Attachment 2Tentative Schedule for RHNA 6
Housing Element Due Date-- This date is 18 months after adoption of the next RTP, provided the deadline for adoption is
no more than eight years later than the deadline for adoption of the previous eight -year housing element. The next RTP
adoption should occur in July 2021, with the Housing Element Due Date of January 31, 2023.
Key Milestones*
The timeframes relate to the Housing Element Due Date of January 31, 2023.
Timeframe
Milestone
Gov't Code Citation
At least 32 months prior
COG can request use of the population/household forecast from RTP for RHND
65584.02(a)(2)
At least 28 months prior
Subregions form
65584.03(a)
At least 26 months prior
Receive RHND from HCD if there are subregions
65584.02(a)(1)
At least 25 months prior
COG has to determine subregional shares
65584.03(c)
At least 24 months prior
COG/subregion shall develop a proposed methodology
65584.04(a)
At least 18 months prior
COG/subregion distributes draft RHNA
65584.05(a)
At least 12 months prior
COG/subregion adopts final RHNA
65584(b)
*This schedule assumes that there are subregions.
Tentative 2023-2031 RHNA / SCS Schedule
Key Milestones
Schedule/Timeframe
1
Subregions Form
No later than Sept. 2020'
2
Dept. of Housing and Community Development (HCD) Issues RHND
No later than Nov. 20202
3
Release Preliminary Draft RHNA Method
No later than Mar. 20203
4
ABAG Assigns Subregional Shares
No later than Dec. 20204
5
ABAG/Subregion surveys member jurisdictions on RHNA factors
Within 6 mos before draft method releases
6
ABAG/Subregion Releases Draft Method
No later than Jan. 20216
7
ABAG/Subregion Adopts Final Method
After 60-day comment period on draft method'
8
ABAG/Subregion Releases Draft Allocation
No later than July 2021s
9
Deadline for Local Requests for Revisions to Draft Allocation
After 60-day comment period on draft allocation9
10
ABAG/Subregion Responds to Requests for Revisions
Within 60 days after deadline for revision requests10
11
Deadline for Local Appeals to Draft Allocation
After responding to revision requests"
12
ABAG/Subregion Public Hearing on Local Appeals
Within 60 days after deadline to file appeals12
13
Deadline for Subregions to Submit Final Allocation and Resolution of
Consistency with SCS to ABAG for Review and Possible Consultation
Generally 6-8 weeks prior to ABAG deadline for issuing
Final Allocation13
14
ABAG Issues Final Allocation
Within 45 days after end of 60-day appeal period14
15
Public Hearing and Adoption of Final RHNA Allocation
No later than Jan. 202215
16
Local Governments Adopt Housing Element Revision
Jan. 31, 202316
GC §65584.03(a)
GC §65584.02(a)(1)
GC §65584.04(a)
° GC §65584.03(c)
GC §65584.04(d)
6 GC §65584.04. ABAG/Subregion must conduct at least one public hearing to receive comments on proposed methodology and
allow 60-day comment period prior to adopting final method.
GC §65584.04(h)
e GC §65584.05(a)
GC §65584.05(b)
10 GC §65584.05(h) ABAG has up to 60 days to respond to requests for revisions, may be compressed.
11 No specific guidance in statute.
11 GC 565584.05 e A hearingmust takeplace no earlier than 40 days and no more than 45 days after the deadline to file appeals.
) Y Y
13 Deadline set by ABAG.
14 GC 565584.05(f)
15
GC 565584.05(h) Must occur within 45 days of issuance of final allocation. No minimum interval required.
16 GC 565588(e) Deadline is 18 months after adoption of the RTP.
Prepared by ABAG Staff
February 9, 2017