30, 2001 was received and filed. AMICUS BRIEF/AMELCO ELECTRIC VS. CITY OF THOUSAND OAKS (09.28) Motion by Mr. Glickman, seconded by Mr. Blanton, that Council authorize the Town Attorney to include the Town of Los Gatos as an amicus curiae in the case of Amelco Electric vs. the City of Thousand Oaks, Supreme Court, case S091069, 2,d civil case B129406, at no cost to the Town. Carried unanimously. FARLEY ROAD 17435 & 17443/PLANNED DEVELOPMENT (11.15) Motion by Mr. Glickman, seconded by Mr. Blanton, that Council accept report in the form ofPlanning Commission minutes recommending approval of Development Application PD-99-1 and Negative Declaration ND-99-2. Carried unanimously. TERRENO DE FLORES 14950 & 14960/LOS GATOS BOULEVARD 14880 & 14890 PLANNED DEVELOPMENT (13.15) Motion by Mr. Glickman, seconded by Mr. Blanton, that Council accept report in the form ofPlanning Commission minutes recommending approval of Development Application PD-00-2 and Negative Declaration ND-00-3. Carried unanimously. PAVEMENT MANAGEMENT COOPERATIVE AGREEMENT/AMENDMENT 2 (15.33) 1996 MEASURE "B"/SANTA CLARA COUNTY TRANSPORTATION/RESOLUTION 2001-54 Motion by Mr. Glickman, seconded by Mr. Blanton, that Council adopt Resolution 2001-54 entitled, RESOLUTION OF THE TOWN OF LOS GATOS AUTHORIZING THE TOWN MANAGER TO EXECUTE AMENDMENT #2 TO THE 1996 MEASURE "B" PAVEMENT MANAGEMENT PROGRAM COOPERATIVE AGREEMENT. Carried unanimously. BRUSH/HAZARDOUS VEGETATION ABATEMENT/RESOLUTION 2001-55 (16.33) Motion by Mr. Glickman, seconded by Mr. Blanton, that Council adopt Resolution 2001-55 entitled, RESOLUTION OF THE TOWN OF LOS GATOS DECLARING HAZARDOUS VEGETATION (BRUSH) A PUBLIC NUISANCE AND PROVIDING FOR ABATEMENT. Carried unanimously. VERDE COURT/TRACT 9153/RESOLUTION 2001-56 (17.25&15) Motion by Mr. Glickman, seconded by Mr. Blanton, that Council adopt Resolution 2001-56 entitled, RESOLUTION OF THE TOWN OF LOS GATOS ACCEPTING WORK OF PINN BROTHERS CONSTRUCTION AND AUTHORIZING THE TOWN MANAGER TO EXECUTE CERTIFICATE OF ACCEPTANCE AND NOTICE OF COMPLETION FOR RECORDING BY THE TOWN CLERK. Carried unanimously. ANNEX/BLOSSOM HILL ROAD #22/BLOSSOM HILL 15651/RESOLUTION 2001-57 (18.14) Motion by Mr. Glickman, seconded by Mr. Blanton, that Council adopt Resolution 2001-57 entitled, RESOLUTION OF THE TOWN OF LOS GATOS ORDERING THE REORGANIZATION OF CERTAIN UNINHABITED TERRITORY DESIGNATED AS BLOSSOM HILL ROAD #22 TO THE TOWN OF LOS GATOS. Carried unanimously. TC:D13:MM060401 2