Loading...
Almond Grove Presentation APPROVE PLANS/SPECS AND AUTHORIZE BIDDING OF ALMOND GROVE PHASE II PROJECT Town Council Meeting February 21, 2017 Sept. 6, 2016 Council Mtg. Confirmed:  Design basis  Changing asphalt sections to concrete  Bid all 8 streets together Dec. 20, 2016 Council Update  Tree Replacements  Ramps  Utility Upgrades/Project Schedule RECENT COUNCIL ACTIONS/MEETINGS Utilities Need Work Schedule Contractor Propose/Town Approve Schedule Start on Streets w/No Utility Upgrades Maintain N/S and E/W Connection 2 – 3 Streets per year Fully Complete in 3 Years A L M O N D G R O V E P H A S E I I P R O J E C T UTILITY UPGRADES/PROJECT SCHEDULE 3 Street Specific - Trees 3 Street Specific – Design Mailings/Door hangers NextDoor postings Website w/up -to -date information E -mail/Text notifications Notify Me One -On-One Discussions RESIDENT OUTREACH A L M O N D G R O V E P H A S E I I P R O J E C T A L M O N D G R O V E P H A S E I I P R O J E C T PROJECT COST ESTIMATING Council Approve PSE/Bidding - Feb. 21, 2017 Council Award of Bid – April 4, 2017 Construction Start (1 st Yr) – May 2017 Const. Closeout(1 st Yr) – Dec. 2017 A L M O N D G R O V E P H A S E I I P R O J E C T NEXT STEPS A L M O N D G R O V E P H A S E I I P R O J E C T RECOMMENDATION •Approve Plans/Specs and Authorize Bidding of the Almond Grove Phase II Project